SlideShare una empresa de Scribd logo
1 de 1
Descargar para leer sin conexión
PROJECT HIGHLIGHTS

Award-Winning Water
Supply System Lowers
Usage and Costs

T

he Georgia Bureau of Investigation
(GBI) headquarters in Decatur
had been coping with high nonpotable water usage and costs to support
systems fed by the county water supply.
In fact, the GBI consumed 1,000,000 gallons

month—costing $34,400 annually. From
this information, they also developed a
b
­ aseline meter reading for the winter months
of just over 140,000 gallons per month.
The source of the additional 230,000 gallons
per month on average was then pinpointed
—the cooling tower make-up
water and ­rrigation systems.
i

To lessen county water usage,
the GBI staff developed an inno­
vative alternative water capture
s
­ ystem and enlisted McKenney’s
engineering expertise and capa­
bilities to implement the system.
It consisted of two cisterns with
10,000-gallon total storage
capacity and an on-site well that
pumps water to the cisterns. In
“ cKenney’s also installed a pump, control addition, the system also tapped
M
into condensate water from air
valves and piping to the cisterns …”
­
handlers in the GBI’s Annex
during a typical hot August. Hoping to
building and diverted rainwater from the
reduce its water usage and its high costs,
b
­ uilding’s roof to the cisterns. ­ cKenney’s
M
the GBI collaborated with McKenney’s to
also installed a pump, control valves and
implement a more feasible, affordable and
p
­ iping to the cisterns to distribute the stored
sustainable solution.
water to the cooling tower make-up and
­irrigation systems.
After several years of monitoring water
usage and carefully analyzing the data, the
With its new non-potable water supply
GBI staff determined that they consumed
s
­ ystem operating successfully, the GBI
an average of 370,000 gallons of water a
expects to achieve $20,000 in cost savings
The content of this document is not intended as an endorsement.

For more information contact McKenney’s at 404-622-5000.
info@mckenneys.com   www.mckenneys.com
McKenney’s, Inc.    1056 Moreland Industrial Boulevard, Atlanta, Georgia 30316

Project Team
žž Owner: Georgia Bureau of
I
­nvestigation and CBRE, Inc.
žž Engineer: McKenney’s, Inc.
The Challenge
žž Calculate water usage
and costs history
žž Pinpoint source of excesses
žž Devise supplemental
water supply solution
The Solution
žž Dig an on-site well and
install storage cisterns
žž Capture condensate and
r
­ ainwater for cisterns
žž Pipe water from cisterns
to cooling tower and
irrigation systems
The Results
žž Cost savings of $20,000 annually
žž Project earned 2013 GASFA
­Innovation Award
žž System payback of four years
annually, which allows the system to pay
for itself in just four years. With such significant results—not only in cost savings but
also reduced environmental impact—the
project earned a 2013 Innovation Award
from the Georgia Association of State Facilities Administrators (GASFA). It also paves
the way for other state agencies with a high
demand for non-­ otable water to enlist a
p
similar solution to lower water use and costs,
provided it has the infrastructure to support
an on-site well and water storage system.

Copyright © 2013 McKenney’s, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A.
McKenney’s, Inc. and the McKenney’s, Inc. logo are registered trademarks of McKenney’s, Inc. All other trademarks are the property of their respective owners.

Más contenido relacionado

La actualidad más candente

05 Water and Energy
05 Water and Energy05 Water and Energy
05 Water and Energy
Jill Watkins
 
ccwi2016_IvoSilvestre
ccwi2016_IvoSilvestreccwi2016_IvoSilvestre
ccwi2016_IvoSilvestre
ivo silvestre
 
Senior Design Water Conservation
Senior Design Water ConservationSenior Design Water Conservation
Senior Design Water Conservation
LaJerrika Carney
 
Thermal Potential in the Built Environment
Thermal Potential in the Built EnvironmentThermal Potential in the Built Environment
Thermal Potential in the Built Environment
Yale Carden
 
Geothermal Discussion: Office of Energy Security
Geothermal Discussion: Office of Energy SecurityGeothermal Discussion: Office of Energy Security
Geothermal Discussion: Office of Energy Security
University of Minnesota
 

