SlideShare una empresa de Scribd logo
1 de 23
Challenge the future
Delft
University of
Technology
Stop criteria for proof load tests verified
with testing of the Ruytenschildt Bridge
Eva Lantsoght, Yuguang Yang, Cor van der Veen, Dick Hordijk, Ane de Boer
2
Overview
• Introduction to proof load testing
• Ruytenschildt Bridge testing: field and laboratory
• Analysis of stop criteria
• Summary & Conclusions
Slab shear experiments, TU Delft
3
Why load testing?
Bridges from 60s and 70s
The Hague in 1959
Increased live loads
common heavy and long truck (600 kN)
End of service life + larger loads
4
Proof load testing
• Target load – other research topic
• Stop criteria:
• Further loading not permitted
• Failure near
• Irreversible damage near
• Safe for bending moment AND shear?
MSc Thesis W. Vos
5
Existing Guidelines for proof loading
• Europe: DAfStB Richtlinie
• Stop criteria
• Concrete strain
• Steel strain
• Crack width and residual
crack width
• Residual deflection
• For flexure
• For buildings
6
Existing Guidelines for proof loading
• North America:
• Buildings: ACI 437.2M-13
• Bridges: Manual of Bridge
Rating Through Load
Testing (1998)
• ACI 437.2M-13 stop criteria:
• Residual deflection
• Permanency ratio
• Deviation from Linearity
Index
7
Ruytenschildt Bridge (1)
• Existing reinforced concrete slab
bridge (1962)
• Test to failure in two spans
• 4 concentrated load – one tandem
• Cyclic loading protocol
• Failure only achieved in span 2
• Failure test: analyse stop criteria and
determine margin of safety
8
Ruytenschildt Bridge (2)
Existing bridge Partial demolition and building new bridge
9
Test results
Span 1
• Maximum load 3049 kN
• Maximum available load for span 1
• Flexural cracks
• No failure
• Order additional load for test 2!
10
Test results
Span 2
• Maximum load 3991 kN
• Large flexural cracks
• Flexural failure
• yielding of reinforcement
• Settlement of bridge pier
with 1.5cm
• Elastic recovery to 8mm
11
Ruytenschildt Bridge (3)
12
Beams from Ruytenschildt Bridge
• Beams from Ruytenschildt Bridge
• Cyclic loading protocol
• Tests: Failure in shear and flexure
• Measurements:
• Lasers: deflection of beam
• LVDTs: crack opening
• Acoustic emission sensors
• Analyze stop criteria and determine
margin of safety
Beams RSB01 after failure (Yang, 2015)
Yang, Y. (2015). "Experimental Studies on the Structural Behaviours of Beams from Ruytenschildt Bridge,"
Stevin Report 25.5-15-09, Delft University of Technology, Delft, 76 pp.
Beams RSB02B after failure (Yang, 2015)
13
Comparison between stop criteria
and field test – German guideline
Criterion Plim (kN)
Span 1
Plim (kN)
Span 2
Strain 2719 3028
Increase in crack width >Pu >Pu
Residual crack width 481 418
Residual deformation (measured) 408 221
Residual deformation (zero) 474 3156
• Strain stop criterion: OK
• Increase in crack width: not exceeded
• Residual crack width and residual deformation: exceeded at first
load level (extremely conservative)
14
Comparison between stop criteria
and field test – ACI 437.2M-13
Criterion Plim (kN)
Span 1
Plim (kN)
Span 2
IDL, loading branch 1438 418 / 3156
IDL, unloading branch 1923 418 / 2657
Ipr 481 444
Residual deformation (measured) 780 3738
Residual deformation (zero) >Pu 3738
• Not very suitable when other loading protocol is used than what is
prescribed by ACI 437.2M-13
• Residual deformation after 24 hours: not practical for bridge
testing
15
Comparison between stop criteria
and field test – TU Delft proposal
Criterion Plim (kN)
Span 1
Plim (kN)
