SlideShare una empresa de Scribd logo
1 de 16
Descargar para leer sin conexión
1/8/2011

Project Management
Knowledge Areas
Section – 3
Chapter – 7
p

Project Cost Management
Session Objectives…
1. To identify Project Cost Management
y
j
g
Knowledge Area Processes
2. How to estimate approximate costs of
the resources needed
3. How to aggregate and determine
budgeted costs of project and to develop
the Cost Baseline
4. How to Control the influencing factors
that create variances to the project
budget

1
1/8/2011

Project Cost Management
Exam Objectives…
1.
1 Estimating Costs of schedule
activities
2. Developing Cost baseline
3. Implementing Cost Control
4.
4 Measuring Project Performance

Project Cost Management
Is primarily concerned with the cost of
p
the resources needed to complete
schedule activities.
Also considers
Cost of using,
Cost of maintaining
Cost f
C t of supporting th product,
ti the
d t
service or result
Is also called as Life-Cycle Costing

2
1/8/2011

Project Cost Management
The Processes in Project Cost Management are:
1. Estimate Costs
2. Determine Budget
3. Control Cost
These processes interact with each other and
with processes in the other knowledge areas
Each process occurs once in every project
Smaller projects scope, estimating costs and
determining budget are viewed as a single process

Project Cost Management
Establishes…
o Level of accuracy
y
Rounding of data to a prescribed precision
o Units of measure
Each unit used in measurement, such as staff
hours/staff days is defined
o Organizational procedures
The WBS component used for the project
cost accounting is called a control account.
This account is assigned a code that is linked
to organization’s accounting system

3
1/8/2011

Project Cost Management
Establishes…
o Control thresholds
Variance thresholds for costs or other
indicators such as person-days, can be
defined to indicate the agreed amount of
variation allowed
o Performance Measurements rules
EVM calculating formulas are defined
o Reporting formats
o Process description

Estimate Costs
Estimate Costs is the process of
g
calculating the costs of the identified
resources needed to complete the
project work.
Estimate Costs is the cost of the
resources required to complete the
p j
project work & Pricing includes a profit
g
p
margin
Estimates are generally expressed in units
of currency

4
1/8/2011

Estimate Costs
•
•
•
•
•

1. Scope Baseline
2. Project Schedule
3. Human Resource Plan
4. Risk Register
5. Enterprise Environmental
Factors
• 6. Organizational Process
Assets

Input

Tools &
Techniques
•
•
•
•
•
•
•
•

1. Expert Judgment
2. Analogous Estimating
3. Parametric Estimating
4. Bottom-Up Estimating
5. Three-Point Estimates
6. Reserve Analysis
7. Cost of Quality
8. Project Management
Estimating Software
• 9.Vender Bid Analysis

• 1. Activity Cost estimates
• 2. Basis of Estimates
• 3. Project Document Updates

Output

Estimate Costs
Inputs
1. Scope Baseline
p
2. Project Schedule
3. Human Resource Plan
4. Risk Register
5. Enterprise Environmental Factors
6. Organizational Process Assets
Cost estimating policies & templates
Historical information
Lessons learned

5
1/8/2011

Estimate Costs
Tools and Techniques
1. Expert J g
p
Judgment
2. Analogous Estimating
3. Parametric Estimating
4. Bottom-up Estimating
5. Three-Point Estimates
6. Reserve Analysis
7. Cost of Quality
8. Project Management Estimating Software
9. Vender Bid Analysis

Estimate Costs
Outputs
1.
1 Activity Cost Estimates
2. Basis of Estimates
3. Project document Updates

6
1/8/2011

Cost Estimating Techniques
Three Point Estimates is to improve
accuracy and reduce risk factors, Program
Evaluation and Review Technique (PERT) is
used
Most likely (Cm)
Optimistic (Co)
Pessimistic (C )
P i i i (Cp)
Weighted average of the activity cost is
(Co + 4 X Cm + Cp) / 6 stages of planning

Cost Estimating Techniques
Analogous Estimating
Relies on historical information to predict
p
the cost of the current project
Also knows as top-down estimating
It’s a form of expert judgment
Bottom-up Estimating
Calculates cost of each component of the
WBS, d i
WBS and arrives at a sum f the project
t
for th
j t
Most time consuming and expensive method
Most accurate method

7
1/8/2011

Cost Estimating Techniques
Parametric Estimating
Uses mathematical model based on known
parameters to predict the cost of a project
Usually calculated cost per unit
Types of parametric estimating
Regression analysis:- a statistical approach
to predict future values, based on historical
values
Learning curve:- Cost per unit
decreases the more units workers
complete

Cost Estimating Techniques
Reserve analysis
Is also called as contingency reserve
Used to meet cost overruns due to
risks that have impacted the projects’
cost baseline