La actualidad más candente (20)

BOMA 2016 - Water is the New Energy
BOMA 2016 - Water is the New EnergyBOMA 2016 - Water is the New Energy
BOMA 2016 - Water is the New Energy
 
River Restoration for NPDES Permit Compliance
River Restoration for NPDES Permit ComplianceRiver Restoration for NPDES Permit Compliance
River Restoration for NPDES Permit Compliance
 
05 Water and Energy
05 Water and Energy05 Water and Energy
05 Water and Energy
 
Berg canlan case study (1)
Berg canlan case study (1)Berg canlan case study (1)
Berg canlan case study (1)
 
Energy audit for a waste water treatment process
Energy audit for a waste water treatment processEnergy audit for a waste water treatment process
Energy audit for a waste water treatment process
 
ccwi2016_IvoSilvestre
ccwi2016_IvoSilvestreccwi2016_IvoSilvestre
ccwi2016_IvoSilvestre
 
Addressing Landscape Water Use
Addressing Landscape Water UseAddressing Landscape Water Use
Addressing Landscape Water Use
 
Circular Economy Solutions in the Water Sector
Circular Economy Solutions in the Water SectorCircular Economy Solutions in the Water Sector
Circular Economy Solutions in the Water Sector
 
Geoexchange Presentation: Grand Designs Live 2013
Geoexchange Presentation: Grand Designs Live 2013Geoexchange Presentation: Grand Designs Live 2013
Geoexchange Presentation: Grand Designs Live 2013
 
GeoExchange Heating and Cooling: The 5 Slide Challenge
GeoExchange Heating and Cooling: The 5 Slide ChallengeGeoExchange Heating and Cooling: The 5 Slide Challenge
GeoExchange Heating and Cooling: The 5 Slide Challenge
 
Eco hydro logger presentation
Eco hydro logger presentationEco hydro logger presentation
Eco hydro logger presentation
 
23% Annual Energy Savings on a Distribution Centre Cold Store for a Major Sup...
23% Annual Energy Savings on a Distribution Centre Cold Store for a Major Sup...23% Annual Energy Savings on a Distribution Centre Cold Store for a Major Sup...
23% Annual Energy Savings on a Distribution Centre Cold Store for a Major Sup...
 
Mihai Grozavescu Aquatim - Timisoara demo case
Mihai Grozavescu Aquatim - Timisoara demo caseMihai Grozavescu Aquatim - Timisoara demo case
Mihai Grozavescu Aquatim - Timisoara demo case
 
Senior Design Water Conservation
Senior Design Water ConservationSenior Design Water Conservation
Senior Design Water Conservation
 
Biogas portal article srinivas kasulla
Biogas portal  article srinivas kasullaBiogas portal  article srinivas kasulla
Biogas portal article srinivas kasulla
 
Benefits of Modular District Energy
Benefits of Modular District EnergyBenefits of Modular District Energy
Benefits of Modular District Energy
 
Thermal Potential in the Built Environment
Thermal Potential in the Built EnvironmentThermal Potential in the Built Environment
Thermal Potential in the Built Environment
 
VGBC Online Series, Module 6: Sử dụng nước hiệu quả trong công trình xanh (2/...
VGBC Online Series, Module 6: Sử dụng nước hiệu quả trong công trình xanh (2/...VGBC Online Series, Module 6: Sử dụng nước hiệu quả trong công trình xanh (2/...
VGBC Online Series, Module 6: Sử dụng nước hiệu quả trong công trình xanh (2/...
 
