SlideShare una empresa de Scribd logo
1 de 10
Analysis and Mitigation of Shunt Capacitor Bank Switching
Transients on 132 kV Grid Station, Qasimabad Hyderabad
SUNNY KATYARA*, ASHFAQUE AHMED HASHMANI**, AND BHAWANI SHANKAR CHOWDHRY***
RECEIVED ON 1811.2014 ACCEPTED ON 17.03.2015
ABSTRACT
In this paper analysis and mitigation methods of capacitor bank switching transients on 132KV Grid
station,QasimabadHyderabadaresimulatedthroughtheMATLABsoftware(MatrixLaboratory).Analysis
oftransientswithandwithoutcapacitorbankismade.Mathematicalmeasurementsofquantitiessuchas
transient voltages and inrush currents for each case are discussed. Reasons for these transients, their
impact on utility and customer systems and their mitigation are provided.
KeyWords: CapacitorBanks,SwitchingTransients,CapacitorInrushCurrent,Pre-InsertionResistor,
Current Limiting Reactor, SurgeArrestor, MATLAB.
* Post-Graduate Student, ** Professor, and *** Meritorious Professor,
Institute of Information & Communication Technologies, Mehran University of Engineering & Technology, Jamshoro
1. INTRODUCTION
energy from network instead of supplying. Hence severe
transients will take place when uncharged capacitor is being
switched on to network at peak voltage. The system voltage
will shoot up by the magnitude equal to the difference
between the system voltage and the voltage of capacitor
bank when a charged capacitor is switched on [3-4].
Theoretically, it has been observed that these transients
would lead to peak amplitude of 2 pu (per unit) but due to
inherent damping present in circuit, these transients are
limited below this value. The initial peak of transients
usually during sub-transient period is the most dangerous
one [5]. However effects of these transients are not
damaging enough to cause failure of line equipments, but
can act as catalyst to affect the most sensitive equipments
of the system and may produce un-necessary tripping of
equipments [6].
In this paper we are presenting Simulink analysis and
mitigation of capacitor switching transients on the
Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821]
1
I
n power system, transients have bad impact on its
reliability and may cause damage to or malfunctioning
of major equipments. The source of these transients
may be switching operations, lightning strikes or failure
of equipment. When shunt capacitor bank is to be switched
on live network, high frequency and high magnitude
transients may occur. Usually capacitor banks are installed
at feeder circuit to improve power factor and voltage
profile. Normally, these capacitor banks are not connected
all the time but switched on and off many times during the
day because the load on power system changing with
time according to certain load curves. These switching
actions will be accompanied by transient currents, when
a capacitor bank is closed on energized circuit [1].
Actually switching of capacitors produces more severe
transients as compared to energisation of load or cable
[2]. When an uncharged capacitor is switched on to
network, the system voltage will reduce, as it starts taking
Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821]
2
Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad
distribution feeder connected to 40 MVA transformer at
132 kV grid station Qasimabad Hyderabad. Capacitor
banks are placed before feeder circuit and initially
energized at peak voltage of the circuit at grid station and
transients in current and voltage near the bank are
analyzed. Now in order to remove these transients different
mitigation techniques are to be adopted and there results
have been included too in this paper and finally comparison
is made on techniques that which is most efficient one.
2. BASIC CONCEPT CONCERNING
ENERGIZATION OFCAPACITORS
Fig. 1 represents distribution network which provides
conceptual introduction about the capacitor switching
transients. R1
and L1
represent the resistance and
inductance of source. As shown in Fig. 1 capacitors C1
and C2
are fed by circuit breaker CB4
. S1
and S2
represent
switches used to take in and out the capacitors C1
and C2
.
Inductance of feeder between C1
and C2
is represented by
LB.
Total impedance of feeder and distribution transformer
is represented by the combination of R2
and L2
. Circuit
breaker CB3
is used here to interrupt the ground fault at
some distance on the feeder.
When switches S1
and S2
close at any instant to energize
capacitors, voltage at feeder to which CB4
is connected
collapses to the voltage on the capacitors and produce
oscillations. When these oscillations are damped out,
feeder voltage would return to its normal value again. But
if the capacitors are energized at peak value of voltage,
which is typically about 1.5-1.8 pu of phase to ground
voltage, large transients with frequency in range of 300-
800 Hz are produced initially. The frequency of these
transients is determined by source inductance L1
and
capacitance of capacitors connected [2].
Actually capacitors are connected in the form of three
phase large banks and breaker closes all three phases of a
capacitor bank simultaneously, so voltage at one of the
phase is always at peak [6-7].
3. REDUCTION OF CAPACITOR
SWITCHINGTRANSIENTS
Many topologies and techniques are available to mitigate
transients such as; use of pre-insertion resistors, inrush
limiting reactors and surge arrester connected across the
capacitor bank. Each technique results in a different
manner to reduce the switching transients.
3.1 Current Limiting Reactors
Here reactor of suitable rating is used in series with the
capacitor bank. Due to use of this reactor the surge
impedance of the circuit increases and hence the peak of
inrush current is reduced. Since the inductor opposes the
change in current so current cannot change instantly,
therefore elevated frequency components of transient are
restricted and the effect of these inrush transients current
is condensed [2,7].
3.2 Pre-Insertion Resistors
In this method, switched resistors are used in series with
capacitor banks. Here the switch will introduce resistors
initially into network and then make contact with capacitor