8
1/8/2011

Determine Budget
Determine budget is aggregating the
estimated costs of individual schedule
activities to determine total cost of
the project
The cost baseline is used for
measuring project performance

Determine Budget

• 1. Activity Cost Estimates
• 2. Basis of Estimates
• 3. Scope Baseline
• 4. Project Schedule
• 5. Resource Calendars
• 6. Contracts
• 7. Organizational Process
Assets

Input

Tools &
Techniques
• 1. Cost Aggregation
• 2. Reserve Analysis
• 3. Expert Judgment
• 4. Historical Relationships
• 5. Funding Limit
Reconciliation

• 1. Cost Performance
Baseline
• 2. Project Funding
Requirements
• 3. Project Document
Updates

Output

9
1/8/2011

Determine Budget
Inputs
1.
1 Activity Cost Estimates
2. Basis of Estimates
3. Scope Baseline
4. Project Schedule
5.
5 Resource Calendars
6. Contracts
7. Organizational Process Assets

Determine Budget
Tools and Techniques
1.
1 Cost Aggregation
2. Reserve Analysis
3. Expert Judgment
4. Historical Relationships
5.
5 Funding Limit Reconciliation

10
1/8/2011

Determine Budget
Outputs
1.
1 Cost Performance Baseline
2. Project Funding Requirements
3. Project Document Updates

Tools & Techniques
Historical Relationships
o Result in parametric or analogous
estimates
involved
to
develop
mathematical models to predict total costs
o Models reliability can be improved by
Accurate historical information
Quantifiable parameters
Scalable models
o Ex. Cost per sqr.ft.

11
1/8/2011

Control Cost
Cost control focuses on the ability of
costs to change and on the ways of
allowing or preventing cost changes from
happening
Is concerned with understanding the cost
variances.
As cost variances happen, they must be
examined, recorded, and investigated.

Control Cost
Cost control focuses on…
Controlling causes of change to ensure
the changes are actually needed
Controlling and documenting changes to
the cost baseline as they happen
Controlling changes in the project and
their influence on cost
h
fl
Performing cost monitoring to recognize
and understand cost variance

12
1/8/2011

Control Cost
Cost control focuses on…
Recording appropriate cost changes in
the cost baseline
Preventing unauthorized changes to the
cost baseline
Communicating the cost changes to the
p p
proper stakeholders
Working to bring and maintain costs
within acceptable range

Control Cost

• 1. Project Management
Plan
• 2. Project Funding
Requirements
• 3. Work Performance
Information
• 4. Organizational Process
Assets

Input

Tools &
Techniques
• 1. Earned Value
Management
• 2. Forecasting
• 3. To-Complete
• Performance Index
•4 P f
4. Performance Reviews
R i
• 5.Variance Analysis
• 6. Project Management
Software

• 1. Work Performance
Measurements
• 2. Budget Forecasts
• 3. Organizational Process
Assets Updates
• 4. Change Requests
• 5. Project
• Management Plan Updates
• 6. Project Document Updates

Output

13
1/8/2011

Control Cost
Inputs
1.
1 Project management plan
2. Project funding requirements
3. Work performance information
4. Organizational Process Assets

Control Cost
Tools and Techniques
1.
1 Earned Value Management
2. Forecasting
3. To-Complete Performance Index
4. Performance reviews
5.
5 Project management software

14
1/8/2011

Control Cost
Outputs
1.
1 Work Performance Measurements
2. Budgeted Forecasts
3. Organizational Process Assets Updates
4. Change Requests
5.
5 Project Management Plan Updates
6. Project Document Updates

Project Cost Management
To Sum up…
1. We know Project Cost Management
j
g
Knowledge Area Processes
2. We
know how to estimate an
approximate costs of the resources
needed
3. We know how to aggregate the
estimated costs of individual activities to
establish a Cost Baseline
4. We know how to Control the influencing
factors that create variances to the
project budget

15
1/8/2011

Questions ?

16

Más contenido relacionado

La actualidad más candente

Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)Nur Azwin
 
IWP Timeline
IWP TimelineIWP Timeline
IWP TimelineScot Fyfe
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementOleksandr Lutsaievskyi
 
Project schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMProject schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMMudassir Iqbal
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementHayat Denzi
 
Cost management plan tyre recycling plant
Cost management plan  tyre recycling plantCost management plan  tyre recycling plant
Cost management plan tyre recycling plantabhishekthakur309
 
Exploring Metrics in Siebel Clinical
Exploring Metrics in Siebel ClinicalExploring Metrics in Siebel Clinical
Exploring Metrics in Siebel ClinicalPerficient
 
CE Partners meeting Nrb enos_Swahili version
CE Partners meeting Nrb enos_Swahili versionCE Partners meeting Nrb enos_Swahili version
CE Partners meeting Nrb enos_Swahili versionEnos Omondi
 
11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk Analysis11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk AnalysisDavidMcLachlan1
 
Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 
Project Implementation Process
Project Implementation ProcessProject Implementation Process
Project Implementation Processeklaksh
 
CONIG 1.6 Process Model Canvas
CONIG 1.6 Process Model CanvasCONIG 1.6 Process Model Canvas
CONIG 1.6 Process Model CanvasYalcin Gerek
 
Project controls
Project controlsProject controls
Project controlsAshok Kumar
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 

La actualidad más candente (20)

Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)
 
IWP Timeline
IWP TimelineIWP Timeline
IWP Timeline
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost Management
 
Session 9 4th edition PMP
Session 9 4th edition PMPSession 9 4th edition PMP
Session 9 4th edition PMP
 
Project schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMProject schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPM
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Cost management plan tyre recycling plant
Cost management plan  tyre recycling plantCost management plan  tyre recycling plant
Cost management plan tyre recycling plant
 
Cost management
Cost managementCost management
Cost management
 
Exploring Metrics in Siebel Clinical
Exploring Metrics in Siebel ClinicalExploring Metrics in Siebel Clinical
Exploring Metrics in Siebel Clinical
 
CE Partners meeting Nrb enos_Swahili version
CE Partners meeting Nrb enos_Swahili versionCE Partners meeting Nrb enos_Swahili version
CE Partners meeting Nrb enos_Swahili version
 
11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk Analysis11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Monitoring the control
Monitoring the control Monitoring the control
Monitoring the control
 
Project Implementation Process
Project Implementation ProcessProject Implementation Process
Project Implementation Process
 
CONIG 1.6 Process Model Canvas
CONIG 1.6 Process Model CanvasCONIG 1.6 Process Model Canvas
CONIG 1.6 Process Model Canvas
 
Project controls
Project controlsProject controls
Project controls
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
ATCO Engineering - Process Evaluation
ATCO Engineering - Process EvaluationATCO Engineering - Process Evaluation
ATCO Engineering - Process Evaluation
 

Destacado

Project human resource management
Project human resource managementProject human resource management
Project human resource managementJahangeer Shams
 
Hierarchichal species distributions model and Maxent
Hierarchichal species distributions model and MaxentHierarchichal species distributions model and Maxent
Hierarchichal species distributions model and Maxentrichardchandler
 
mary hanley rec. letter
mary hanley rec. lettermary hanley rec. letter
mary hanley rec. letterMichelle Duron
 
Bombas Dosadoras _ Português
Bombas Dosadoras _ PortuguêsBombas Dosadoras _ Português
Bombas Dosadoras _ PortuguêsVibropac
 
Improving NDT Compliance: A New Approach in Software
Improving NDT Compliance: A New Approach in SoftwareImproving NDT Compliance: A New Approach in Software
Improving NDT Compliance: A New Approach in SoftwareSarah Kennedy
 
WeCareTLC Risk Management White Paper 2015_1452008903358
WeCareTLC Risk Management White Paper 2015_1452008903358WeCareTLC Risk Management White Paper 2015_1452008903358
WeCareTLC Risk Management White Paper 2015_1452008903358Kevin Cooksey
 
Lifestyle Holidays Vacation Club Announces Whale Season In The Dominican Repu...
Lifestyle Holidays Vacation Club Announces Whale Season In The Dominican Repu...Lifestyle Holidays Vacation Club Announces Whale Season In The Dominican Repu...
Lifestyle Holidays Vacation Club Announces Whale Season In The Dominican Repu...Lifestyle Holidays Vacation Club
 
Executive skills reference by bhawani nandan prasad
Executive skills reference by bhawani nandan prasadExecutive skills reference by bhawani nandan prasad
Executive skills reference by bhawani nandan prasadBhawani N Prasad
 
الإيدز و الصحة و آلناس لبنان ـ 2005
الإيدز و الصحة و آلناس لبنان ـ 2005الإيدز و الصحة و آلناس لبنان ـ 2005
الإيدز و الصحة و آلناس لبنان ـ 2005ITPCMENA
 
Importar imágenes a un proyecto android desde eclipse
Importar imágenes a un proyecto android desde eclipseImportar imágenes a un proyecto android desde eclipse
Importar imágenes a un proyecto android desde eclipseYanori Perez
 
Blockchain - Beyond the Buzzword
Blockchain - Beyond the BuzzwordBlockchain - Beyond the Buzzword
Blockchain - Beyond the BuzzwordMiguel Neumann
 

Destacado (19)

Project managment 4
Project managment 4Project managment 4
Project managment 4
 
Project human resource management
Project human resource managementProject human resource management
Project human resource management
 
Project managment 6 (a)
Project managment 6 (a)Project managment 6 (a)
Project managment 6 (a)
 