Geothermal Discussion: Office of Energy Security
Geothermal Discussion: Office of Energy SecurityGeothermal Discussion: Office of Energy Security
Geothermal Discussion: Office of Energy Security
 
BREEAM
BREEAMBREEAM
BREEAM
 

Destacado

3i angels lista de beneficios
3i angels   lista de beneficios3i angels   lista de beneficios
3i angels lista de beneficios
Michel Porcino
 
10. metonimias. construcciones simuladas
10. metonimias. construcciones simuladas10. metonimias. construcciones simuladas
10. metonimias. construcciones simuladas
cmiglesias
 
Meaning of market segmentation
Meaning of market segmentationMeaning of market segmentation
Meaning of market segmentation
Prem Pun
 
OeRC_BioNatMedSciences_TeamOverview_Dec2013
OeRC_BioNatMedSciences_TeamOverview_Dec2013OeRC_BioNatMedSciences_TeamOverview_Dec2013
OeRC_BioNatMedSciences_TeamOverview_Dec2013
Susanna-Assunta Sansone
 

Destacado (16)

Schedule
ScheduleSchedule
Schedule
 
Hi - LOL
Hi - LOL Hi - LOL
Hi - LOL
 
Its learning i austevollpptx
Its learning i austevollpptxIts learning i austevollpptx
Its learning i austevollpptx
 
Centre verd company profile
Centre verd company profileCentre verd company profile
Centre verd company profile
 
3i angels lista de beneficios
3i angels   lista de beneficios3i angels   lista de beneficios
3i angels lista de beneficios
 
Web 2
Web 2Web 2
Web 2
 
Origin of chinese characters 说文解字 298 征(徵) go on a long journey
Origin of chinese characters 说文解字 298 征(徵) go on a long journeyOrigin of chinese characters 说文解字 298 征(徵) go on a long journey
Origin of chinese characters 说文解字 298 征(徵) go on a long journey
 
10. metonimias. construcciones simuladas
10. metonimias. construcciones simuladas10. metonimias. construcciones simuladas
10. metonimias. construcciones simuladas
 
Meaning of market segmentation
Meaning of market segmentationMeaning of market segmentation
Meaning of market segmentation
 
Forum du Livradois-Forez 2013 - Plénière - maison du tourisme - bilan des act...
Forum du Livradois-Forez 2013 - Plénière - maison du tourisme - bilan des act...Forum du Livradois-Forez 2013 - Plénière - maison du tourisme - bilan des act...
Forum du Livradois-Forez 2013 - Plénière - maison du tourisme - bilan des act...
 
SUMMARY
SUMMARYSUMMARY
SUMMARY
 
Asc
AscAsc
Asc
 
CV English
CV EnglishCV English
CV English
 
Searching for a job in Palestine
Searching for a job in Palestine Searching for a job in Palestine
Searching for a job in Palestine
 
OeRC_BioNatMedSciences_TeamOverview_Dec2013
OeRC_BioNatMedSciences_TeamOverview_Dec2013OeRC_BioNatMedSciences_TeamOverview_Dec2013
OeRC_BioNatMedSciences_TeamOverview_Dec2013
 
newsletter
newsletter newsletter
newsletter
 

Similar a Award-Winning Water Supply System Lowers Usage and Costs

Bond Financing & Eligible QECB Projects - UNC School of Government Environmen...
Bond Financing & Eligible QECB Projects - UNC School of Government Environmen...Bond Financing & Eligible QECB Projects - UNC School of Government Environmen...
Bond Financing & Eligible QECB Projects - UNC School of Government Environmen...
TNenergy
 
Houston Commercial Cooling Tower Case Study - Aug. 22 2016
Houston Commercial Cooling Tower Case Study - Aug. 22 2016Houston Commercial Cooling Tower Case Study - Aug. 22 2016
Houston Commercial Cooling Tower Case Study - Aug. 22 2016
Bevan Brinkley
 
Marion City Council Community Newsletter
Marion City Council Community NewsletterMarion City Council Community Newsletter
Marion City Council Community Newsletter
Grant Rench
 
High Efficiency Fitness Center
High Efficiency Fitness CenterHigh Efficiency Fitness Center
High Efficiency Fitness Center
rogers160
 
BULLITT CENTER, SEATTLE, WASHINGTON.pptx
BULLITT CENTER, SEATTLE, WASHINGTON.pptxBULLITT CENTER, SEATTLE, WASHINGTON.pptx
BULLITT CENTER, SEATTLE, WASHINGTON.pptx
PushpaHarshitha05
 

Similar a Award-Winning Water Supply System Lowers Usage and Costs (20)

EECBG Program Success
EECBG Program SuccessEECBG Program Success
EECBG Program Success
 