bank. Due to the use of these resistors, overall losses in
the circuit are increased which facilitate to decrease the
peak value of transients in the voltage and current. The
time at which pre-insertion resistors are introduced into
circuit is about one fourth of supply frequency i.e. 50 Hz.
This helps to decrease the initial peak which is most
damaging one of transients [7].
FIG. 1. NETWORK USED TO ILLUSTRATE CAPACITOR
SWITCHING TRANSIENTS
Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821]
3
Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad
3.3 SurgeArrester
Gap type surge arresters with a series non-linear resistor
can be used along with capacitor bank to reduce higher
magnitude transient stresses. Gap in the arresters is set in
such a way that it remain non conducting at terminal
voltage but when transients energizes the gap, the
capacitor will discharge completely and energy is
dissipated through arrestor. However if gap less metal
oxide arresters are used then capacitor will not discharge
below terminal voltage [8-12].
4. NETWORK REPRESENTATION
4.1 Network Data
The network of 132 kV grid station Qasimabad, Hyderabad
shown in Fig. 2 includes two 132 kV sources, four different
MVA transformers, 25 feeders and four capacitor banks.
Here the analysis is made on one 132 kV source having a
three phase short circuit MVAlevel of 24.4 MVAwhich is
connected to 132/11.5 kV, 40MVAtransformer.Aload of 15
MVA at power factor of 0.87 lagging is simulated. The
typical values of circuit capacitance, resistance and
inductance are included in our MATLAB/Simulink model.
Forimprovingpowerfactorfrom0.87-0.93,capacitorbanks
of 1.211 MVAR have be installed at the grid station and
switching transients in the voltage and current were
analyzed then.
5. SIMULINK REPRESENTATION OF
SYSTEM
132 kV grid station Qasimabad, Hyderabad, is feed from
two 132 kV sources, one is from TPS (Thermal Power
Station), Jamshoro and other from Halla. Fig.3 represents
the Simulink model of 132 kV grid station Qasimabad
Hyderabad from 132 kV TPS, Jamshoro source to
Cumulative load of 14 feeders. With the help of sim power
system laboratory of MATLAB, the load is simulated as
lump sum three phase load of 14 feeders and transmission
network is simulated through pi-section with a transformer
of 40 MVA to step down voltage to 11 kV. Three phase
breaker which is externally controlled is connected to
capacitor bank on one side and to feeder circuit on other
side is also simulated.
FIG. 2. GRAPHICAL REPRESENTATION OF 132 KV GRID STATION QASIMABAD, HYDERABAD
Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821]
4
Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad
6. SIMULATIONS
6.1 Initial Scenario
The Simulink diagram is shown in Fig. 4. The capacitor
bank was introduced into network at 0.06 sec and taken
out at 0.08 sec. the phase A peaks at 0.06 on the feeder.
The transients in voltage and current on Phase-A are
analyzed as result of capacitor bank being switched. Fig. 5
depicts three phase voltage at the load side before and
after the capacitor bank was switched in.
FIG. 3. SIMULATION OF 132 KV GRID STATION QASIMABAD, HYDERABAD
FIG. 4. VOLTAGE NEAR THE CAPACITOR BANK WHEN ENERGIZED AT PEAK VOLTAGE OF PHASE-A
Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821]
5
Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad
When the capacitor bank is injected into system at the
peak voltage of Phase-A then it produces inrush current
with magnitude Imax =
1468 A. This inrush current has
transient nature and a frequency of magnitude as
determined by the system inductances and capacitor banks’
capacitances.
Our objective in this paper is to mitigate the transients in
voltages and currents to the normal base value. So the
use of current limiting reactors, pre-insertion resistors and
surge arrestors is precautionary.
6.2 SimulationsUsingtheCurrentLimiting
Reactors
Referring above simulation results:
Vmax
=15kV,Vnormal
=11kV
Vshoot
=(15-11)kV
I max
= 1468A, Inormal
= 763A
Ishoot
=(1468-763)
P.Fload
= 0.87
P.Fcorrected
= 0.93
P.Fdifference
= (0.93-0.87)
Ztotal
=
max
max
I
V
= 10.31 ohms (1)
Preactor
= Vshoot
* Ishoot
P.Funcorrected
= 169.2 Kvar (2)
The reactor of 169.2Kvar is used with the controlled
capacitor bank in order to reduce the inrush current to 763
A which is the normal value of current flowing.
When the capacitor is switched in at the peak value of
Phase-A voltage then system voltage suddenly shoots to
twice of base value. Behavior of capacitor bank switching
transients after being introduced into system along with
limiting reactor can be shown by Figs. 6-7.
By Increasing value of current limiting reactor the
magnitude of inrush current is limited to desired value,
approximately to half of the base value.
It is confirmed from above simulation results that by
increasing the surge impedance of system, the magnitude
of transients has reduced. Actually frequency of current
transients has been reduced to 0.587 KHz. This recovery
of base current and voltage quantities quantities near the
FIG. 5. CURRENT AT CAPACITOR BANKS WHEN ENERGIZED AT THE PEAK VOLTAGE OF PHASE-A
Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821]
6
Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad
capacitor bank can be observed from Figs.6-7. Fig. 6 shows
how Phase-A voltage shoots to 142% of base value and
then reduces to steady value after damping of transient
frequency.
6.3 Simulations using the Pre-Insertion
Resistors
Resistors would be connected in series with capacitor
bank to damp out the transients mainly in current [12].
Use of this method requires an additional circuit breaker
which closes at 0.068 sec of the supply frequency. This
breaker would take the resistor out of system after 0.08
sec of supply frequency, to avoid un-necessary power
loss. Fig. 8 represents that voltage transients due to
capacitor switching have been reduced approximately to
base value while some transients are again observed when
breaker opens at 0.08 sec, which are mitigated because
reactor was also out along with capacitor bank.
FIG. 6. VOLTAGE AT THE BANK WHEN CAPACITOR BANK ENERGIZED ALONG WITH THE CURRENT LIMITING REACTOR
