CONSTRUCCIÓN DEL GASODUCTO GIBRALTAR – BUCARAMANGA 29‐07‐2011
                             RESUMEN DE AVANCE POR NIVEL DE PROGRAMACION
                              PESO         ACUM ANTERIOR         EJEC. PERIODO           ACUM . PREVISTO
      DESCRIPCION
                                        P. TEMPR   EJECUT.   PROG.        EJECUT.   P. TEMPR       EJECUT.
      TOTAL PROYECTO          100,0%      99,25%    98,23%   0,75%         0,08%     100,00%         98,31%
COMPLETACIÓN MEC.             99,25%      99,25%    98,23%                 0,61%      99,25%         98,84%
TRAMO 1                       53,56%     100,00%    98,43%                 0,11%     100,00%         98,54%
TRAMO 2                       44,81%     100,00%    99,97%                           100,00%         99,97%
CULMINACIÓN MEC
              MEC.            100,00%
                              100 00%    100,00%
                                         100 00%    69,03%
                                                    69 03%                 2,40%
                                                                           2 40%     100,00%
                                                                                     100 00%         71,43%
                                                                                                     71 43%
TRAMO 1                       90,92%     100,00%    69,52%                 2,08%     100,00%         71,60%
CRUCE RIO CUBUGON             13,30%     100,00%    78,80%                 9,74%     100,00%         88,55%
ESTRUCTURA LANZAM.             2,28%     100,00%   100,00%                           100,00%        100,00%
ESTRUCTURA PUENTE             10,06%     100,00%    81,52%                12,88%     100,00%         94,40%
SECTOR 1 PK 4+750 - 2+170     15,93%
                              15 93%     100,00%
                                         100 00%    61,97%
                                                    61 97%                 0,73%
                                                                           0 73%     100,00%
                                                                                     100 00%         62,70%
                                                                                                     62 70%
CRUCE AEREO RIO NEGRO          2,17%     100,00%    97,50%                           100,00%         97,50%
SECTOR 2 PK25+170 - 58+380    12,85%     100,00%    63,81%                 2,94%     100,00%         66,75%
LIM. CAL. PK 25 PK 35          1,48%     100,00%   100,00%                           100,00%        100,00%
LIM. CAL. PK 35 PK 58          0,92%     100,00%   100,00%                           100,00%        100,00%
PRUEBA NEUMATICA T1S2          1,26%
                               1 26%     100,00%
                                         100 00%    30,00%
                                                    30 00%                10,01%
                                                                          10 01%     100,00%
                                                                                     100 00%         40,01%
                                                                                                     40 01%
SECTOR 3 PK58+380 - 77+804    48,25%     100,00%    71,24%                0,88%      100,00%         72,12%
INST. TUB. PK60 - 64          20,71%     100,00%    98,27%                0,19%      100,00%         98,47%
CRUCE AEREO DE CHERELA         2,29%     100,00%   100,00%                           100,00%        100,00%
CRUCE AEREO DE PELUCO          4,51%     100,00%    99,18%                 0,82%     100,00%        100,00%
CRUCE AEREO DE CHIPARA          ,
                               2,70%     100,00%
                                             ,      97,72%
                                                       ,                   2,28%
                                                                            ,        100,00%
                                                                                         ,          100,00%
                                                                                                         ,
LIM. CAL. PK 58 PK 77          2,78%     100,00%   100,00%                           100,00%        100,00%
PRUEBA NEUMATICA T1S3          1,37%     100,00%    13,33%                23,49%     100,00%         36,82%
INSTRUMENTACIÓN                0,43%     100,00%    64,58%                           100,00%         64,58%
TRAMO 2                        5,72%     100,00%    96,52%                           100,00%         96,52%
EMPAL. CRUCE A. PK140+188      0,81%     100,00%   100,00%                           100,00%        100,00%
PRUEBAS DE PRESIÓN             1,36%     100,00%   100,00%                           100,00%        100,00%
PAQ. 7 PK153 149+445           0,15%     100,00%   100,00%                           100,00%        100,00%
PAQ. 8 PK149+445 148+020       0,24%     100,00%   100,00%                           100,00%        100,00%
PAQ. 9 PK148+020 145+640       0,33%     100,00%   100,00%                           100,00%        100,00%
PAQ. 10 PK145+640 137+600      0,64%     100,00%   100,00%                           100,00%        100,00%
SECADO DE LA LINEA             0,67%     100,00%   100,00%                           100,00%        100,00%
SECADO PK175+670 153+000       0,27%     100,00%   100,00%                           100,00%        100,00%
SECADO PK153+000 137+600       0,40%     100,00%   100,00%                           100,00%        100,00%
INSTRUMENTACIÓN                0,72%     100,00%    64,63%                20,75%     100,00%         85,38%
IMPL.FORMATOS CHECK LIST       2,34%     100,00%     9,99%                           100,00%          9,99%
CONSTRUCCIÓN DEL GASODUCTO GIBRALTAR – BUCARAMANGA 29‐07‐2011
                                                                Curva de Progreso Fisico COMPLETACIÓN MECÁNICA
                 101,00%




