Enviar búsqueda
Cargar
Earned value management in action - A Webinar by Vivek Prakash, pmwares
•
4 recomendaciones
•
3,446 vistas
Vivek Prakash
Seguir
Empresariales
Tecnología
Denunciar
Compartir
Denunciar
Compartir
1 de 14
Descargar ahora
Descargar para leer sin conexión
Recomendados
Controller area network
Controller area network
Divi1597
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
TecnicoItca
Earned value analysis
Earned value analysis
Nikhil Raj
ELECTRICAL ENGINEER CV M
ELECTRICAL ENGINEER CV M
usama gamal
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
Chris Carson
Historical pipeline cost analysis
Historical pipeline cost analysis
zhenhuarui
MEP engineer CV
MEP engineer CV
Khalid Wdn
Earned value
Earned value
Oliver
Recomendados
Controller area network
Controller area network
Divi1597
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
TecnicoItca
Earned value analysis
Earned value analysis
Nikhil Raj
ELECTRICAL ENGINEER CV M
ELECTRICAL ENGINEER CV M
usama gamal
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
Chris Carson
Historical pipeline cost analysis
Historical pipeline cost analysis
zhenhuarui
MEP engineer CV
MEP engineer CV
Khalid Wdn
Earned value
Earned value
Oliver
Earned Value Analysis - EVA
Earned Value Analysis - EVA
Ahmed Bamasdoos
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
Planisware
Django10 cheat-sheet-grayscale
Django10 cheat-sheet-grayscale
Amir Reza Zareian
Earned Value Management Essentials
Earned Value Management Essentials
Glen Alleman
Executive Overview of Managing Agile Programs with Earned Value
Executive Overview of Managing Agile Programs with Earned Value
Glen Alleman
EVMS Made Simple
EVMS Made Simple
Glen Alleman
Jerald kerby
Jerald kerby
NASAPMC
Learning Earned Value Management using Lego Bricks
Learning Earned Value Management using Lego Bricks
Youssef Mourra
Earned Value Management
Earned Value Management
Tiago Franco
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Tipsographic . com
EVA/EVM
EVA/EVM
Anderson Cezar de Menezes
Earned Value fundamentals
Earned Value fundamentals
Denise Fotopoulou
Earned Value Management - Foundation
Earned Value Management - Foundation
Mirosław Dąbrowski C-level IT manager, CEO, Agile, ICF Coach, Speaker
Earned value management
Earned value management
Ashif AR
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
Waleed Elbasyouni ,PgMP®,P3O®,PMP®,RMP®,KPI-P®,APMG-CH®,TOT®,SSYB™
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
Association for Project Management
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMP
JustAcademy
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
Glen Alleman
Earned Value Management
Earned Value Management
Russell Taylor BEng CEng FAPM FIET
Earning Value from Earned Value Management
Earning Value from Earned Value Management
Glen Alleman
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
Nabeel Ahmad
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
Baroness PM
Más contenido relacionado
Destacado
Earned Value Analysis - EVA
Earned Value Analysis - EVA
Ahmed Bamasdoos
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
Planisware
Django10 cheat-sheet-grayscale
Django10 cheat-sheet-grayscale
Amir Reza Zareian
Earned Value Management Essentials
Earned Value Management Essentials
Glen Alleman
Executive Overview of Managing Agile Programs with Earned Value
Executive Overview of Managing Agile Programs with Earned Value
Glen Alleman
EVMS Made Simple
EVMS Made Simple
Glen Alleman
Jerald kerby
Jerald kerby
NASAPMC
Learning Earned Value Management using Lego Bricks
Learning Earned Value Management using Lego Bricks
Youssef Mourra
Earned Value Management
Earned Value Management
Tiago Franco
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Tipsographic . com
EVA/EVM
EVA/EVM
Anderson Cezar de Menezes
Earned Value fundamentals
Earned Value fundamentals
Denise Fotopoulou
Earned Value Management - Foundation
Earned Value Management - Foundation
Mirosław Dąbrowski C-level IT manager, CEO, Agile, ICF Coach, Speaker
Earned value management
Earned value management
Ashif AR
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
Waleed Elbasyouni ,PgMP®,P3O®,PMP®,RMP®,KPI-P®,APMG-CH®,TOT®,SSYB™
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
Association for Project Management
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMP
JustAcademy
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
Glen Alleman
Earned Value Management
Earned Value Management
Russell Taylor BEng CEng FAPM FIET
Earning Value from Earned Value Management
Earning Value from Earned Value Management
Glen Alleman
Destacado
(20)
Earned Value Analysis - EVA
Earned Value Analysis - EVA
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
Django10 cheat-sheet-grayscale
Django10 cheat-sheet-grayscale
Earned Value Management Essentials
Earned Value Management Essentials
Executive Overview of Managing Agile Programs with Earned Value
Executive Overview of Managing Agile Programs with Earned Value
EVMS Made Simple
EVMS Made Simple
Jerald kerby
Jerald kerby
Learning Earned Value Management using Lego Bricks
Learning Earned Value Management using Lego Bricks
Earned Value Management