FIG. 7. INRUSH CURRENT NEARBY VCB USING CURRENT LIMITING REACTOR
Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821]
7
Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad
By knowing the value of capacitance of capacitor bank
and current to be reduced, the value of resistor to be
connected can be found by Equation (3).
ohms
IwC
Vs
R 75.0
2
1
 (3)
This perphase resistance mitigates the maximum current
and voltage transients nearly at base value.
Fig. 9 illustrates that magnitude of inrush current has
reduced to 0.78kA; it is worthwhile to point out that
damping of transients is faster with resistors than with the
limiting reactors.
FIG. 8. VOLTAGE NEAR CAPACITOR BANK USING PRE-INSERTION RESISTOR
FIG. 9. CURRENT NEAR CAPACITOR BANK USING PRE-INSERTION RESISTOR
Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821]
8
Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad
Since, it can be viewed from the above Simulink results
that high frequency current transients were very closer
to one obtained during initial scenario. It is due to the
fact that circuit parameters L’s and C’s remained same.
The voltage shoots up to the magnitude of 131% of
base value and then returned back to original value
after the damping of high frequency transients. The
magnitude of transients obtained in this method is
less than that, obtained by using current limiting
reactors.
FIG. 10. VOLTAGE NEAR THE CAPACITOR BANK USING SURGE ARRESTOR
FIG. 11. CURRENT NEAR CAPACITOR BANK USING SURGE ARRESTOR
Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821]
9
Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad
6.4 Simulations using the SurgeArrester
Here gap less surge arresters are connected across the
capacitor bank either in phase to phase or phase to neutral
configuration. With their different position across the
capacitor bank, the best choice is the phase to ground
connection [7]. We have used this connection for
simulation with results shown in Figs. 10-11. The inrush
transient current across the switched capacitor bank is
limited to 0.783 kA.
7. CONCLUSION
In this paper characteristics of transients which
originated from utility capacitor bank switching, were
studied. The information obtained from the simulations
and results depicts that transients are produced in the
current and voltage when capacitor banks are taken into
the network along with feeder circuit. These transients’
peaks up to 1.5-1.8 pu of base value. Moreover, these
high frequency transients were found to be causing
malfunctioning of the sensitive devices used in network.
Therefore, three different techniques for the mitigation
of these transients have been analyzed. Among these
techniques the most promising one is pre insertion
resistor method, which reduces the transients to such a
value that they cause no serious threat to current sensitive
switch gears. Other techniques i.e. surge arrester and
current limiting reactor methods were also found to be
useful in the mitigation of current as well as voltage
transients, but at lesser rate. Still their effects were
noticeable and lasted for few milliseconds. When our
sole purpose is to mitigate capacitor switching transients,
the best option for medium voltage switch gears would
be pre-insertion resistor method. It has been observed
practically current limiting reactor technique is expensive
than other techniques. The most simple and less
expensive technique for high voltage switch gears would
be the surge arrestor technique.
ACKNOWLEDGEMENT
The authors are grateful to Mehran University of
Engineering & Technology, Jamshoro, Pakistan, for
providing necessary help and facility to perform this
research work.Additionally, the first author is thankful to
his Master Thesis Group Members, Institute of Information
& Communication Technologies, Mehran University of
Engineering & Technology Jamshoro, Pakistan, for their
support and cooperation.
REFERENCES
[1] Greenwood, A., “Electrical Transients in Power Systems”,
pp. 37-46, John Wiley & Sons, New York, USA, August,
1996.
[2] Ramasamy, N., “Power System Capacitors”, Taylor &
Francis Group, LLC, [ISBN: 0:1-57444-710-6],
pp. 23-27, USA, May, 2005.
[3] Van Der Sluis, L., “Transients in Power Systems”, John
Wiley & Sons, [ISBN:0-471-48639-6], pp. 13-18, USA,
August, 2001.
[4] Grebe, T.E., “Application of Distribution System
Capacitor Banks and their Impact on PowerQuality”,
IEEE Transactions on Industry Applications,
Volume 32, No. 3, pp. 714-719, October, 1996.
[5] Chun, L., “Initial Voltage Change on Capacitor
Switching”, IEEE Transactions on Power Delivery,
Volume 27, No. 1, January, 2012.
[6] Ali, S.A.W., “Capacitor Banks Switching Transient in
Power System”, Canada[ISSN: 1923-8460], Volume 2,
No. 2, pp. 62-73, July, 2011.
[7] Das, J.C., “Analysis and Control of Large Shunt Capacitor
Bank Switching Transient”, IEEE Transactions on
Industry Application, Volume 41, No. 6, pp. 1444-1451,
October, 2005.
[8] Chandwani, H., Upadhyay, C., Vahora, A., and Som, G.,
“Mitigation of Switching over Voltage by Application
of Surge Arrester on Capacitor Bank”, International
Journal of Electrical Engineering & Technology,
Volume 4, No. 2, pp. 37-45, March-April, 2013.
Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821]
10
Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad
[9] Iizarry-Silvestrini, M.F., Prepa, T.E., and Velez-
Sepulveda, P., “Mitigation of Back to Back Capacitor
Switching Transient on Distribution Circuit”,[ISSN:
62002], Volume 45, No. 31, November, 2001.
[10] Gebhardt, L., and Richter, B., “Surge Arrester Application
of MV-Capacitor Banks to Mitigate Problems of
Switching Restrikes”, CIRED Vienna, Volume6, No. 23,
pp. 21-24, May, 2005.
[11] Nafar, M., Gevork, B., and Niknam, G.T., “A Novel
Parameter Estimation Method for Metal Oxide Surge
Arrester Models”, International Journal of Electrical
Engineering & Technology, Volume 3, No. 1, pp. 69-78,
December, 2011.
[12] Upadhyay, C., and Chandwani, H., “Modeling of
Switching Effects &Its Mitigation Techniques on MV-
Capacitor Bank with VCB”, Conference on Power and
Energy Systems: Towards Sustainable Energy, pp. 4-6,
India, June, 2014.