                                                                                                                                                                                                           100,00%
                 100,00%




                 99,00%
                                                                                                                                                                                                                           98,84%
Título del eje




                 98,00%




                 97,00%
                 97 00%                                                                                                                                                            REPROGRAMACION
                                                                                                                                                                                   PRO‐INICIAL
                                                                                                                                                                                   TARDIA
                                                                                                                                                                                   REPROGRAMACION 2 TARDIA
                                                                                                                                                                                   REPROGRAMACIÓN 2 TEMPRANA
                 96,00%
                 96 00%
                                                                                                                                                                                   EJECUTADO
                                                                                                                                                                                   Reprogramacion 3 temprana
                                                                                                                                                                                   Reprogramacion 3 Tardia



                 95,00%
                 95 00%
                           15/abr/11



                                       22/abr/11



                                                   29/abr/11




                                                                                                              3/jun/11




                                                                                                                                                             1/jul/11



                                                                                                                                                                        8/jul/11




                                                                                                                                                                                                                                5/ago/11
                                                                          13/may/11



                                                                                      20/may/11



                                                                                                  27/may/11




                                                                                                                         10/jun/11



                                                                                                                                     17/jun/11



                                                                                                                                                 24/jun/11




                                                                                                                                                                                   15/jul/11



                                                                                                                                                                                               22/jul/11



                                                                                                                                                                                                               29/jul/11
                                                               6/may/11
CONSTRUCCIÓN DEL GASODUCTO GIBRALTAR – BUCARAMANGA 04‐08‐2011

Más contenido relacionado

Destacado

Filling the Data Lake - Strata + HadoopWorld San Jose 2016 Preview Presentation
Filling the Data Lake - Strata + HadoopWorld San Jose 2016 Preview PresentationFilling the Data Lake - Strata + HadoopWorld San Jose 2016 Preview Presentation
Filling the Data Lake - Strata + HadoopWorld San Jose 2016 Preview PresentationPentaho
 
Data Mashups for Analytics
Data Mashups for AnalyticsData Mashups for Analytics
Data Mashups for AnalyticsPentaho
 
Netaji subhash chandra bose PPT in hindi
Netaji subhash chandra bose PPT in hindiNetaji subhash chandra bose PPT in hindi
Netaji subhash chandra bose PPT in hindiAbhishek Dev
 
Julius Caesar - PPT
Julius Caesar - PPTJulius Caesar - PPT
Julius Caesar - PPTAbhishek Dev
 
LINEAR EQUATION IN TWO VARIABLES PPT
LINEAR EQUATION  IN  TWO VARIABLES PPTLINEAR EQUATION  IN  TWO VARIABLES PPT
LINEAR EQUATION IN TWO VARIABLES PPTAbhishek Dev
 

Destacado (8)

Filling the Data Lake - Strata + HadoopWorld San Jose 2016 Preview Presentation
Filling the Data Lake - Strata + HadoopWorld San Jose 2016 Preview PresentationFilling the Data Lake - Strata + HadoopWorld San Jose 2016 Preview Presentation
Filling the Data Lake - Strata + HadoopWorld San Jose 2016 Preview Presentation
 
Data Mashups for Analytics
Data Mashups for AnalyticsData Mashups for Analytics
Data Mashups for Analytics
 