Hierarchichal species distributions model and Maxent
Hierarchichal species distributions model and MaxentHierarchichal species distributions model and Maxent
Hierarchichal species distributions model and Maxent
 
mary hanley rec. letter
mary hanley rec. lettermary hanley rec. letter
mary hanley rec. letter
 
Bombas Dosadoras _ Português
Bombas Dosadoras _ PortuguêsBombas Dosadoras _ Português
Bombas Dosadoras _ Português
 
ElliottHarrington_Poster_AGU-2013
ElliottHarrington_Poster_AGU-2013ElliottHarrington_Poster_AGU-2013
ElliottHarrington_Poster_AGU-2013
 
Improving NDT Compliance: A New Approach in Software
Improving NDT Compliance: A New Approach in SoftwareImproving NDT Compliance: A New Approach in Software
Improving NDT Compliance: A New Approach in Software
 
WeCareTLC Risk Management White Paper 2015_1452008903358
WeCareTLC Risk Management White Paper 2015_1452008903358WeCareTLC Risk Management White Paper 2015_1452008903358
WeCareTLC Risk Management White Paper 2015_1452008903358
 
YFriday CPhT 2016
YFriday CPhT 2016YFriday CPhT 2016
YFriday CPhT 2016
 
Lifestyle Holidays Vacation Club Announces Whale Season In The Dominican Repu...
Lifestyle Holidays Vacation Club Announces Whale Season In The Dominican Repu...Lifestyle Holidays Vacation Club Announces Whale Season In The Dominican Repu...
Lifestyle Holidays Vacation Club Announces Whale Season In The Dominican Repu...
 
Всё про mmorpg
Всё про mmorpgВсё про mmorpg
Всё про mmorpg
 
Executive skills reference by bhawani nandan prasad
Executive skills reference by bhawani nandan prasadExecutive skills reference by bhawani nandan prasad
Executive skills reference by bhawani nandan prasad
 
Project managment 3
Project managment 3Project managment 3
Project managment 3
 
M.V. ALVA STAR
M.V. ALVA STARM.V. ALVA STAR
M.V. ALVA STAR
 
الإيدز و الصحة و آلناس لبنان ـ 2005
الإيدز و الصحة و آلناس لبنان ـ 2005الإيدز و الصحة و آلناس لبنان ـ 2005
الإيدز و الصحة و آلناس لبنان ـ 2005
 
Importar imágenes a un proyecto android desde eclipse
Importar imágenes a un proyecto android desde eclipseImportar imágenes a un proyecto android desde eclipse
Importar imágenes a un proyecto android desde eclipse
 
Blockchain - Beyond the Buzzword
Blockchain - Beyond the BuzzwordBlockchain - Beyond the Buzzword
Blockchain - Beyond the Buzzword
 
5 трендов в SMM - 2016.
5 трендов в SMM - 2016.5 трендов в SMM - 2016.
5 трендов в SMM - 2016.
 

Similar a Project managment 6

Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfHuyNguyen657394
 
4- Project Cost Management.ppt
4- Project Cost Management.ppt4- Project Cost Management.ppt
4- Project Cost Management.pptMohamadAGhareb
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Agus Suhanto
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenetAla Ibrahim
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost ManagementDavidMcLachlan1
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementYudha Pratama, PMP
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagementDhamo daran
 
PMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementPMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementAndrew Mikityuk
 
PMP Module 4 - Cost
PMP Module 4 - CostPMP Module 4 - Cost
PMP Module 4 - CostCybrary
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgetingIzah Asmadi
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1Skillogic Solutions
 
projectplanningandprojectworkplan-130828212658-phpapp02-converted.pptx
projectplanningandprojectworkplan-130828212658-phpapp02-converted.pptxprojectplanningandprojectworkplan-130828212658-phpapp02-converted.pptx
projectplanningandprojectworkplan-130828212658-phpapp02-converted.pptxChandrasen Sharma
 
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdf
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdfprojectplanningandprojectworkplan-130828212658-phpapp02 (1).pdf
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdfJyotiYadav916744
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxssusercf695b
 

Similar a Project managment 6 (20)

PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 
4- Project Cost Management.ppt
4- Project Cost Management.ppt4- Project Cost Management.ppt
4- Project Cost Management.ppt
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost Management
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost management
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
PMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementPMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration Management
 
PMP Module 4 - Cost
PMP Module 4 - CostPMP Module 4 - Cost
PMP Module 4 - Cost
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1
 
Cost Management PMBOK
Cost Management PMBOKCost Management PMBOK
Cost Management PMBOK
 
projectplanningandprojectworkplan-130828212658-phpapp02-converted.pptx
projectplanningandprojectworkplan-130828212658-phpapp02-converted.pptxprojectplanningandprojectworkplan-130828212658-phpapp02-converted.pptx
projectplanningandprojectworkplan-130828212658-phpapp02-converted.pptx
 
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdf
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdfprojectplanningandprojectworkplan-130828212658-phpapp02 (1).pdf
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdf
 