Span 2
Concrete strain 2719 3028
Maximum crack width >Pu >Pu
Residual crack width >Pu >Pu
Stiffness reduction (5%), loading branch 481 444
Stiffness reduction (5%), unloading branch 481 1492
Stiffness reduction (25%), loading branch 1923 3159
Stiffness reduction (25%), loading branch 1949 3159
Deformation profiles – longitudinal 1900 2600
Deformation profiles - transverse 1900 2600
• Based on this analysis: replace stiffness reduction (5% in original
proposal, now use 25%)
16
Comparison between stop criteria
and field test – TU Delft proposal
• Stiffness is determined based on loading and unloading branch
• Use deflection plots to check repeatability and linearity
17
Comparison between stop criteria
and lab test – German guideline
Criterion Plim (kN)
RSB01F
Plim (kN)
RSB02A
Plim (kN)
RSB02B
Plim (kN)
RSB03F
Plim (kN)
RSB03A
Strain 150 196 219 319 585
Increase in crack
width
274 Pu >Pu Pu >Pu
Residual crack width 77 76 74 147 >Pu
Residual deformation
(measured)
49 226 74 147 196
Residual deformation
(zero)
49 Pu 74 147 Pu
• Recommended: use strain stop criterion
• Other stop criteria: sometimes exceeded at very low load level
18
Comparison between stop criteria
and lab test – ACI 437.2M-13
Criterion Plim (kN)
RSB01F
Plim (kN)
RSB02A
Plim (kN)
RSB02B
Plim (kN)
RSB03F
Plim (kN)
RSB03A
IDL, loading 77 175 > Pu 293 390
IDL, unloading 77 175 >Pu 244 391
Ipr 75 126 125 293 196
Residual
deformation
(measured)
49 Pu 74 147 Pu
Residual
deformation
(zero)
50 Pu 74 Pu Pu
• Loading protocol should be same as in ACI 437.2M-13
• Requires force-controlled testing
• Residual deformation: large scatter
19
Comparison between stop criteria
and lab test – TU Delft proposal
Criterion Plim (kN)
RSB01F
Plim (kN)
RSB02A
Plim (kN)
RSB02B
Plim (kN)
RSB03F
Plim (kN)
RSB03A
Concrete strain 150 196 219 319 585
Max. crack width 274 > Pu > Pu Pu > Pu
Res. crack width 150 226 416 Pu > Pu
ΔEI (25%), L, laser
3
77 175 - - 391
ΔEI (25%), UL,
laser 3
103 175 - - 391
ΔEI (25%), L, laser
6
274 Pu > Pu 244 Pu
Stiffness reduction
(25%), UL, laser 6
150 >Pu > Pu 244 391
Def. prof. –
horizontal, N
150 225 175 Pu -
Def. prof. –
horizontal, S
- > Pu 175 342 -
Def. prof. – vertical 150 225 175 342 391
20
Comparison between stop criteria
and lab test – TU Delft proposal
• Different results for lasers 3 and 6 because beam was not sawn
straight
• “-” required sensor output not measured
• Ignore crack width smaller than 0.05 mm
• RSB01F: strong fluctuation of stiffness, possibly torsional distress
due to beam not being straight, stop criterion (stiffness) exceeded
at 28% of Pu
• RSB02A: stop criterion (stiffness) exceeded at 47% of Pu
• RSB02B: stop criterion (deformation profiles) exceeded at 42% of
Pu
• RSB03F: stop criterion (stiffness) exceeded at 41% of Pu
• RSB03A: stop criterion (displacement profiles) exceeded at 57%
of Pu
21
Recommended stop criteria
• Validation of stop criteria for
bending moment
• Not enough data for shear
• Field test: exceeded at 60 –
70% of max load
• Lab test: exceeded at 40 –
60% of max load (RSB01F
neglected)
22
Summary & Conclusions
• Ruytenschildt Bridge
• Existing slab bridge scheduled for
replacement
• Testing in 2 spans, failure in span 2
• Beams sawn and tested in lab
• Stop criteria
• When exceeded: margin of safety
• Comparison to German guideline and
ACI 437.2M-13
• Comparison to TU Delft proposal
• OK for bending moment
• More experiments necessary for shear
23
Contact:
Eva Lantsoght
E.O.L.Lantsoght@tudelft.nl // elantsoght@usfq.edu.ec
+31(0)152787449