Ozymandias PPT
Ozymandias PPTOzymandias PPT
Ozymandias PPT
 
Patol babu PPT
Patol babu PPTPatol babu PPT
Patol babu PPT
 
Netaji subhash chandra bose PPT in hindi
Netaji subhash chandra bose PPT in hindiNetaji subhash chandra bose PPT in hindi
Netaji subhash chandra bose PPT in hindi
 
A shady plot PPT
A shady plot PPTA shady plot PPT
A shady plot PPT
 
Julius Caesar - PPT
Julius Caesar - PPTJulius Caesar - PPT
Julius Caesar - PPT
 
LINEAR EQUATION IN TWO VARIABLES PPT
LINEAR EQUATION  IN  TWO VARIABLES PPTLINEAR EQUATION  IN  TWO VARIABLES PPT
LINEAR EQUATION IN TWO VARIABLES PPT
 

Similar a Avance proyecto gasoducto gibraltar bucaramanga 29 07-11

Terracerias... septiembre 2012 (corte al 07 sep-2012)
Terracerias... septiembre 2012 (corte al 07 sep-2012)Terracerias... septiembre 2012 (corte al 07 sep-2012)
Terracerias... septiembre 2012 (corte al 07 sep-2012)Luis Hernandez Arevalo
 
Analytics Code.Google.Com P Hdd40 20080826 20090925 (Geo Map Report)
Analytics Code.Google.Com P Hdd40 20080826 20090925 (Geo Map Report)Analytics Code.Google.Com P Hdd40 20080826 20090925 (Geo Map Report)
Analytics Code.Google.Com P Hdd40 20080826 20090925 (Geo Map Report)Grupo Herramienta de Documentalista
 
Ya paso la tormenta trend shopper exma - noviembre de 2017
Ya paso la tormenta   trend shopper exma - noviembre de 2017Ya paso la tormenta   trend shopper exma - noviembre de 2017
Ya paso la tormenta trend shopper exma - noviembre de 2017Camilo Herrera
 
Presentación de investigacion
Presentación de investigacionPresentación de investigacion
Presentación de investigaciongestionhumanaredes
 
Tarifas aereas ams_mia_semanas_43_52
Tarifas aereas ams_mia_semanas_43_52Tarifas aereas ams_mia_semanas_43_52
Tarifas aereas ams_mia_semanas_43_52rosanamaisincho
 
Tabulador mano de obra 01 de enero 2020
Tabulador mano de obra 01 de enero 2020Tabulador mano de obra 01 de enero 2020
Tabulador mano de obra 01 de enero 2020JoseHernandez1409
 
Tabulador mano de obra 01 de enero 2020
Tabulador mano de obra 01 de enero 2020Tabulador mano de obra 01 de enero 2020
Tabulador mano de obra 01 de enero 2020JoseHernandez1409
 
Estado de la salud visual en colombia
Estado de la salud visual en colombiaEstado de la salud visual en colombia
Estado de la salud visual en colombiasoniaxmo
 
Correlación ejercicio 2
Correlación ejercicio 2Correlación ejercicio 2
Correlación ejercicio 2jullio-rmz10
 
Cuadro Comparativo De Inversion Publicitaria Argentina 2008 Versus 2007
Cuadro Comparativo De Inversion Publicitaria Argentina 2008 Versus 2007Cuadro Comparativo De Inversion Publicitaria Argentina 2008 Versus 2007
Cuadro Comparativo De Inversion Publicitaria Argentina 2008 Versus 2007Juan Varela
 
Normalizacion de registros
Normalizacion de registrosNormalizacion de registros
Normalizacion de registrosLucía Jara
 

Similar a Avance proyecto gasoducto gibraltar bucaramanga 29 07-11 (20)

Terracerias... septiembre 2012 (corte al 07 sep-2012)
Terracerias... septiembre 2012 (corte al 07 sep-2012)Terracerias... septiembre 2012 (corte al 07 sep-2012)
Terracerias... septiembre 2012 (corte al 07 sep-2012)
 