Más contenido relacionado

La actualidad más candente

High Voltage Direct Current Transmission Systems 2Mark Materials
High Voltage Direct Current Transmission Systems 2Mark MaterialsHigh Voltage Direct Current Transmission Systems 2Mark Materials
High Voltage Direct Current Transmission Systems 2Mark Materials
Santhosh Kumar
 
FAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINE
FAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINEFAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINE
FAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINE
Dr. Babasaheb Ambedkar Technological University
 
Control and Analysis of VSC Based High Voltage DC Transmission
Control and Analysis of VSC Based High Voltage DC TransmissionControl and Analysis of VSC Based High Voltage DC Transmission
Control and Analysis of VSC Based High Voltage DC Transmission
ijsrd.com
 
Major Project, HVDC Thesis - Saurabh Saxena
Major Project, HVDC Thesis - Saurabh SaxenaMajor Project, HVDC Thesis - Saurabh Saxena
Major Project, HVDC Thesis - Saurabh Saxena
Saurabh Saxena
 
HVDC Thesis,2011EEE 079
HVDC Thesis,2011EEE 079HVDC Thesis,2011EEE 079
HVDC Thesis,2011EEE 079
Ahmed Aziz
 
A Three Phase D-STATCOM to Compensate AC and DC loads by using Fuzzy Logic DC...
A Three Phase D-STATCOM to Compensate AC and DC loads by using Fuzzy Logic DC...A Three Phase D-STATCOM to Compensate AC and DC loads by using Fuzzy Logic DC...
A Three Phase D-STATCOM to Compensate AC and DC loads by using Fuzzy Logic DC...
IJMTST Journal
 

La actualidad más candente (20)

RGPV EX7102 UNITIII
RGPV EX7102 UNITIIIRGPV EX7102 UNITIII
RGPV EX7102 UNITIII
 
RGPV EX7102 unit I
RGPV EX7102 unit IRGPV EX7102 unit I
RGPV EX7102 unit I
 
VSC BASED HVDC SYTEM DESIGN AND PROTECTION AGAINST OVER VOLTAGES
VSC BASED HVDC SYTEM DESIGN AND PROTECTION AGAINST OVER VOLTAGESVSC BASED HVDC SYTEM DESIGN AND PROTECTION AGAINST OVER VOLTAGES
VSC BASED HVDC SYTEM DESIGN AND PROTECTION AGAINST OVER VOLTAGES
 
Simplified analysis of graetz circuit copy - copy
Simplified analysis of graetz circuit   copy - copySimplified analysis of graetz circuit   copy - copy
Simplified analysis of graetz circuit copy - copy
 
Y04408126132
Y04408126132Y04408126132
Y04408126132
 
A High Performance PWM Voltage Source Inverter Used for VAR Compensation and ...
A High Performance PWM Voltage Source Inverter Used for VAR Compensation and ...A High Performance PWM Voltage Source Inverter Used for VAR Compensation and ...
A High Performance PWM Voltage Source Inverter Used for VAR Compensation and ...
 
Vsc based hvdc transmission
Vsc based hvdc transmissionVsc based hvdc transmission
Vsc based hvdc transmission
 
High Voltage Direct Current Transmission Systems 2Mark Materials
High Voltage Direct Current Transmission Systems 2Mark MaterialsHigh Voltage Direct Current Transmission Systems 2Mark Materials
High Voltage Direct Current Transmission Systems 2Mark Materials
 
IRJET - A Zero Voltage Switching Pulse Width Modulated Multilevel Buck Converter
IRJET - A Zero Voltage Switching Pulse Width Modulated Multilevel Buck ConverterIRJET - A Zero Voltage Switching Pulse Width Modulated Multilevel Buck Converter
IRJET - A Zero Voltage Switching Pulse Width Modulated Multilevel Buck Converter
 
Introduction
IntroductionIntroduction
Introduction
 
An Efficient High Gain DC-DC Converter for Automotive Applications
An Efficient High Gain DC-DC Converter for Automotive ApplicationsAn Efficient High Gain DC-DC Converter for Automotive Applications
An Efficient High Gain DC-DC Converter for Automotive Applications
 
Performance Investigation of a Monopolar HVDC Transmission System Feeding a ...
Performance Investigation of a Monopolar HVDC Transmission  System Feeding a ...Performance Investigation of a Monopolar HVDC Transmission  System Feeding a ...
Performance Investigation of a Monopolar HVDC Transmission System Feeding a ...
 
FAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINE
FAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINEFAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINE
FAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINE
 
Control and Analysis of VSC Based High Voltage DC Transmission
Control and Analysis of VSC Based High Voltage DC TransmissionControl and Analysis of VSC Based High Voltage DC Transmission
Control and Analysis of VSC Based High Voltage DC Transmission
 
Major Project, HVDC Thesis - Saurabh Saxena
Major Project, HVDC Thesis - Saurabh SaxenaMajor Project, HVDC Thesis - Saurabh Saxena
Major Project, HVDC Thesis - Saurabh Saxena
 
HVDC Thesis,2011EEE 079
HVDC Thesis,2011EEE 079HVDC Thesis,2011EEE 079
HVDC Thesis,2011EEE 079
 
A Three Phase D-STATCOM to Compensate AC and DC loads by using Fuzzy Logic DC...
A Three Phase D-STATCOM to Compensate AC and DC loads by using Fuzzy Logic DC...A Three Phase D-STATCOM to Compensate AC and DC loads by using Fuzzy Logic DC...
A Three Phase D-STATCOM to Compensate AC and DC loads by using Fuzzy Logic DC...
 
azadar_training
azadar_trainingazadar_training
azadar_training
 
Appropriate Switching State Selection to Avoid Sapacitor Imbalance in Five-Le...
Appropriate Switching State Selection to Avoid Sapacitor Imbalance in Five-Le...Appropriate Switching State Selection to Avoid Sapacitor Imbalance in Five-Le...
Appropriate Switching State Selection to Avoid Sapacitor Imbalance in Five-Le...
 
Power Factor Correction with Current Controlled Buck Converter for BLDC Motor...
Power Factor Correction with Current Controlled Buck Converter for BLDC Motor...Power Factor Correction with Current Controlled Buck Converter for BLDC Motor...
Power Factor Correction with Current Controlled Buck Converter for BLDC Motor...
 