Project planning and project work plan
Project planning and project work planProject planning and project work plan
Project planning and project work plan
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 

Más de Абдулазіз Мухаммед (6)

Project managment 10
Project managment  10Project managment  10
Project managment 10
 
Project managment 9
Project managment  9Project managment  9
Project managment 9
 
Project managment 8
Project managment  8Project managment  8
Project managment 8
 
Project managment 7
Project managment  7Project managment  7
Project managment 7
 
Project managment 2
Project managment 2Project managment 2
Project managment 2
 
Project managment 1
Project managment 1Project managment 1
Project managment 1
 

Último

Technical SEO for Improved Accessibility WTS FEST
Technical SEO for Improved Accessibility  WTS FESTTechnical SEO for Improved Accessibility  WTS FEST
Technical SEO for Improved Accessibility WTS FESTBillieHyde
 
EMEA What is ThousandEyes? Webinar
EMEA What is ThousandEyes? WebinarEMEA What is ThousandEyes? Webinar
EMEA What is ThousandEyes? WebinarThousandEyes
 
Planetek Italia Srl - Corporate Profile Brochure
Planetek Italia Srl - Corporate Profile BrochurePlanetek Italia Srl - Corporate Profile Brochure
Planetek Italia Srl - Corporate Profile BrochurePlanetek Italia Srl
 
Oracle Database 23c Security New Features.pptx
Oracle Database 23c Security New Features.pptxOracle Database 23c Security New Features.pptx
Oracle Database 23c Security New Features.pptxSatishbabu Gunukula
 
Webinar: The Art of Prioritizing Your Product Roadmap by AWS Sr PM - Tech
Webinar: The Art of Prioritizing Your Product Roadmap by AWS Sr PM - TechWebinar: The Art of Prioritizing Your Product Roadmap by AWS Sr PM - Tech
Webinar: The Art of Prioritizing Your Product Roadmap by AWS Sr PM - TechProduct School
 
My key hands-on projects in Quantum, and QAI
My key hands-on projects in Quantum, and QAIMy key hands-on projects in Quantum, and QAI
My key hands-on projects in Quantum, and QAIVijayananda Mohire
 
The Importance of Indoor Air Quality (English)
The Importance of Indoor Air Quality (English)The Importance of Indoor Air Quality (English)
The Importance of Indoor Air Quality (English)IES VE
 
CyberSecurity - Computers In Libraries 2024
CyberSecurity - Computers In Libraries 2024CyberSecurity - Computers In Libraries 2024
CyberSecurity - Computers In Libraries 2024Brian Pichman
 
Extra-120324-Visite-Entreprise-icare.pdf
Extra-120324-Visite-Entreprise-icare.pdfExtra-120324-Visite-Entreprise-icare.pdf
Extra-120324-Visite-Entreprise-icare.pdfInfopole1
 
Outage Analysis: March 5th/6th 2024 Meta, Comcast, and LinkedIn
Outage Analysis: March 5th/6th 2024 Meta, Comcast, and LinkedInOutage Analysis: March 5th/6th 2024 Meta, Comcast, and LinkedIn
Outage Analysis: March 5th/6th 2024 Meta, Comcast, and LinkedInThousandEyes
 
Introduction to RAG (Retrieval Augmented Generation) and its application
Introduction to RAG (Retrieval Augmented Generation) and its applicationIntroduction to RAG (Retrieval Augmented Generation) and its application
Introduction to RAG (Retrieval Augmented Generation) and its applicationKnoldus Inc.
 
Keep Your Finger on the Pulse of Your Building's Performance with IES Live
Keep Your Finger on the Pulse of Your Building's Performance with IES LiveKeep Your Finger on the Pulse of Your Building's Performance with IES Live
Keep Your Finger on the Pulse of Your Building's Performance with IES LiveIES VE
 
GraphSummit Copenhagen 2024 - Neo4j Vision and Roadmap.pptx
GraphSummit Copenhagen 2024 - Neo4j Vision and Roadmap.pptxGraphSummit Copenhagen 2024 - Neo4j Vision and Roadmap.pptx
GraphSummit Copenhagen 2024 - Neo4j Vision and Roadmap.pptxNeo4j
 
20140402 - Smart house demo kit
20140402 - Smart house demo kit20140402 - Smart house demo kit
20140402 - Smart house demo kitJamie (Taka) Wang
 
UiPath Studio Web workshop series - Day 4
UiPath Studio Web workshop series - Day 4UiPath Studio Web workshop series - Day 4
UiPath Studio Web workshop series - Day 4DianaGray10
 
UiPath Studio Web workshop Series - Day 3
UiPath Studio Web workshop Series - Day 3UiPath Studio Web workshop Series - Day 3
UiPath Studio Web workshop Series - Day 3DianaGray10
 