Analytics Code.Google.Com P Hdd40 20080826 20090925 (Geo Map Report)
Analytics Code.Google.Com P Hdd40 20080826 20090925 (Geo Map Report)Analytics Code.Google.Com P Hdd40 20080826 20090925 (Geo Map Report)
Analytics Code.Google.Com P Hdd40 20080826 20090925 (Geo Map Report)
 
Cuenta Pública Jueves 28/03/2013
Cuenta Pública Jueves 28/03/2013Cuenta Pública Jueves 28/03/2013
Cuenta Pública Jueves 28/03/2013
 
Epi info
Epi infoEpi info
Epi info
 
Epi info
Epi infoEpi info
Epi info
 
Ya paso la tormenta trend shopper exma - noviembre de 2017
Ya paso la tormenta   trend shopper exma - noviembre de 2017Ya paso la tormenta   trend shopper exma - noviembre de 2017
Ya paso la tormenta trend shopper exma - noviembre de 2017
 
Diapositivas babyfruticos
Diapositivas babyfruticosDiapositivas babyfruticos
Diapositivas babyfruticos
 
026 situacion bacteria - panama 2011
026   situacion bacteria - panama 2011026   situacion bacteria - panama 2011
026 situacion bacteria - panama 2011
 
Direccion financiera
Direccion financieraDireccion financiera
Direccion financiera
 
Modelo de inventario ABC
Modelo de inventario ABCModelo de inventario ABC
Modelo de inventario ABC
 
Presentación de investigacion
Presentación de investigacionPresentación de investigacion
Presentación de investigacion
 
Tarifas aereas ams_mia_semanas_43_52
Tarifas aereas ams_mia_semanas_43_52Tarifas aereas ams_mia_semanas_43_52
Tarifas aereas ams_mia_semanas_43_52
 
Tabulador mano de obra 01 de enero 2020
Tabulador mano de obra 01 de enero 2020Tabulador mano de obra 01 de enero 2020
Tabulador mano de obra 01 de enero 2020
 
Tabulador mano de obra 01 de enero 2020
Tabulador mano de obra 01 de enero 2020Tabulador mano de obra 01 de enero 2020
Tabulador mano de obra 01 de enero 2020
 
Estado de la salud visual en colombia
Estado de la salud visual en colombiaEstado de la salud visual en colombia
Estado de la salud visual en colombia
 
Correlación ejercicio 2
Correlación ejercicio 2Correlación ejercicio 2
Correlación ejercicio 2
 
Cuadro Comparativo De Inversion Publicitaria Argentina 2008 Versus 2007
Cuadro Comparativo De Inversion Publicitaria Argentina 2008 Versus 2007Cuadro Comparativo De Inversion Publicitaria Argentina 2008 Versus 2007
Cuadro Comparativo De Inversion Publicitaria Argentina 2008 Versus 2007
 
IMPLEMENTACIÓN
IMPLEMENTACIÓN IMPLEMENTACIÓN
IMPLEMENTACIÓN
 
Graficas estadisticas
Graficas estadisticasGraficas estadisticas
Graficas estadisticas
 
Normalizacion de registros
Normalizacion de registrosNormalizacion de registros
Normalizacion de registros
 