Similar a Chapter 8 (synny katyara-ashfaq hashmani-bs chowdhry)(1)

Hardware Implementation of Solar Photovoltaic System based Half Bridge Series...
Hardware Implementation of Solar Photovoltaic System based Half Bridge Series...Hardware Implementation of Solar Photovoltaic System based Half Bridge Series...
Hardware Implementation of Solar Photovoltaic System based Half Bridge Series...
International Journal of Power Electronics and Drive Systems
 
Student_01_Ankit Kherodia_Nirma Univ_Ahmedabad
Student_01_Ankit Kherodia_Nirma Univ_AhmedabadStudent_01_Ankit Kherodia_Nirma Univ_Ahmedabad
Student_01_Ankit Kherodia_Nirma Univ_Ahmedabad
ankit kherodiya
 
Reactive Power Compensation in 132kv & 33kv Grid of Narsinghpur Area
Reactive Power Compensation in 132kv & 33kv Grid of Narsinghpur AreaReactive Power Compensation in 132kv & 33kv Grid of Narsinghpur Area
Reactive Power Compensation in 132kv & 33kv Grid of Narsinghpur Area
ijceronline
 
Comparative Application of Load Tap-Changing Transformer (LTCT) and Shunt Cap...
Comparative Application of Load Tap-Changing Transformer (LTCT) and Shunt Cap...Comparative Application of Load Tap-Changing Transformer (LTCT) and Shunt Cap...
Comparative Application of Load Tap-Changing Transformer (LTCT) and Shunt Cap...
International journal of scientific and technical research in engineering (IJSTRE)
 

Similar a Chapter 8 (synny katyara-ashfaq hashmani-bs chowdhry)(1) (20)

PV Cell Fed High Step-up DC-DC Converter for PMSM Drive Applications
PV Cell Fed High Step-up DC-DC Converter for PMSM Drive ApplicationsPV Cell Fed High Step-up DC-DC Converter for PMSM Drive Applications
PV Cell Fed High Step-up DC-DC Converter for PMSM Drive Applications
 
R01043105113
R01043105113R01043105113
R01043105113
 
Hardware Implementation of Solar Photovoltaic System based Half Bridge Series...
Hardware Implementation of Solar Photovoltaic System based Half Bridge Series...Hardware Implementation of Solar Photovoltaic System based Half Bridge Series...
Hardware Implementation of Solar Photovoltaic System based Half Bridge Series...
 
12 16134 paper 064 ijeecs(edit)
12 16134 paper 064 ijeecs(edit)12 16134 paper 064 ijeecs(edit)
12 16134 paper 064 ijeecs(edit)
 
Student_01_Ankit Kherodia_Nirma Univ_Ahmedabad
Student_01_Ankit Kherodia_Nirma Univ_AhmedabadStudent_01_Ankit Kherodia_Nirma Univ_Ahmedabad
Student_01_Ankit Kherodia_Nirma Univ_Ahmedabad
 
Reactive Power Compensation in 132kv & 33kv Grid of Narsinghpur Area
Reactive Power Compensation in 132kv & 33kv Grid of Narsinghpur AreaReactive Power Compensation in 132kv & 33kv Grid of Narsinghpur Area
Reactive Power Compensation in 132kv & 33kv Grid of Narsinghpur Area
 
ZVZCS Based High Frequency Link Grid Connected SVM Applied Three Phase Three ...
ZVZCS Based High Frequency Link Grid Connected SVM Applied Three Phase Three ...ZVZCS Based High Frequency Link Grid Connected SVM Applied Three Phase Three ...
ZVZCS Based High Frequency Link Grid Connected SVM Applied Three Phase Three ...
 
Comparative Application of Load Tap-Changing Transformer (LTCT) and Shunt Cap...
Comparative Application of Load Tap-Changing Transformer (LTCT) and Shunt Cap...Comparative Application of Load Tap-Changing Transformer (LTCT) and Shunt Cap...
Comparative Application of Load Tap-Changing Transformer (LTCT) and Shunt Cap...
 
HVDC System
HVDC SystemHVDC System
HVDC System
 
Power Quality Improvement using Passive shunt filters, TCR and TSC combination
Power Quality Improvement using Passive shunt filters, TCR and TSC combinationPower Quality Improvement using Passive shunt filters, TCR and TSC combination
Power Quality Improvement using Passive shunt filters, TCR and TSC combination
 
Thyristor switched capacitor
Thyristor switched capacitorThyristor switched capacitor
Thyristor switched capacitor
 
Control of parallel dc dc converters in a dc microgrid
Control of parallel dc dc converters in a dc microgridControl of parallel dc dc converters in a dc microgrid
Control of parallel dc dc converters in a dc microgrid
 
22 9151 transformer exchangingwithvacuum edit septian
22 9151 transformer exchangingwithvacuum edit septian22 9151 transformer exchangingwithvacuum edit septian
22 9151 transformer exchangingwithvacuum edit septian
 
A Modern Technique of Deduction in Leakage Current in Resonant Bi-directional...
A Modern Technique of Deduction in Leakage Current in Resonant Bi-directional...A Modern Technique of Deduction in Leakage Current in Resonant Bi-directional...
A Modern Technique of Deduction in Leakage Current in Resonant Bi-directional...
 
IRJET- Generation and Control of Transient Overvoltages in Power System Networks
IRJET- Generation and Control of Transient Overvoltages in Power System NetworksIRJET- Generation and Control of Transient Overvoltages in Power System Networks
IRJET- Generation and Control of Transient Overvoltages in Power System Networks
 
A DC-DC Converter with Ripple Current Cancellation Based On Duty Cycle Selection
A DC-DC Converter with Ripple Current Cancellation Based On Duty Cycle SelectionA DC-DC Converter with Ripple Current Cancellation Based On Duty Cycle Selection
A DC-DC Converter with Ripple Current Cancellation Based On Duty Cycle Selection
 
An Approach to Voltage Quality Enhancement by Introduction of CWVM for Distri...
An Approach to Voltage Quality Enhancement by Introduction of CWVM for Distri...An Approach to Voltage Quality Enhancement by Introduction of CWVM for Distri...
An Approach to Voltage Quality Enhancement by Introduction of CWVM for Distri...
 