SIM INFORMATION SYSTEM: REVOLUTIONIZING DATA MANAGEMENT
SIM INFORMATION SYSTEM: REVOLUTIONIZING DATA MANAGEMENTSIM INFORMATION SYSTEM: REVOLUTIONIZING DATA MANAGEMENT
SIM INFORMATION SYSTEM: REVOLUTIONIZING DATA MANAGEMENTxtailishbaloch
 
3 Pitfalls Everyone Should Avoid with Cloud Data
3 Pitfalls Everyone Should Avoid with Cloud Data3 Pitfalls Everyone Should Avoid with Cloud Data
3 Pitfalls Everyone Should Avoid with Cloud DataEric D. Schabell
 
TrustArc Webinar - How to Live in a Post Third-Party Cookie World
TrustArc Webinar - How to Live in a Post Third-Party Cookie WorldTrustArc Webinar - How to Live in a Post Third-Party Cookie World
TrustArc Webinar - How to Live in a Post Third-Party Cookie WorldTrustArc
 
Trailblazer Community - Flows Workshop (Session 2)
Trailblazer Community - Flows Workshop (Session 2)Trailblazer Community - Flows Workshop (Session 2)
Trailblazer Community - Flows Workshop (Session 2)Muhammad Tiham Siddiqui
 

Último (20)

Technical SEO for Improved Accessibility WTS FEST
Technical SEO for Improved Accessibility  WTS FESTTechnical SEO for Improved Accessibility  WTS FEST
Technical SEO for Improved Accessibility WTS FEST
 
EMEA What is ThousandEyes? Webinar
EMEA What is ThousandEyes? WebinarEMEA What is ThousandEyes? Webinar
EMEA What is ThousandEyes? Webinar
 
Planetek Italia Srl - Corporate Profile Brochure
Planetek Italia Srl - Corporate Profile BrochurePlanetek Italia Srl - Corporate Profile Brochure
Planetek Italia Srl - Corporate Profile Brochure
 
Oracle Database 23c Security New Features.pptx
Oracle Database 23c Security New Features.pptxOracle Database 23c Security New Features.pptx
Oracle Database 23c Security New Features.pptx
 
Webinar: The Art of Prioritizing Your Product Roadmap by AWS Sr PM - Tech
Webinar: The Art of Prioritizing Your Product Roadmap by AWS Sr PM - TechWebinar: The Art of Prioritizing Your Product Roadmap by AWS Sr PM - Tech
Webinar: The Art of Prioritizing Your Product Roadmap by AWS Sr PM - Tech
 
My key hands-on projects in Quantum, and QAI
My key hands-on projects in Quantum, and QAIMy key hands-on projects in Quantum, and QAI
My key hands-on projects in Quantum, and QAI
 
The Importance of Indoor Air Quality (English)
The Importance of Indoor Air Quality (English)The Importance of Indoor Air Quality (English)
The Importance of Indoor Air Quality (English)
 
CyberSecurity - Computers In Libraries 2024
CyberSecurity - Computers In Libraries 2024CyberSecurity - Computers In Libraries 2024
CyberSecurity - Computers In Libraries 2024
 
Extra-120324-Visite-Entreprise-icare.pdf
Extra-120324-Visite-Entreprise-icare.pdfExtra-120324-Visite-Entreprise-icare.pdf
Extra-120324-Visite-Entreprise-icare.pdf
 
Outage Analysis: March 5th/6th 2024 Meta, Comcast, and LinkedIn
Outage Analysis: March 5th/6th 2024 Meta, Comcast, and LinkedInOutage Analysis: March 5th/6th 2024 Meta, Comcast, and LinkedIn
Outage Analysis: March 5th/6th 2024 Meta, Comcast, and LinkedIn
 
Introduction to RAG (Retrieval Augmented Generation) and its application
Introduction to RAG (Retrieval Augmented Generation) and its applicationIntroduction to RAG (Retrieval Augmented Generation) and its application
Introduction to RAG (Retrieval Augmented Generation) and its application
 
Keep Your Finger on the Pulse of Your Building's Performance with IES Live
Keep Your Finger on the Pulse of Your Building's Performance with IES LiveKeep Your Finger on the Pulse of Your Building's Performance with IES Live
Keep Your Finger on the Pulse of Your Building's Performance with IES Live
 
GraphSummit Copenhagen 2024 - Neo4j Vision and Roadmap.pptx
GraphSummit Copenhagen 2024 - Neo4j Vision and Roadmap.pptxGraphSummit Copenhagen 2024 - Neo4j Vision and Roadmap.pptx
GraphSummit Copenhagen 2024 - Neo4j Vision and Roadmap.pptx
 
20140402 - Smart house demo kit
20140402 - Smart house demo kit20140402 - Smart house demo kit
20140402 - Smart house demo kit
 