EECBG Program Success 2012
EECBG Program Success 2012EECBG Program Success 2012
EECBG Program Success 2012
 
Program and Policy Innovations at the Water Energy Nexus
Program and Policy Innovations at the Water Energy NexusProgram and Policy Innovations at the Water Energy Nexus
Program and Policy Innovations at the Water Energy Nexus
 
Bond Financing & Eligible QECB Projects - UNC School of Government Environmen...
Bond Financing & Eligible QECB Projects - UNC School of Government Environmen...Bond Financing & Eligible QECB Projects - UNC School of Government Environmen...
Bond Financing & Eligible QECB Projects - UNC School of Government Environmen...
 
Houston Commercial Cooling Tower Case Study - Aug. 22 2016
Houston Commercial Cooling Tower Case Study - Aug. 22 2016Houston Commercial Cooling Tower Case Study - Aug. 22 2016
Houston Commercial Cooling Tower Case Study - Aug. 22 2016
 
Optimized Operation of Indoor Public Pool Facilities
Optimized Operation of Indoor Public Pool FacilitiesOptimized Operation of Indoor Public Pool Facilities
Optimized Operation of Indoor Public Pool Facilities
 
dancookgcc2014
dancookgcc2014dancookgcc2014
dancookgcc2014
 
Case studies in residual use and energy conservation in wastewater treatment ...
Case studies in residual use and energy conservation in wastewater treatment ...Case studies in residual use and energy conservation in wastewater treatment ...
Case studies in residual use and energy conservation in wastewater treatment ...
 
Winter Springs 2023 Water and Wastewater Rate Study
Winter Springs 2023 Water and Wastewater Rate StudyWinter Springs 2023 Water and Wastewater Rate Study
Winter Springs 2023 Water and Wastewater Rate Study
 
2023 Winter Springs Water and Wastewater Rate Study Presentation
2023 Winter Springs Water and Wastewater Rate Study Presentation2023 Winter Springs Water and Wastewater Rate Study Presentation
2023 Winter Springs Water and Wastewater Rate Study Presentation
 
ISTC1
ISTC1ISTC1
ISTC1
 
Sustainable Water Savings for Irrigation Systems
Sustainable Water Savings for Irrigation SystemsSustainable Water Savings for Irrigation Systems
Sustainable Water Savings for Irrigation Systems
 
Palm Bay Utilities Update
Palm Bay Utilities UpdatePalm Bay Utilities Update
Palm Bay Utilities Update
 
Marion City Council Community Newsletter
Marion City Council Community NewsletterMarion City Council Community Newsletter
Marion City Council Community Newsletter
 
Jenna Ide GCC 2015
Jenna Ide GCC 2015Jenna Ide GCC 2015
Jenna Ide GCC 2015
 
Water and Energy Efficiency: The Next Big Thing
Water and Energy Efficiency: The Next Big ThingWater and Energy Efficiency: The Next Big Thing
Water and Energy Efficiency: The Next Big Thing
 
Laura van wie panel 3 - moderator
Laura van wie   panel 3 - moderatorLaura van wie   panel 3 - moderator
Laura van wie panel 3 - moderator
 
High Efficiency Fitness Center
High Efficiency Fitness CenterHigh Efficiency Fitness Center
High Efficiency Fitness Center
 
RHOK MKE - WaterTech Solution
RHOK MKE - WaterTech SolutionRHOK MKE - WaterTech Solution
RHOK MKE - WaterTech Solution
 
BULLITT CENTER, SEATTLE, WASHINGTON.pptx
BULLITT CENTER, SEATTLE, WASHINGTON.pptxBULLITT CENTER, SEATTLE, WASHINGTON.pptx
BULLITT CENTER, SEATTLE, WASHINGTON.pptx
 

Más de McKenney's Inc

Más de McKenney's Inc (20)

CRAC Units Installation for a Data Center Project in Alpharetta, GA
CRAC Units Installation for a Data Center Project in Alpharetta, GACRAC Units Installation for a Data Center Project in Alpharetta, GA
CRAC Units Installation for a Data Center Project in Alpharetta, GA
 