Earned Value Management
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
EVA/EVM
EVA/EVM
Earned Value fundamentals
Earned Value fundamentals
Earned Value Management - Foundation
Earned Value Management - Foundation
Earned value management
Earned value management
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMP
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
Earned Value Management
Earned Value Management
Earning Value from Earned Value Management
Earning Value from Earned Value Management
Similar a Earned value management in action - A Webinar by Vivek Prakash, pmwares
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
Nabeel Ahmad
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
Baroness PM
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
RedhaElhuni
Evm.calculations.Summary sheet
Evm.calculations.Summary sheet
Essam Lotffy, PMP®, CCP®
Project Cost Management
Project Cost Management
Serdar Temiz
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
Najm Naqvi
Earned Value Analysis
Earned Value Analysis
Ahmed Rami Elsherif, PMP, ITBMC
Earned Value Management
Earned Value Management
Matt Stehling
PMP COST FORMULAE
PMP COST FORMULAE
Bhaskara Reddy Sannapureddy
Formulas for pmp exam
Formulas for pmp exam
Ibrahem Faheem
Earned Value Management Project Analysis
Earned Value Management Project Analysis
Roger H. Mandel
Ms Project 2007(advanced)
Ms Project 2007(advanced)
Dinesh Singh
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
S-Curve Presentation- 20130529
S-Curve Presentation- 20130529
James Zhang (Chi, Zhang)
Evm Basics
Evm Basics
gfbreaux
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
ProPM Academy
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
ProfDrAnbalaganChinn
Project Health.doc
Project Health.doc
Patricia Benedict, PMP
Earned value analysis - presentation
Earned value analysis - presentation
ProPM Academy
PMP Training - 07 project cost management
PMP Training - 07 project cost management
ejlp12
Similar a Earned value management in action - A Webinar by Vivek Prakash, pmwares
(20)
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
Evm.calculations.Summary sheet
Evm.calculations.Summary sheet
Project Cost Management
Project Cost Management
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
Earned Value Analysis
Earned Value Analysis
Earned Value Management
Earned Value Management
PMP COST FORMULAE
PMP COST FORMULAE
Formulas for pmp exam
Formulas for pmp exam
Earned Value Management Project Analysis
Earned Value Management Project Analysis
Ms Project 2007(advanced)
Ms Project 2007(advanced)
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
S-Curve Presentation- 20130529
S-Curve Presentation- 20130529
Evm Basics
Evm Basics
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
Project Health.doc
Project Health.doc
Earned value analysis - presentation
Earned value analysis - presentation
PMP Training - 07 project cost management
PMP Training - 07 project cost management
Último
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
lizamodels9
Eluru Call Girls Service ☎ ️93326-06886 ❤️🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️🔥 Enjoy 24/7 Escort Service
Damini Dixit
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
dlhescort
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
dlhescort
Phases of Negotiation .pptx
Phases of Negotiation .pptx
nandhinijagan9867
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Admir Softic
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
rwgiffor
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Sheetaleventcompany
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
uneakwhite
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon investment
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
lizamodels9
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
rajveerescorts2022
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
P&CO
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
allensay1
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Damini Dixit
Último
(20)
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Eluru Call Girls Service ☎ ️93326-06886 ❤️🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️🔥 Enjoy 24/7 Escort Service
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Phases of Negotiation .pptx
Phases of Negotiation .pptx
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Earned value management in action - A Webinar by Vivek Prakash, pmwares
1.
Earned Value Management
in Action Vivek Prakash – Aug, 16, 2012 © 2012 pmwares – All rights reserved
2.
Earned Value Management Definitions EVM
Terms Explanation Planned Value (PV) Estimated value of the work planned to be spent as of today. Earned Value (EV) Value of the work that is completed as of today (PV of completed work) Actual Cost (AC) Total cost actually incurred as of today Budget at Completion (BAC) Total planned value of the project Estimate at Completion (EAC) Forecasted total project cost as of today Estimate to Complete (ETC) Estimated cost of the remaining work Variance at Completion (VAC) The variance of total project cost project as of today © 2012 pmwares – All rights reserved
3.