Avance proyecto gasoducto gibraltar bucaramanga 29 07-11

  • 1. CONSTRUCCIÓN DEL GASODUCTO GIBRALTAR – BUCARAMANGA 29‐07‐2011 RESUMEN DE AVANCE POR NIVEL DE PROGRAMACION PESO ACUM ANTERIOR EJEC. PERIODO ACUM . PREVISTO DESCRIPCION P. TEMPR EJECUT. PROG. EJECUT. P. TEMPR EJECUT. TOTAL PROYECTO 100,0% 99,25% 98,23% 0,75% 0,08% 100,00% 98,31% COMPLETACIÓN MEC. 99,25% 99,25% 98,23% 0,61% 99,25% 98,84% TRAMO 1 53,56% 100,00% 98,43% 0,11% 100,00% 98,54% TRAMO 2 44,81% 100,00% 99,97% 100,00% 99,97% CULMINACIÓN MEC MEC. 100,00% 100 00% 100,00% 100 00% 69,03% 69 03% 2,40% 2 40% 100,00% 100 00% 71,43% 71 43% TRAMO 1 90,92% 100,00% 69,52% 2,08% 100,00% 71,60% CRUCE RIO CUBUGON 13,30% 100,00% 78,80% 9,74% 100,00% 88,55% ESTRUCTURA LANZAM. 2,28% 100,00% 100,00% 100,00% 100,00% ESTRUCTURA PUENTE 10,06% 100,00% 81,52% 12,88% 100,00% 94,40% SECTOR 1 PK 4+750 - 2+170 15,93% 15 93% 100,00% 100 00% 61,97% 61 97% 0,73% 0 73% 100,00% 100 00% 62,70% 62 70% CRUCE AEREO RIO NEGRO 2,17% 100,00% 97,50% 100,00% 97,50% SECTOR 2 PK25+170 - 58+380 12,85% 100,00% 63,81% 2,94% 100,00% 66,75% LIM. CAL. PK 25 PK 35 1,48% 100,00% 100,00% 100,00% 100,00% LIM. CAL. PK 35 PK 58 0,92% 100,00% 100,00% 100,00% 100,00% PRUEBA NEUMATICA T1S2 1,26% 1 26% 100,00% 100 00% 30,00% 30 00% 10,01% 10 01% 100,00% 100 00% 40,01% 40 01% SECTOR 3 PK58+380 - 77+804 48,25% 100,00% 71,24% 0,88% 100,00% 72,12% INST. TUB. PK60 - 64 20,71% 100,00% 98,27% 0,19% 100,00% 98,47% CRUCE AEREO DE CHERELA 2,29% 100,00% 100,00% 100,00% 100,00% CRUCE AEREO DE PELUCO 4,51% 100,00% 99,18% 0,82% 100,00% 100,00% CRUCE AEREO DE CHIPARA , 2,70% 100,00% , 97,72% , 2,28% , 100,00% , 100,00% , LIM. CAL. PK 58 PK 77 2,78% 100,00% 100,00% 100,00% 100,00% PRUEBA NEUMATICA T1S3 1,37% 100,00% 13,33% 23,49% 100,00% 36,82% INSTRUMENTACIÓN 0,43% 100,00% 64,58% 100,00% 64,58% TRAMO 2 5,72% 100,00% 96,52% 100,00% 96,52% EMPAL. CRUCE A. PK140+188 0,81% 100,00% 100,00% 100,00% 100,00% PRUEBAS DE PRESIÓN 1,36% 100,00% 100,00% 100,00% 100,00% PAQ. 7 PK153 149+445 0,15% 100,00% 100,00% 100,00% 100,00% PAQ. 8 PK149+445 148+020 0,24% 100,00% 100,00% 100,00% 100,00% PAQ. 9 PK148+020 145+640 0,33% 100,00% 100,00% 100,00% 100,00% PAQ. 10 PK145+640 137+600 0,64% 100,00% 100,00% 100,00% 100,00% SECADO DE LA LINEA 0,67% 100,00% 100,00% 100,00% 100,00% SECADO PK175+670 153+000 0,27% 100,00% 100,00% 100,00% 100,00% SECADO PK153+000 137+600 0,40% 100,00% 100,00% 100,00% 100,00% INSTRUMENTACIÓN 0,72% 100,00% 64,63% 20,75% 100,00% 85,38% IMPL.FORMATOS CHECK LIST 2,34% 100,00% 9,99% 100,00% 9,99%
  • 2. CONSTRUCCIÓN DEL GASODUCTO GIBRALTAR – BUCARAMANGA 29‐07‐2011 Curva de Progreso Fisico COMPLETACIÓN MECÁNICA 101,00% 100,00% 100,00% 99,00% 98,84% Título del eje 98,00% 97,00% 97 00% REPROGRAMACION PRO‐INICIAL TARDIA REPROGRAMACION 2 TARDIA REPROGRAMACIÓN 2 TEMPRANA 96,00% 96 00% EJECUTADO Reprogramacion 3 temprana Reprogramacion 3 Tardia 95,00% 95 00% 15/abr/11 22/abr/11 29/abr/11 3/jun/11 1/jul/11 8/jul/11 5/ago/11 13/may/11 20/may/11 27/may/11 10/jun/11 17/jun/11 24/jun/11 15/jul/11 22/jul/11 29/jul/11 6/may/11