Mission Critical Data Center Retrofit Project - Catawaba County, NC
Mission Critical Data Center Retrofit Project - Catawaba County, NCMission Critical Data Center Retrofit Project - Catawaba County, NC
Mission Critical Data Center Retrofit Project - Catawaba County, NC
 
Generating a Reliable Backup Plan - Data Center Retrofit Project
Generating a Reliable Backup Plan - Data Center Retrofit ProjectGenerating a Reliable Backup Plan - Data Center Retrofit Project
Generating a Reliable Backup Plan - Data Center Retrofit Project
 
Performing a Cooling Transplant in Braselton, Georgia
Performing a Cooling Transplant in Braselton, GeorgiaPerforming a Cooling Transplant in Braselton, Georgia
Performing a Cooling Transplant in Braselton, Georgia
 
Lab Installation Cools Concerns - Federal Laboratory Renovation
Lab Installation Cools Concerns - Federal Laboratory RenovationLab Installation Cools Concerns - Federal Laboratory Renovation
Lab Installation Cools Concerns - Federal Laboratory Renovation
 
Blowing the Lid Off City Hall - Energy Savings Performance Contracting
Blowing the Lid Off City Hall - Energy Savings Performance ContractingBlowing the Lid Off City Hall - Energy Savings Performance Contracting
Blowing the Lid Off City Hall - Energy Savings Performance Contracting
 
Design/Build Mechanical Systems Projects - Atlanta, GA
Design/Build Mechanical Systems Projects - Atlanta, GADesign/Build Mechanical Systems Projects - Atlanta, GA
Design/Build Mechanical Systems Projects - Atlanta, GA
 
Building Relationships on the Double - Design/Build Mechanical Systems Projects
Building Relationships on the Double - Design/Build Mechanical Systems ProjectsBuilding Relationships on the Double - Design/Build Mechanical Systems Projects
Building Relationships on the Double - Design/Build Mechanical Systems Projects
 
Keeping the Fans Waving - Cooling Systems Replacement
Keeping the Fans Waving - Cooling Systems ReplacementKeeping the Fans Waving - Cooling Systems Replacement
Keeping the Fans Waving - Cooling Systems Replacement
 
A Breakout Turnkey HVAC Conversion - Turnkey Design/Build
A Breakout Turnkey HVAC Conversion - Turnkey Design/BuildA Breakout Turnkey HVAC Conversion - Turnkey Design/Build
A Breakout Turnkey HVAC Conversion - Turnkey Design/Build
 
Installation of Plumbing and HVAC systems - Hospitality Construction
Installation of Plumbing and HVAC systems - Hospitality ConstructionInstallation of Plumbing and HVAC systems - Hospitality Construction
Installation of Plumbing and HVAC systems - Hospitality Construction
 
Covering All the Bases - Plumbing and HVAC Systems Installation
Covering All the Bases - Plumbing and HVAC Systems InstallationCovering All the Bases - Plumbing and HVAC Systems Installation
Covering All the Bases - Plumbing and HVAC Systems Installation
 
Reducing Building Energy Consumption in Zero Energy Buildings (ZEB)
Reducing Building Energy Consumption in Zero Energy Buildings (ZEB)Reducing Building Energy Consumption in Zero Energy Buildings (ZEB)
Reducing Building Energy Consumption in Zero Energy Buildings (ZEB)
 
Turnkey Solution for an ESPC (Energy Savings Performance Contract) Project
Turnkey Solution for an ESPC (Energy Savings Performance Contract) ProjectTurnkey Solution for an ESPC (Energy Savings Performance Contract) Project
Turnkey Solution for an ESPC (Energy Savings Performance Contract) Project
 
McKenney’s, Inc. Critical Systems - High-Quality Mechanical Services for Miss...
McKenney’s, Inc. Critical Systems - High-Quality Mechanical Services for Miss...McKenney’s, Inc. Critical Systems - High-Quality Mechanical Services for Miss...
McKenney’s, Inc. Critical Systems - High-Quality Mechanical Services for Miss...
 