Más contenido relacionado

Similar a Stop criteria for proof load tests verified with field and laboratory testing of the Ruytenschildt Bridge

Determination of loading protocol and stop criteria for proof loading with be...
Determination of loading protocol and stop criteria for proof loading with be...Determination of loading protocol and stop criteria for proof loading with be...
Determination of loading protocol and stop criteria for proof loading with be...Eva Lantsoght
 
Shear testing of prestressed concrete girders
Shear testing of prestressed concrete girdersShear testing of prestressed concrete girders
Shear testing of prestressed concrete girdersEva Lantsoght
 
Proof load testing in the Netherlands - overview of current research
Proof load testing in the Netherlands - overview of current researchProof load testing in the Netherlands - overview of current research
Proof load testing in the Netherlands - overview of current researchEva Lantsoght
 
Proposed stop criteria for proof load testing of concrete bridges and verific...
Proposed stop criteria for proof load testing of concrete bridges and verific...Proposed stop criteria for proof load testing of concrete bridges and verific...
Proposed stop criteria for proof load testing of concrete bridges and verific...Eva Lantsoght
 
Applying Experimental Results to the Shear Assessment Method for Solid Slab B...
Applying Experimental Results to the Shear Assessment Method for Solid Slab B...Applying Experimental Results to the Shear Assessment Method for Solid Slab B...
Applying Experimental Results to the Shear Assessment Method for Solid Slab B...Eva Lantsoght
 
Extending service life of existing bridges
Extending service life of existing bridgesExtending service life of existing bridges
Extending service life of existing bridgesEva Lantsoght
 
Recommendations for the Shear Assessment of Reinforced Concrete Solid Slab Br...
Recommendations for the Shear Assessment of Reinforced Concrete Solid Slab Br...Recommendations for the Shear Assessment of Reinforced Concrete Solid Slab Br...
Recommendations for the Shear Assessment of Reinforced Concrete Solid Slab Br...Eva Lantsoght
 
Shear and moment capacity of the Ruytenschildt Bridge
Shear and moment capacity of the Ruytenschildt BridgeShear and moment capacity of the Ruytenschildt Bridge
Shear and moment capacity of the Ruytenschildt BridgeEva Lantsoght
 
Shear and Moment Capacity of the Ruytenschildt Bridge
Shear and Moment Capacity of the Ruytenschildt BridgeShear and Moment Capacity of the Ruytenschildt Bridge
Shear and Moment Capacity of the Ruytenschildt BridgeEva Lantsoght
 
Application of Modified Bond Model to the capacity of Ruytenschildt Bridge
Application of Modified Bond Model to the capacity of Ruytenschildt BridgeApplication of Modified Bond Model to the capacity of Ruytenschildt Bridge
Application of Modified Bond Model to the capacity of Ruytenschildt BridgeEva Lantsoght
 
Assessment of slab bridges through proof loading in the Netherlands
Assessment of slab bridges through proof loading in the NetherlandsAssessment of slab bridges through proof loading in the Netherlands
Assessment of slab bridges through proof loading in the NetherlandsEva Lantsoght
 
BriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOAD
BriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOADBriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOAD
BriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOADmichael mabrouk
 
Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...
Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...
Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...Eva Lantsoght
 
Assessment of the Shear Capacity of Existing Reinforced Concrete Solid Slab B...
Assessment of the Shear Capacity of Existing Reinforced Concrete Solid Slab B...Assessment of the Shear Capacity of Existing Reinforced Concrete Solid Slab B...
Assessment of the Shear Capacity of Existing Reinforced Concrete Solid Slab B...Eva Lantsoght
 
Shear tests of reinforced concrete slabs and slab strips under concentrated l...
Shear tests of reinforced concrete slabs and slab strips under concentrated l...Shear tests of reinforced concrete slabs and slab strips under concentrated l...
Shear tests of reinforced concrete slabs and slab strips under concentrated l...Eva Lantsoght
 
Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...
Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...
Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...Ruud Arkesteijn
 
