Diagrama de gantt
1. Nombre de
Actividad Fecha Inicio
Duración
en días Fecha Fin
A 1-may. 10 10-may.
B 2-may. 3 4-may.
C 3-may. 16 18-may.
D 4-may. 9 12-may.
E 5-may. 3 7-may.
F 6-may. 4 9-may.
G 7-may. 9 15-may.
H 8-may. 15 22-may.
I 9-may. 6 14-may.
J 10-may. 12 21-may.
Inicio Proyecto 43586,00
Fin Proyecto 43607,00
1-may. 4-may. 7-may. 10-may. 13-may. 16-may. 19-may. 22-may.
A
B
C
D
E
F
G
H
I
J
DIAGRAMA DE GANTT