E010623545
E010623545E010623545
E010623545
 
Single Phase Matrix Converter for Input Power Factor Improvement
Single Phase Matrix Converter for Input Power Factor ImprovementSingle Phase Matrix Converter for Input Power Factor Improvement
Single Phase Matrix Converter for Input Power Factor Improvement
 
International Refereed Journal of Engineering and Science (IRJES)
International Refereed Journal of Engineering and Science (IRJES)International Refereed Journal of Engineering and Science (IRJES)
International Refereed Journal of Engineering and Science (IRJES)
 

Último

Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 

Último (20)

University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 

Chapter 8 (synny katyara-ashfaq hashmani-bs chowdhry)(1)

  • 1. Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad SUNNY KATYARA*, ASHFAQUE AHMED HASHMANI**, AND BHAWANI SHANKAR CHOWDHRY*** RECEIVED ON 1811.2014 ACCEPTED ON 17.03.2015 ABSTRACT In this paper analysis and mitigation methods of capacitor bank switching transients on 132KV Grid station,QasimabadHyderabadaresimulatedthroughtheMATLABsoftware(MatrixLaboratory).Analysis oftransientswithandwithoutcapacitorbankismade.Mathematicalmeasurementsofquantitiessuchas transient voltages and inrush currents for each case are discussed. Reasons for these transients, their impact on utility and customer systems and their mitigation are provided. KeyWords: CapacitorBanks,SwitchingTransients,CapacitorInrushCurrent,Pre-InsertionResistor, Current Limiting Reactor, SurgeArrestor, MATLAB. * Post-Graduate Student, ** Professor, and *** Meritorious Professor, Institute of Information & Communication Technologies, Mehran University of Engineering & Technology, Jamshoro 1. INTRODUCTION energy from network instead of supplying. Hence severe transients will take place when uncharged capacitor is being switched on to network at peak voltage. The system voltage will shoot up by the magnitude equal to the difference between the system voltage and the voltage of capacitor bank when a charged capacitor is switched on [3-4]. Theoretically, it has been observed that these transients would lead to peak amplitude of 2 pu (per unit) but due to inherent damping present in circuit, these transients are limited below this value. The initial peak of transients usually during sub-transient period is the most dangerous one [5]. However effects of these transients are not damaging enough to cause failure of line equipments, but can act as catalyst to affect the most sensitive equipments of the system and may produce un-necessary tripping of equipments [6]. In this paper we are presenting Simulink analysis and mitigation of capacitor switching transients on the Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821] 1 I n power system, transients have bad impact on its reliability and may cause damage to or malfunctioning of major equipments. The source of these transients may be switching operations, lightning strikes or failure of equipment. When shunt capacitor bank is to be switched on live network, high frequency and high magnitude transients may occur. Usually capacitor banks are installed at feeder circuit to improve power factor and voltage profile. Normally, these capacitor banks are not connected all the time but switched on and off many times during the day because the load on power system changing with time according to certain load curves. These switching actions will be accompanied by transient currents, when a capacitor bank is closed on energized circuit [1]. Actually switching of capacitors produces more severe transients as compared to energisation of load or cable [2]. When an uncharged capacitor is switched on to network, the system voltage will reduce, as it starts taking
  • 2. Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821] 2 Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad distribution feeder connected to 40 MVA transformer at 132 kV grid station Qasimabad Hyderabad. Capacitor banks are placed before feeder circuit and initially energized at peak voltage of the circuit at grid station and transients in current and voltage near the bank are analyzed. Now in order to remove these transients different mitigation techniques are to be adopted and there results have been included too in this paper and finally comparison is made on techniques that which is most efficient one. 2. BASIC CONCEPT CONCERNING ENERGIZATION OFCAPACITORS Fig. 1 represents distribution network which provides conceptual introduction about the capacitor switching transients. R1 and L1 represent the resistance and inductance of source. As shown in Fig. 1 capacitors C1 and C2 are fed by circuit breaker CB4 . S1 and S2 represent switches used to take in and out the capacitors C1 and C2 . Inductance of feeder between C1 and C2 is represented by LB. Total impedance of feeder and distribution transformer is represented by the combination of R2 and L2 . Circuit breaker CB3 is used here to interrupt the ground fault at some distance on the feeder. When switches S1 and S2 close at any instant to energize capacitors, voltage at feeder to which CB4 is connected collapses to the voltage on the capacitors and produce oscillations. When these oscillations are damped out, feeder voltage would return to its normal value again. But if the capacitors are energized at peak value of voltage, which is typically about 1.5-1.8 pu of phase to ground voltage, large transients with frequency in range of 300- 800 Hz are produced initially. The frequency of these transients is determined by source inductance L1 and capacitance of capacitors connected [2]. Actually capacitors are connected in the form of three phase large banks and breaker closes all three phases of a capacitor bank simultaneously, so voltage at one of the phase is always at peak [6-7]. 3. REDUCTION OF CAPACITOR SWITCHINGTRANSIENTS Many topologies and techniques are available to mitigate transients such as; use of pre-insertion resistors, inrush limiting reactors and surge arrester connected across the capacitor bank. Each technique results in a different manner to reduce the switching transients. 3.1 Current Limiting Reactors Here reactor of suitable rating is used in series with the capacitor bank. Due to use of this reactor the surge impedance of the circuit increases and hence the peak of inrush current is reduced. Since the inductor opposes the change in current so current cannot change instantly, therefore elevated frequency components of transient are restricted and the effect of these inrush transients current is condensed [2,7]. 3.2 Pre-Insertion Resistors In this method, switched resistors are used in series with capacitor banks. Here the switch will introduce resistors initially into network and then make contact with capacitor bank. Due to the use of these resistors, overall losses in the circuit are increased which facilitate to decrease the peak value of transients in the voltage and current. The time at which pre-insertion resistors are introduced into circuit is about one fourth of supply frequency i.e. 50 Hz. This helps to decrease the initial peak which is most damaging one of transients [7]. FIG. 1. NETWORK USED TO ILLUSTRATE CAPACITOR SWITCHING TRANSIENTS