Shear in Reinforced Concrete Slabs under Concentrated Loads close to Supports
Shear in Reinforced Concrete Slabs under Concentrated Loads close to SupportsShear in Reinforced Concrete Slabs under Concentrated Loads close to Supports
Shear in Reinforced Concrete Slabs under Concentrated Loads close to SupportsEva Lantsoght
 
Extended Strip Model for slabs subjected to a combination of loads
Extended Strip Model for slabs subjected to a combination of loadsExtended Strip Model for slabs subjected to a combination of loads
Extended Strip Model for slabs subjected to a combination of loadsEva Lantsoght
 
Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...
Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...
Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...Ruud Arkesteijn
 
Load testing of reinforced concrete bridges in the Netherlands
Load testing of reinforced concrete bridges in the NetherlandsLoad testing of reinforced concrete bridges in the Netherlands
Load testing of reinforced concrete bridges in the NetherlandsEva Lantsoght
 

Similar a Stop criteria for proof load tests verified with field and laboratory testing of the Ruytenschildt Bridge (20)

Determination of loading protocol and stop criteria for proof loading with be...
Determination of loading protocol and stop criteria for proof loading with be...Determination of loading protocol and stop criteria for proof loading with be...
Determination of loading protocol and stop criteria for proof loading with be...
 
Shear testing of prestressed concrete girders
Shear testing of prestressed concrete girdersShear testing of prestressed concrete girders
Shear testing of prestressed concrete girders
 
Proof load testing in the Netherlands - overview of current research
Proof load testing in the Netherlands - overview of current researchProof load testing in the Netherlands - overview of current research
Proof load testing in the Netherlands - overview of current research
 
Proposed stop criteria for proof load testing of concrete bridges and verific...
Proposed stop criteria for proof load testing of concrete bridges and verific...Proposed stop criteria for proof load testing of concrete bridges and verific...
Proposed stop criteria for proof load testing of concrete bridges and verific...
 
Applying Experimental Results to the Shear Assessment Method for Solid Slab B...
Applying Experimental Results to the Shear Assessment Method for Solid Slab B...Applying Experimental Results to the Shear Assessment Method for Solid Slab B...
Applying Experimental Results to the Shear Assessment Method for Solid Slab B...
 
Extending service life of existing bridges
Extending service life of existing bridgesExtending service life of existing bridges
Extending service life of existing bridges
 
Recommendations for the Shear Assessment of Reinforced Concrete Solid Slab Br...
Recommendations for the Shear Assessment of Reinforced Concrete Solid Slab Br...Recommendations for the Shear Assessment of Reinforced Concrete Solid Slab Br...
Recommendations for the Shear Assessment of Reinforced Concrete Solid Slab Br...
 
Shear and moment capacity of the Ruytenschildt Bridge
Shear and moment capacity of the Ruytenschildt BridgeShear and moment capacity of the Ruytenschildt Bridge
Shear and moment capacity of the Ruytenschildt Bridge
 
Shear and Moment Capacity of the Ruytenschildt Bridge
Shear and Moment Capacity of the Ruytenschildt BridgeShear and Moment Capacity of the Ruytenschildt Bridge
Shear and Moment Capacity of the Ruytenschildt Bridge
 
Application of Modified Bond Model to the capacity of Ruytenschildt Bridge
Application of Modified Bond Model to the capacity of Ruytenschildt BridgeApplication of Modified Bond Model to the capacity of Ruytenschildt Bridge
Application of Modified Bond Model to the capacity of Ruytenschildt Bridge
 
Assessment of slab bridges through proof loading in the Netherlands
Assessment of slab bridges through proof loading in the NetherlandsAssessment of slab bridges through proof loading in the Netherlands
Assessment of slab bridges through proof loading in the Netherlands
 
BriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOAD
BriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOADBriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOAD
BriefTHE EFFECT OF CREATED OPENING UNDER WORKING LOAD
 
Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...
Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...
Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...
 
Assessment of the Shear Capacity of Existing Reinforced Concrete Solid Slab B...
Assessment of the Shear Capacity of Existing Reinforced Concrete Solid Slab B...Assessment of the Shear Capacity of Existing Reinforced Concrete Solid Slab B...
Assessment of the Shear Capacity of Existing Reinforced Concrete Solid Slab B...
 