UiPath Studio Web workshop series - Day 4
UiPath Studio Web workshop series - Day 4UiPath Studio Web workshop series - Day 4
UiPath Studio Web workshop series - Day 4
 
UiPath Studio Web workshop Series - Day 3
UiPath Studio Web workshop Series - Day 3UiPath Studio Web workshop Series - Day 3
UiPath Studio Web workshop Series - Day 3
 
SIM INFORMATION SYSTEM: REVOLUTIONIZING DATA MANAGEMENT
SIM INFORMATION SYSTEM: REVOLUTIONIZING DATA MANAGEMENTSIM INFORMATION SYSTEM: REVOLUTIONIZING DATA MANAGEMENT
SIM INFORMATION SYSTEM: REVOLUTIONIZING DATA MANAGEMENT
 
3 Pitfalls Everyone Should Avoid with Cloud Data
3 Pitfalls Everyone Should Avoid with Cloud Data3 Pitfalls Everyone Should Avoid with Cloud Data
3 Pitfalls Everyone Should Avoid with Cloud Data
 
TrustArc Webinar - How to Live in a Post Third-Party Cookie World
TrustArc Webinar - How to Live in a Post Third-Party Cookie WorldTrustArc Webinar - How to Live in a Post Third-Party Cookie World
TrustArc Webinar - How to Live in a Post Third-Party Cookie World
 
Trailblazer Community - Flows Workshop (Session 2)
Trailblazer Community - Flows Workshop (Session 2)Trailblazer Community - Flows Workshop (Session 2)
Trailblazer Community - Flows Workshop (Session 2)
 