Earned Value Management Formulas EVM
Terms EVM Formula Explanation Schedule Variance SV = EV - PV Measure of schedule performance. –ve value indicate delay Cost Variance CV = EV - AC Measure of cost performance. –ve value indicate cost overrun Schedule Performance Index SPI = EV/PV Measure of progress achieved. Value less than 1 indicate delay Cost Performance Index CPI = EV/AC Measure of value of the work completed. Value less than 1 indicate cost overun To Complete Performance Index TCPI = (BAC-EV) (BAC-AC) Measure of cost performance to be achieved on remaining work to meet project objectives Estimate to Complete ETC = EAC - AC Estimated cost of remaining work © 2012 pmwares – All rights reserved
4.
Earned Value Management Formulas EVM
Terms EVM Formula Explanation Variance at Completion VAC = BAC - EAC Variance of total projected cost from budget AC + Bottom up ETC When original estimates are fundamentally flawed BAC Cumulative CPI Observing no variance, will continue with same expenditure rate AC + (BAC-EV) Variance observed as of now will not be observed in future. Will complete the project in remaining budget Estimate at Completion (EAC) AC + [(BAC-EV)/ Current variance trends will continue. (Cum.CPI x Cum.SPI)] Remaining budget is modified with cost and schedule performance © 2012 pmwares – All rights reserved
5.
Earned Value Management Cost Cost
baseline Time © 2012 pmwares – All rights reserved
6.
Earned Value Management Cost Cost
baseline Actuals Time © 2012 pmwares – All rights reserved
7.
Earned Value Management Cost Cost
baseline Actuals Earned Time © 2012 pmwares – All rights reserved
8.
Earned Value Management AC PV Cost Cost
baseline Actuals Earned EV Time © 2012 pmwares – All rights reserved
9.
Earned Value Management AC PV Cost Cost
baseline Actuals Schedule variance in $ Earned EV Time © 2012 pmwares – All rights reserved
10.
Earned Value Management AC PV Cost Cost
baseline Actuals Cost variance Earned EV Time © 2012 pmwares – All rights reserved
11.
Earned Value Management A
wall is to be constructed around a square plot. Each side takes 1 week with estimated budget of $1,000. You have only one crew (with 1 supervisor and 3 workers), therefore construction is planned in sequence. After 1st week, a worker fell ill. We are not at end of 2nd week and status of the project is as below Side 1 Side 2 Side 3 Side 4 Task Side 1 Side 2 Week 1 Week 2 Week 3 Week 4 AS------AF AS--------PF Side 3 Cost incurred Complete $1000 Half done PS-----------PF Side 4 Status $800 To start PS-----------PF To start Status at the end of 2nd Week AS – Actual Start, AF – Actual Finish, PS – Planned Start, PF – Planned Finish © 2012 pmwares – All rights reserved
12.
Earned Value Management # Terms 1. PV 2. AC 3. EV 4. BAC 5. CV 5. SV 6. CPI 7. SPI 8. EAC 9. ETC 10. VAC Values Comments ©
2012 pmwares – All rights reserved
13.
Earned Value Management # Terms 1. 2. 3. 4. 5. 5. 6. PV
= 1000+1000 AC = 1000+800 EV = 1000+500 BAC CV (EV-AC) = 1500 – 1800 SV (EV-PV) = 1500 – 2000 CPI (EV/AC) = 1500/1800 2000 1800 1500 4000 -300 -500 0.833 7. 8. SPI (EV/PV) = 1500/2000 EAC (BAC/CPI) = 4000/0.833 0.75 We are progressing @ 75% 4801 We currently estimate that the total project will cost $4801 9. ETC (EAC–AC) = 4801 – 1800 3001 We currently estimate that we have to spend $3001 to finish the project 10. VAC (BAC–EAC) = 4000 – 4801 -801 We currently estimate that we will spend $801 more than budgeted. Values Comments We planned to do work worth $2000 We actually spent $1800 We actually completed $1500 worth of work Originally budgeted to complete in $4000 We are over budget by $300 We are behind schedule We are getting 83 cents out of every dollar invested © 2012 pmwares – All rights reserved
14.
What it needs
to implement EVM Discipline Planning Stable baseline Periodic tracking Gathering data of actual progress from team Actual Efforts & Remaining Efforts Updating plan Reporting Measuring variance Action Plan Reporting to stakeholders © 2012 pmwares – All rights reserved