Shear tests of reinforced concrete slabs and slab strips under concentrated l...
Shear tests of reinforced concrete slabs and slab strips under concentrated l...Shear tests of reinforced concrete slabs and slab strips under concentrated l...
Shear tests of reinforced concrete slabs and slab strips under concentrated l...
 
Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...
Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...
Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...
 
Shear in Reinforced Concrete Slabs under Concentrated Loads close to Supports
Shear in Reinforced Concrete Slabs under Concentrated Loads close to SupportsShear in Reinforced Concrete Slabs under Concentrated Loads close to Supports
Shear in Reinforced Concrete Slabs under Concentrated Loads close to Supports
 
Extended Strip Model for slabs subjected to a combination of loads
Extended Strip Model for slabs subjected to a combination of loadsExtended Strip Model for slabs subjected to a combination of loads
Extended Strip Model for slabs subjected to a combination of loads
 
Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...
Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...
Presentation for lecture on underwater concrete - TU Delft: MSc Geotechnical ...
 
Load testing of reinforced concrete bridges in the Netherlands
Load testing of reinforced concrete bridges in the NetherlandsLoad testing of reinforced concrete bridges in the Netherlands
Load testing of reinforced concrete bridges in the Netherlands
 

Más de Eva Lantsoght

Coneic presentation 2020
Coneic presentation 2020Coneic presentation 2020
Coneic presentation 2020Eva Lantsoght
 
Pruebas de cortante en vigas postensadas
Pruebas de cortante en vigas postensadasPruebas de cortante en vigas postensadas
Pruebas de cortante en vigas postensadasEva Lantsoght
 
Pruebas de carga en puentes de hormigón armado
Pruebas de carga en puentes de hormigón armadoPruebas de carga en puentes de hormigón armado
Pruebas de carga en puentes de hormigón armadoEva Lantsoght
 
El futuro del hormigon
El futuro del hormigonEl futuro del hormigon
El futuro del hormigonEva Lantsoght
 
Load testing of structures
Load testing of structuresLoad testing of structures
Load testing of structuresEva Lantsoght
 
The road to breaking bridges and stereotypes
The road to breaking bridges and stereotypesThe road to breaking bridges and stereotypes
The road to breaking bridges and stereotypesEva Lantsoght
 
Load rating using load testing: introducing the new bridge load testing e-cir...
Load rating using load testing: introducing the new bridge load testing e-cir...Load rating using load testing: introducing the new bridge load testing e-cir...
Load rating using load testing: introducing the new bridge load testing e-cir...Eva Lantsoght
 
Como evaluar la capacidad de puentes de hormigón existentes?
Como evaluar la capacidad de puentes de hormigón existentes?Como evaluar la capacidad de puentes de hormigón existentes?
Como evaluar la capacidad de puentes de hormigón existentes?Eva Lantsoght
 
Inspeccion, mantenimiento y evaluacion de puentes de hormigon
Inspeccion, mantenimiento y evaluacion de puentes de hormigonInspeccion, mantenimiento y evaluacion de puentes de hormigon
Inspeccion, mantenimiento y evaluacion de puentes de hormigonEva Lantsoght
 
10 Planning Concepts I wish I'd known Before my PhD
10 Planning Concepts I wish I'd known Before my PhD10 Planning Concepts I wish I'd known Before my PhD
10 Planning Concepts I wish I'd known Before my PhDEva Lantsoght
 
Diagnostic load testing of bridges - case studies
Diagnostic load testing of bridges - case studies Diagnostic load testing of bridges - case studies
Diagnostic load testing of bridges - case studies Eva Lantsoght
 
Load testing of structures
Load testing of structuresLoad testing of structures
Load testing of structuresEva Lantsoght
 
Proof load testing of viaduct De Beek
Proof load testing of viaduct De BeekProof load testing of viaduct De Beek
Proof load testing of viaduct De BeekEva Lantsoght
 
Sound in engineering
Sound in engineeringSound in engineering
Sound in engineeringEva Lantsoght
 