  • 3. Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821] 3 Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad 3.3 SurgeArrester Gap type surge arresters with a series non-linear resistor can be used along with capacitor bank to reduce higher magnitude transient stresses. Gap in the arresters is set in such a way that it remain non conducting at terminal voltage but when transients energizes the gap, the capacitor will discharge completely and energy is dissipated through arrestor. However if gap less metal oxide arresters are used then capacitor will not discharge below terminal voltage [8-12]. 4. NETWORK REPRESENTATION 4.1 Network Data The network of 132 kV grid station Qasimabad, Hyderabad shown in Fig. 2 includes two 132 kV sources, four different MVA transformers, 25 feeders and four capacitor banks. Here the analysis is made on one 132 kV source having a three phase short circuit MVAlevel of 24.4 MVAwhich is connected to 132/11.5 kV, 40MVAtransformer.Aload of 15 MVA at power factor of 0.87 lagging is simulated. The typical values of circuit capacitance, resistance and inductance are included in our MATLAB/Simulink model. Forimprovingpowerfactorfrom0.87-0.93,capacitorbanks of 1.211 MVAR have be installed at the grid station and switching transients in the voltage and current were analyzed then. 5. SIMULINK REPRESENTATION OF SYSTEM 132 kV grid station Qasimabad, Hyderabad, is feed from two 132 kV sources, one is from TPS (Thermal Power Station), Jamshoro and other from Halla. Fig.3 represents the Simulink model of 132 kV grid station Qasimabad Hyderabad from 132 kV TPS, Jamshoro source to Cumulative load of 14 feeders. With the help of sim power system laboratory of MATLAB, the load is simulated as lump sum three phase load of 14 feeders and transmission network is simulated through pi-section with a transformer of 40 MVA to step down voltage to 11 kV. Three phase breaker which is externally controlled is connected to capacitor bank on one side and to feeder circuit on other side is also simulated. FIG. 2. GRAPHICAL REPRESENTATION OF 132 KV GRID STATION QASIMABAD, HYDERABAD
  • 4. Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821] 4 Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad 6. SIMULATIONS 6.1 Initial Scenario The Simulink diagram is shown in Fig. 4. The capacitor bank was introduced into network at 0.06 sec and taken out at 0.08 sec. the phase A peaks at 0.06 on the feeder. The transients in voltage and current on Phase-A are analyzed as result of capacitor bank being switched. Fig. 5 depicts three phase voltage at the load side before and after the capacitor bank was switched in. FIG. 3. SIMULATION OF 132 KV GRID STATION QASIMABAD, HYDERABAD FIG. 4. VOLTAGE NEAR THE CAPACITOR BANK WHEN ENERGIZED AT PEAK VOLTAGE OF PHASE-A
  • 5. Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821] 5 Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad When the capacitor bank is injected into system at the peak voltage of Phase-A then it produces inrush current with magnitude Imax = 1468 A. This inrush current has transient nature and a frequency of magnitude as determined by the system inductances and capacitor banks’ capacitances. Our objective in this paper is to mitigate the transients in voltages and currents to the normal base value. So the use of current limiting reactors, pre-insertion resistors and surge arrestors is precautionary. 6.2 SimulationsUsingtheCurrentLimiting Reactors Referring above simulation results: Vmax =15kV,Vnormal =11kV Vshoot =(15-11)kV I max = 1468A, Inormal = 763A Ishoot =(1468-763) P.Fload = 0.87 P.Fcorrected = 0.93 P.Fdifference = (0.93-0.87) Ztotal = max max I V = 10.31 ohms (1) Preactor = Vshoot * Ishoot P.Funcorrected = 169.2 Kvar (2) The reactor of 169.2Kvar is used with the controlled capacitor bank in order to reduce the inrush current to 763 A which is the normal value of current flowing. When the capacitor is switched in at the peak value of Phase-A voltage then system voltage suddenly shoots to twice of base value. Behavior of capacitor bank switching transients after being introduced into system along with limiting reactor can be shown by Figs. 6-7. By Increasing value of current limiting reactor the magnitude of inrush current is limited to desired value, approximately to half of the base value. It is confirmed from above simulation results that by increasing the surge impedance of system, the magnitude of transients has reduced. Actually frequency of current transients has been reduced to 0.587 KHz. This recovery of base current and voltage quantities quantities near the FIG. 5. CURRENT AT CAPACITOR BANKS WHEN ENERGIZED AT THE PEAK VOLTAGE OF PHASE-A
  • 6. Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821] 6 Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad capacitor bank can be observed from Figs.6-7. Fig. 6 shows how Phase-A voltage shoots to 142% of base value and then reduces to steady value after damping of transient frequency. 6.3 Simulations using the Pre-Insertion Resistors Resistors would be connected in series with capacitor bank to damp out the transients mainly in current [12]. Use of this method requires an additional circuit breaker which closes at 0.068 sec of the supply frequency. This breaker would take the resistor out of system after 0.08 sec of supply frequency, to avoid un-necessary power loss. Fig. 8 represents that voltage transients due to capacitor switching have been reduced approximately to base value while some transients are again observed when breaker opens at 0.08 sec, which are mitigated because reactor was also out along with capacitor bank. FIG. 6. VOLTAGE AT THE BANK WHEN CAPACITOR BANK ENERGIZED ALONG WITH THE CURRENT LIMITING REACTOR FIG. 7. INRUSH CURRENT NEARBY VCB USING CURRENT LIMITING REACTOR