Efficient Solutions for Rainwater and Condensate Harvesting
Efficient Solutions for Rainwater and Condensate HarvestingEfficient Solutions for Rainwater and Condensate Harvesting
Efficient Solutions for Rainwater and Condensate Harvesting
 
Plumbing Preventive Maintenance in Commercial Buildings
Plumbing Preventive Maintenance in Commercial BuildingsPlumbing Preventive Maintenance in Commercial Buildings
Plumbing Preventive Maintenance in Commercial Buildings
 
McKenney’s, Inc. Interiors & Special Projects - Your Single Source for High-q...
McKenney’s, Inc. Interiors & Special Projects - Your Single Source for High-q...McKenney’s, Inc. Interiors & Special Projects - Your Single Source for High-q...
McKenney’s, Inc. Interiors & Special Projects - Your Single Source for High-q...
 
Creating a Showstopper in Charlotte - Mechanical Systems Installation
Creating a Showstopper in Charlotte - Mechanical Systems InstallationCreating a Showstopper in Charlotte - Mechanical Systems Installation
Creating a Showstopper in Charlotte - Mechanical Systems Installation
 
A Greener Hospital by Design
A Greener Hospital by DesignA Greener Hospital by Design
A Greener Hospital by Design
 

Award-Winning Water Supply System Lowers Usage and Costs

  • 1. PROJECT HIGHLIGHTS Award-Winning Water Supply System Lowers Usage and Costs T he Georgia Bureau of Investigation (GBI) headquarters in Decatur had been coping with high nonpotable water usage and costs to support systems fed by the county water supply. In fact, the GBI consumed 1,000,000 gallons month—costing $34,400 annually. From this information, they also developed a b ­ aseline meter reading for the winter months of just over 140,000 gallons per month. The source of the additional 230,000 gallons per month on average was then pinpointed —the cooling tower make-up water and ­rrigation systems. i To lessen county water usage, the GBI staff developed an inno­ vative alternative water capture s ­ ystem and enlisted McKenney’s engineering expertise and capa­ bilities to implement the system. It consisted of two cisterns with 10,000-gallon total storage capacity and an on-site well that pumps water to the cisterns. In “ cKenney’s also installed a pump, control addition, the system also tapped M into condensate water from air valves and piping to the cisterns …” ­ handlers in the GBI’s Annex during a typical hot August. Hoping to building and diverted rainwater from the reduce its water usage and its high costs, b ­ uilding’s roof to the cisterns. ­ cKenney’s M the GBI collaborated with McKenney’s to also installed a pump, control valves and implement a more feasible, affordable and p ­ iping to the cisterns to distribute the stored sustainable solution. water to the cooling tower make-up and ­irrigation systems. After several years of monitoring water usage and carefully analyzing the data, the With its new non-potable water supply GBI staff determined that they consumed s ­ ystem operating successfully, the GBI an average of 370,000 gallons of water a expects to achieve $20,000 in cost savings The content of this document is not intended as an endorsement. For more information contact McKenney’s at 404-622-5000. info@mckenneys.com   www.mckenneys.com McKenney’s, Inc.    1056 Moreland Industrial Boulevard, Atlanta, Georgia 30316 Project Team žž Owner: Georgia Bureau of I ­nvestigation and CBRE, Inc. žž Engineer: McKenney’s, Inc. The Challenge žž Calculate water usage and costs history žž Pinpoint source of excesses žž Devise supplemental water supply solution The Solution žž Dig an on-site well and install storage cisterns žž Capture condensate and r ­ ainwater for cisterns žž Pipe water from cisterns to cooling tower and irrigation systems The Results žž Cost savings of $20,000 annually žž Project earned 2013 GASFA ­Innovation Award žž System payback of four years annually, which allows the system to pay for itself in just four years. With such significant results—not only in cost savings but also reduced environmental impact—the project earned a 2013 Innovation Award from the Georgia Association of State Facilities Administrators (GASFA). It also paves the way for other state agencies with a high demand for non-­ otable water to enlist a p similar solution to lower water use and costs, provided it has the infrastructure to support an on-site well and water storage system. Copyright © 2013 McKenney’s, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A. McKenney’s, Inc. and the McKenney’s, Inc. logo are registered trademarks of McKenney’s, Inc. All other trademarks are the property of their respective owners.