Pruebas de carga en puentes de hormigon armado
Pruebas de carga en puentes de hormigon armado Pruebas de carga en puentes de hormigon armado
Pruebas de carga en puentes de hormigon armado Eva Lantsoght
 
Proof load testing of the viaduct De Beek
Proof load testing of the viaduct De BeekProof load testing of the viaduct De Beek
Proof load testing of the viaduct De BeekEva Lantsoght
 
Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...Eva Lantsoght
 
Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...Eva Lantsoght
 
Reliability index after proof load testing: viaduct De Beek
Reliability index after proof load testing: viaduct De BeekReliability index after proof load testing: viaduct De Beek
Reliability index after proof load testing: viaduct De BeekEva Lantsoght
 

Más de Eva Lantsoght (20)

Coneic presentation 2020
Coneic presentation 2020Coneic presentation 2020
Coneic presentation 2020
 
Pruebas de cortante en vigas postensadas
Pruebas de cortante en vigas postensadasPruebas de cortante en vigas postensadas
Pruebas de cortante en vigas postensadas
 
Pruebas de carga en puentes de hormigón armado
Pruebas de carga en puentes de hormigón armadoPruebas de carga en puentes de hormigón armado
Pruebas de carga en puentes de hormigón armado
 
El futuro del hormigon
El futuro del hormigonEl futuro del hormigon
El futuro del hormigon
 
Load testing of structures
Load testing of structuresLoad testing of structures
Load testing of structures
 
The road to breaking bridges and stereotypes
The road to breaking bridges and stereotypesThe road to breaking bridges and stereotypes
The road to breaking bridges and stereotypes
 
Load rating using load testing: introducing the new bridge load testing e-cir...
Load rating using load testing: introducing the new bridge load testing e-cir...Load rating using load testing: introducing the new bridge load testing e-cir...
Load rating using load testing: introducing the new bridge load testing e-cir...
 
Como evaluar la capacidad de puentes de hormigón existentes?
Como evaluar la capacidad de puentes de hormigón existentes?Como evaluar la capacidad de puentes de hormigón existentes?
Como evaluar la capacidad de puentes de hormigón existentes?
 
Inspeccion, mantenimiento y evaluacion de puentes de hormigon
Inspeccion, mantenimiento y evaluacion de puentes de hormigonInspeccion, mantenimiento y evaluacion de puentes de hormigon
Inspeccion, mantenimiento y evaluacion de puentes de hormigon
 
10 Planning Concepts I wish I'd known Before my PhD
10 Planning Concepts I wish I'd known Before my PhD10 Planning Concepts I wish I'd known Before my PhD
10 Planning Concepts I wish I'd known Before my PhD
 
Diagnostic load testing of bridges - case studies
Diagnostic load testing of bridges - case studies Diagnostic load testing of bridges - case studies
Diagnostic load testing of bridges - case studies
 
Load testing of structures
Load testing of structuresLoad testing of structures
Load testing of structures
 
Proof load testing of viaduct De Beek
Proof load testing of viaduct De BeekProof load testing of viaduct De Beek
Proof load testing of viaduct De Beek
 
CV Eva Lantsoght
CV Eva LantsoghtCV Eva Lantsoght
CV Eva Lantsoght
 
Sound in engineering
Sound in engineeringSound in engineering
Sound in engineering
 
Pruebas de carga en puentes de hormigon armado
Pruebas de carga en puentes de hormigon armado Pruebas de carga en puentes de hormigon armado
Pruebas de carga en puentes de hormigon armado
 
Proof load testing of the viaduct De Beek
Proof load testing of the viaduct De BeekProof load testing of the viaduct De Beek
Proof load testing of the viaduct De Beek
 
Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...
 
Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...Recommendations for proof load testing of reinforced concrete slab bridges - ...
Recommendations for proof load testing of reinforced concrete slab bridges - ...
 
