In this construction sequence of a CFRD dam you will be able to quickly notice the excavation for plinth/foundations that must be carried out first from the top down (volumes in red). Then, rock filling and civil works of plinths and concrete face can be carried out simultaneously, this sequence presentation gives emphasis to the concrete face that will be in contact with the water. This project was developed in Ecuador (2005-2009) , its name is Mazar Hydroelectric Project. The construction was executed by Impregilo (now Webuild). I devoloped this model from a TIN surface generated in Eagle Point software, and later I generated the parametric and adaptative solids in Autodesk Inventor (version 5). You could wonder why Inventor, I am mechanical Engineer, and I saw the construction process like and a special assembly, with special processes, methodologies, technologies. And I love to integrate all these when I try to solve problems.