  • 7. Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821] 7 Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad By knowing the value of capacitance of capacitor bank and current to be reduced, the value of resistor to be connected can be found by Equation (3). ohms IwC Vs R 75.0 2 1  (3) This perphase resistance mitigates the maximum current and voltage transients nearly at base value. Fig. 9 illustrates that magnitude of inrush current has reduced to 0.78kA; it is worthwhile to point out that damping of transients is faster with resistors than with the limiting reactors. FIG. 8. VOLTAGE NEAR CAPACITOR BANK USING PRE-INSERTION RESISTOR FIG. 9. CURRENT NEAR CAPACITOR BANK USING PRE-INSERTION RESISTOR
  • 8. Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821] 8 Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad Since, it can be viewed from the above Simulink results that high frequency current transients were very closer to one obtained during initial scenario. It is due to the fact that circuit parameters L’s and C’s remained same. The voltage shoots up to the magnitude of 131% of base value and then returned back to original value after the damping of high frequency transients. The magnitude of transients obtained in this method is less than that, obtained by using current limiting reactors. FIG. 10. VOLTAGE NEAR THE CAPACITOR BANK USING SURGE ARRESTOR FIG. 11. CURRENT NEAR CAPACITOR BANK USING SURGE ARRESTOR
  • 9. Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821] 9 Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad 6.4 Simulations using the SurgeArrester Here gap less surge arresters are connected across the capacitor bank either in phase to phase or phase to neutral configuration. With their different position across the capacitor bank, the best choice is the phase to ground connection [7]. We have used this connection for simulation with results shown in Figs. 10-11. The inrush transient current across the switched capacitor bank is limited to 0.783 kA. 7. CONCLUSION In this paper characteristics of transients which originated from utility capacitor bank switching, were studied. The information obtained from the simulations and results depicts that transients are produced in the current and voltage when capacitor banks are taken into the network along with feeder circuit. These transients’ peaks up to 1.5-1.8 pu of base value. Moreover, these high frequency transients were found to be causing malfunctioning of the sensitive devices used in network. Therefore, three different techniques for the mitigation of these transients have been analyzed. Among these techniques the most promising one is pre insertion resistor method, which reduces the transients to such a value that they cause no serious threat to current sensitive switch gears. Other techniques i.e. surge arrester and current limiting reactor methods were also found to be useful in the mitigation of current as well as voltage transients, but at lesser rate. Still their effects were noticeable and lasted for few milliseconds. When our sole purpose is to mitigate capacitor switching transients, the best option for medium voltage switch gears would be pre-insertion resistor method. It has been observed practically current limiting reactor technique is expensive than other techniques. The most simple and less expensive technique for high voltage switch gears would be the surge arrestor technique. ACKNOWLEDGEMENT The authors are grateful to Mehran University of Engineering & Technology, Jamshoro, Pakistan, for providing necessary help and facility to perform this research work.Additionally, the first author is thankful to his Master Thesis Group Members, Institute of Information & Communication Technologies, Mehran University of Engineering & Technology Jamshoro, Pakistan, for their support and cooperation. REFERENCES [1] Greenwood, A., “Electrical Transients in Power Systems”, pp. 37-46, John Wiley & Sons, New York, USA, August, 1996. [2] Ramasamy, N., “Power System Capacitors”, Taylor & Francis Group, LLC, [ISBN: 0:1-57444-710-6], pp. 23-27, USA, May, 2005. [3] Van Der Sluis, L., “Transients in Power Systems”, John Wiley & Sons, [ISBN:0-471-48639-6], pp. 13-18, USA, August, 2001. [4] Grebe, T.E., “Application of Distribution System Capacitor Banks and their Impact on PowerQuality”, IEEE Transactions on Industry Applications, Volume 32, No. 3, pp. 714-719, October, 1996. [5] Chun, L., “Initial Voltage Change on Capacitor Switching”, IEEE Transactions on Power Delivery, Volume 27, No. 1, January, 2012. [6] Ali, S.A.W., “Capacitor Banks Switching Transient in Power System”, Canada[ISSN: 1923-8460], Volume 2, No. 2, pp. 62-73, July, 2011. [7] Das, J.C., “Analysis and Control of Large Shunt Capacitor Bank Switching Transient”, IEEE Transactions on Industry Application, Volume 41, No. 6, pp. 1444-1451, October, 2005. [8] Chandwani, H., Upadhyay, C., Vahora, A., and Som, G., “Mitigation of Switching over Voltage by Application of Surge Arrester on Capacitor Bank”, International Journal of Electrical Engineering & Technology, Volume 4, No. 2, pp. 37-45, March-April, 2013.
  • 10. Mehran University Research Journal of Engineering & Technology, Volume 34, No. 3, July, 2015 [ISSN 0254-7821] 10 Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kV Grid Station, Qasimabad Hyderabad [9] Iizarry-Silvestrini, M.F., Prepa, T.E., and Velez- Sepulveda, P., “Mitigation of Back to Back Capacitor Switching Transient on Distribution Circuit”,[ISSN: 62002], Volume 45, No. 31, November, 2001. [10] Gebhardt, L., and Richter, B., “Surge Arrester Application of MV-Capacitor Banks to Mitigate Problems of Switching Restrikes”, CIRED Vienna, Volume6, No. 23, pp. 21-24, May, 2005. [11] Nafar, M., Gevork, B., and Niknam, G.T., “A Novel Parameter Estimation Method for Metal Oxide Surge Arrester Models”, International Journal of Electrical Engineering & Technology, Volume 3, No. 1, pp. 69-78, December, 2011. [12] Upadhyay, C., and Chandwani, H., “Modeling of Switching Effects &Its Mitigation Techniques on MV- Capacitor Bank with VCB”, Conference on Power and Energy Systems: Towards Sustainable Energy, pp. 4-6, India, June, 2014.