Reliability index after proof load testing: viaduct De Beek
Reliability index after proof load testing: viaduct De BeekReliability index after proof load testing: viaduct De Beek
Reliability index after proof load testing: viaduct De Beek
 

Último

Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...DianaGray10
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessPixlogix Infotech
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CVKhem
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdflior mazor
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobeapidays
 

Último (20)

Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your Business
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 

Stop criteria for proof load tests verified with field and laboratory testing of the Ruytenschildt Bridge

  • 1. Challenge the future Delft University of Technology Stop criteria for proof load tests verified with testing of the Ruytenschildt Bridge Eva Lantsoght, Yuguang Yang, Cor van der Veen, Dick Hordijk, Ane de Boer
  • 2. 2 Overview • Introduction to proof load testing • Ruytenschildt Bridge testing: field and laboratory • Analysis of stop criteria • Summary & Conclusions Slab shear experiments, TU Delft
  • 3. 3 Why load testing? Bridges from 60s and 70s The Hague in 1959 Increased live loads common heavy and long truck (600 kN) End of service life + larger loads
  • 4. 4 Proof load testing • Target load – other research topic • Stop criteria: • Further loading not permitted • Failure near • Irreversible damage near • Safe for bending moment AND shear? MSc Thesis W. Vos
  • 5. 5 Existing Guidelines for proof loading • Europe: DAfStB Richtlinie • Stop criteria • Concrete strain • Steel strain • Crack width and residual crack width • Residual deflection • For flexure • For buildings
  • 6. 6 Existing Guidelines for proof loading • North America: • Buildings: ACI 437.2M-13 • Bridges: Manual of Bridge Rating Through Load Testing (1998) • ACI 437.2M-13 stop criteria: • Residual deflection • Permanency ratio • Deviation from Linearity Index
  • 7. 7 Ruytenschildt Bridge (1) • Existing reinforced concrete slab bridge (1962) • Test to failure in two spans • 4 concentrated load – one tandem • Cyclic loading protocol • Failure only achieved in span 2 • Failure test: analyse stop criteria and determine margin of safety
  • 8. 8 Ruytenschildt Bridge (2) Existing bridge Partial demolition and building new bridge
  • 9. 9 Test results Span 1 • Maximum load 3049 kN • Maximum available load for span 1 • Flexural cracks • No failure • Order additional load for test 2!
  • 10. 10 Test results Span 2 • Maximum load 3991 kN • Large flexural cracks • Flexural failure • yielding of reinforcement • Settlement of bridge pier with 1.5cm • Elastic recovery to 8mm
  • 12. 12 Beams from Ruytenschildt Bridge • Beams from Ruytenschildt Bridge • Cyclic loading protocol • Tests: Failure in shear and flexure • Measurements: • Lasers: deflection of beam • LVDTs: crack opening • Acoustic emission sensors • Analyze stop criteria and determine margin of safety Beams RSB01 after failure (Yang, 2015) Yang, Y. (2015). "Experimental Studies on the Structural Behaviours of Beams from Ruytenschildt Bridge," Stevin Report 25.5-15-09, Delft University of Technology, Delft, 76 pp. Beams RSB02B after failure (Yang, 2015)
  • 13. 13 Comparison between stop criteria and field test – German guideline Criterion Plim (kN) Span 1 Plim (kN) Span 2 Strain 2719 3028 Increase in crack width >Pu >Pu Residual crack width 481 418 Residual deformation (measured) 408 221 Residual deformation (zero) 474 3156 • Strain stop criterion: OK • Increase in crack width: not exceeded • Residual crack width and residual deformation: exceeded at first load level (extremely conservative)