Project managment 6

  • 1. 1/8/2011 Project Management Knowledge Areas Section – 3 Chapter – 7 p Project Cost Management Session Objectives… 1. To identify Project Cost Management y j g Knowledge Area Processes 2. How to estimate approximate costs of the resources needed 3. How to aggregate and determine budgeted costs of project and to develop the Cost Baseline 4. How to Control the influencing factors that create variances to the project budget 1
  • 2. 1/8/2011 Project Cost Management Exam Objectives… 1. 1 Estimating Costs of schedule activities 2. Developing Cost baseline 3. Implementing Cost Control 4. 4 Measuring Project Performance Project Cost Management Is primarily concerned with the cost of p the resources needed to complete schedule activities. Also considers Cost of using, Cost of maintaining Cost f C t of supporting th product, ti the d t service or result Is also called as Life-Cycle Costing 2
  • 3. 1/8/2011 Project Cost Management The Processes in Project Cost Management are: 1. Estimate Costs 2. Determine Budget 3. Control Cost These processes interact with each other and with processes in the other knowledge areas Each process occurs once in every project Smaller projects scope, estimating costs and determining budget are viewed as a single process Project Cost Management Establishes… o Level of accuracy y Rounding of data to a prescribed precision o Units of measure Each unit used in measurement, such as staff hours/staff days is defined o Organizational procedures The WBS component used for the project cost accounting is called a control account. This account is assigned a code that is linked to organization’s accounting system 3
  • 4. 1/8/2011 Project Cost Management Establishes… o Control thresholds Variance thresholds for costs or other indicators such as person-days, can be defined to indicate the agreed amount of variation allowed o Performance Measurements rules EVM calculating formulas are defined o Reporting formats o Process description Estimate Costs Estimate Costs is the process of g calculating the costs of the identified resources needed to complete the project work. Estimate Costs is the cost of the resources required to complete the p j project work & Pricing includes a profit g p margin Estimates are generally expressed in units of currency 4
  • 5. 1/8/2011 Estimate Costs • • • • • 1. Scope Baseline 2. Project Schedule 3. Human Resource Plan 4. Risk Register 5. Enterprise Environmental Factors • 6. Organizational Process Assets Input Tools & Techniques • • • • • • • • 1. Expert Judgment 2. Analogous Estimating 3. Parametric Estimating 4. Bottom-Up Estimating 5. Three-Point Estimates 6. Reserve Analysis 7. Cost of Quality 8. Project Management Estimating Software • 9.Vender Bid Analysis • 1. Activity Cost estimates • 2. Basis of Estimates • 3. Project Document Updates Output Estimate Costs Inputs 1. Scope Baseline p 2. Project Schedule 3. Human Resource Plan 4. Risk Register 5. Enterprise Environmental Factors 6. Organizational Process Assets Cost estimating policies & templates Historical information Lessons learned 5
  • 6. 1/8/2011 Estimate Costs Tools and Techniques 1. Expert J g p Judgment 2. Analogous Estimating 3. Parametric Estimating 4. Bottom-up Estimating 5. Three-Point Estimates 6. Reserve Analysis 7. Cost of Quality 8. Project Management Estimating Software 9. Vender Bid Analysis Estimate Costs Outputs 1. 1 Activity Cost Estimates 2. Basis of Estimates 3. Project document Updates 6
  • 7. 1/8/2011 Cost Estimating Techniques Three Point Estimates is to improve accuracy and reduce risk factors, Program Evaluation and Review Technique (PERT) is used Most likely (Cm) Optimistic (Co) Pessimistic (C ) P i i i (Cp) Weighted average of the activity cost is (Co + 4 X Cm + Cp) / 6 stages of planning Cost Estimating Techniques Analogous Estimating Relies on historical information to predict p the cost of the current project Also knows as top-down estimating It’s a form of expert judgment Bottom-up Estimating Calculates cost of each component of the WBS, d i WBS and arrives at a sum f the project t for th j t Most time consuming and expensive method Most accurate method 7
  • 8. 1/8/2011 Cost Estimating Techniques Parametric Estimating Uses mathematical model based on known parameters to predict the cost of a project Usually calculated cost per unit Types of parametric estimating Regression analysis:- a statistical approach to predict future values, based on historical values Learning curve:- Cost per unit decreases the more units workers complete Cost Estimating Techniques Reserve analysis Is also called as contingency reserve Used to meet cost overruns due to risks that have impacted the projects’ cost baseline 8
  • 9. 1/8/2011 Determine Budget Determine budget is aggregating the estimated costs of individual schedule activities to determine total cost of the project The cost baseline is used for measuring project performance Determine Budget • 1. Activity Cost Estimates • 2. Basis of Estimates • 3. Scope Baseline • 4. Project Schedule • 5. Resource Calendars • 6. Contracts • 7. Organizational Process Assets Input Tools & Techniques • 1. Cost Aggregation • 2. Reserve Analysis • 3. Expert Judgment • 4. Historical Relationships • 5. Funding Limit Reconciliation • 1. Cost Performance Baseline • 2. Project Funding Requirements • 3. Project Document Updates Output 9
  • 10. 1/8/2011 Determine Budget Inputs 1. 1 Activity Cost Estimates 2. Basis of Estimates 3. Scope Baseline 4. Project Schedule 5. 5 Resource Calendars 6. Contracts 7. Organizational Process Assets Determine Budget Tools and Techniques 1. 1 Cost Aggregation 2. Reserve Analysis 3. Expert Judgment 4. Historical Relationships 5. 5 Funding Limit Reconciliation 10
  • 11. 1/8/2011 Determine Budget Outputs 1. 1 Cost Performance Baseline 2. Project Funding Requirements 3. Project Document Updates Tools & Techniques Historical Relationships o Result in parametric or analogous estimates involved to develop mathematical models to predict total costs o Models reliability can be improved by Accurate historical information Quantifiable parameters Scalable models o Ex. Cost per sqr.ft. 11
  • 12. 1/8/2011 Control Cost Cost control focuses on the ability of costs to change and on the ways of allowing or preventing cost changes from happening Is concerned with understanding the cost variances. As cost variances happen, they must be examined, recorded, and investigated. Control Cost Cost control focuses on… Controlling causes of change to ensure the changes are actually needed Controlling and documenting changes to the cost baseline as they happen Controlling changes in the project and their influence on cost h fl Performing cost monitoring to recognize and understand cost variance 12
  • 13. 1/8/2011 Control Cost Cost control focuses on… Recording appropriate cost changes in the cost baseline Preventing unauthorized changes to the cost baseline Communicating the cost changes to the p p proper stakeholders Working to bring and maintain costs within acceptable range Control Cost • 1. Project Management Plan • 2. Project Funding Requirements • 3. Work Performance Information • 4. Organizational Process Assets Input Tools & Techniques • 1. Earned Value Management • 2. Forecasting • 3. To-Complete • Performance Index •4 P f 4. Performance Reviews R i • 5.Variance Analysis • 6. Project Management Software • 1. Work Performance Measurements • 2. Budget Forecasts • 3. Organizational Process Assets Updates • 4. Change Requests • 5. Project • Management Plan Updates • 6. Project Document Updates Output 13
  • 14. 1/8/2011 Control Cost Inputs 1. 1 Project management plan 2. Project funding requirements 3. Work performance information 4. Organizational Process Assets Control Cost Tools and Techniques 1. 1 Earned Value Management 2. Forecasting 3. To-Complete Performance Index 4. Performance reviews 5. 5 Project management software 14
  • 15. 1/8/2011 Control Cost Outputs 1. 1 Work Performance Measurements 2. Budgeted Forecasts 3. Organizational Process Assets Updates 4. Change Requests 5. 5 Project Management Plan Updates 6. Project Document Updates Project Cost Management To Sum up… 1. We know Project Cost Management j g Knowledge Area Processes 2. We know how to estimate an approximate costs of the resources needed 3. We know how to aggregate the estimated costs of individual activities to establish a Cost Baseline 4. We know how to Control the influencing factors that create variances to the project budget 15