  • 14. 14 Comparison between stop criteria and field test – ACI 437.2M-13 Criterion Plim (kN) Span 1 Plim (kN) Span 2 IDL, loading branch 1438 418 / 3156 IDL, unloading branch 1923 418 / 2657 Ipr 481 444 Residual deformation (measured) 780 3738 Residual deformation (zero) >Pu 3738 • Not very suitable when other loading protocol is used than what is prescribed by ACI 437.2M-13 • Residual deformation after 24 hours: not practical for bridge testing
  • 15. 15 Comparison between stop criteria and field test – TU Delft proposal Criterion Plim (kN) Span 1 Plim (kN) Span 2 Concrete strain 2719 3028 Maximum crack width >Pu >Pu Residual crack width >Pu >Pu Stiffness reduction (5%), loading branch 481 444 Stiffness reduction (5%), unloading branch 481 1492 Stiffness reduction (25%), loading branch 1923 3159 Stiffness reduction (25%), loading branch 1949 3159 Deformation profiles – longitudinal 1900 2600 Deformation profiles - transverse 1900 2600 • Based on this analysis: replace stiffness reduction (5% in original proposal, now use 25%)
  • 16. 16 Comparison between stop criteria and field test – TU Delft proposal • Stiffness is determined based on loading and unloading branch • Use deflection plots to check repeatability and linearity
  • 17. 17 Comparison between stop criteria and lab test – German guideline Criterion Plim (kN) RSB01F Plim (kN) RSB02A Plim (kN) RSB02B Plim (kN) RSB03F Plim (kN) RSB03A Strain 150 196 219 319 585 Increase in crack width 274 Pu >Pu Pu >Pu Residual crack width 77 76 74 147 >Pu Residual deformation (measured) 49 226 74 147 196 Residual deformation (zero) 49 Pu 74 147 Pu • Recommended: use strain stop criterion • Other stop criteria: sometimes exceeded at very low load level
  • 18. 18 Comparison between stop criteria and lab test – ACI 437.2M-13 Criterion Plim (kN) RSB01F Plim (kN) RSB02A Plim (kN) RSB02B Plim (kN) RSB03F Plim (kN) RSB03A IDL, loading 77 175 > Pu 293 390 IDL, unloading 77 175 >Pu 244 391 Ipr 75 126 125 293 196 Residual deformation (measured) 49 Pu 74 147 Pu Residual deformation (zero) 50 Pu 74 Pu Pu • Loading protocol should be same as in ACI 437.2M-13 • Requires force-controlled testing • Residual deformation: large scatter
  • 19. 19 Comparison between stop criteria and lab test – TU Delft proposal Criterion Plim (kN) RSB01F Plim (kN) RSB02A Plim (kN) RSB02B Plim (kN) RSB03F Plim (kN) RSB03A Concrete strain 150 196 219 319 585 Max. crack width 274 > Pu > Pu Pu > Pu Res. crack width 150 226 416 Pu > Pu ΔEI (25%), L, laser 3 77 175 - - 391 ΔEI (25%), UL, laser 3 103 175 - - 391 ΔEI (25%), L, laser 6 274 Pu > Pu 244 Pu Stiffness reduction (25%), UL, laser 6 150 >Pu > Pu 244 391 Def. prof. – horizontal, N 150 225 175 Pu - Def. prof. – horizontal, S - > Pu 175 342 - Def. prof. – vertical 150 225 175 342 391
  • 20. 20 Comparison between stop criteria and lab test – TU Delft proposal • Different results for lasers 3 and 6 because beam was not sawn straight • “-” required sensor output not measured • Ignore crack width smaller than 0.05 mm • RSB01F: strong fluctuation of stiffness, possibly torsional distress due to beam not being straight, stop criterion (stiffness) exceeded at 28% of Pu • RSB02A: stop criterion (stiffness) exceeded at 47% of Pu • RSB02B: stop criterion (deformation profiles) exceeded at 42% of Pu • RSB03F: stop criterion (stiffness) exceeded at 41% of Pu • RSB03A: stop criterion (displacement profiles) exceeded at 57% of Pu
  • 21. 21 Recommended stop criteria • Validation of stop criteria for bending moment • Not enough data for shear • Field test: exceeded at 60 – 70% of max load • Lab test: exceeded at 40 – 60% of max load (RSB01F neglected)
  • 22. 22 Summary & Conclusions • Ruytenschildt Bridge • Existing slab bridge scheduled for replacement • Testing in 2 spans, failure in span 2 • Beams sawn and tested in lab • Stop criteria • When exceeded: margin of safety • Comparison to German guideline and ACI 437.2M-13 • Comparison to TU Delft proposal • OK for bending moment • More experiments necessary for shear
  • 23. 23 Contact: Eva Lantsoght E.O.L.Lantsoght@tudelft.nl // elantsoght@usfq.edu.ec +31(0)152787449