1. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
INFORME DE ACTIVIDADES
MES DE NOVIEMBRE 2018
DEPARTAMENTO
DE PROYECTOS
2. ÍNDICE
C O N S T R U C C I Ó N D E R E D E L É C T R I C A ( P R I M E R E T A P A ) , C O L O N I A P E D R E G A L , Z O N A
C E N T R O N O R T E , E N E L M U N I C I P I O D E A L T A M I R A , T A M A U L I P A S .
R E E N C A R P E T A D O A S F Á L T I C O D E 5 C M E N C A L L E F U N D O L E G A L E N T R E C A L L E L A G U N A
D E C H A M P A Y Á N Y C A L L E P E D R O J . M É N D E Z , C O L O N I A R E V O L U C I Ó N V E R D E , Z O N A
C E N T R O , E N E L M U N I C I P I O D E A L T A M I R A , T A M A U L I P A S .
P A V I M E N T A C I Ó N D E C O N C R E T O A S F Á L T I C O E N C A L L E R Í O P Á N U C O , E N T R E C A L L E 2 Y
R Í O P A P A L O A P A N , C A L L E R Í O P Á N U C O , E N T R E C A L L E 4 Y C A L L E 2 , E N L A C O L O N I A
R Í O T A M I A H U A , E N E L M U N I C I P I O D E A L T A M I R A , T A M A U L I P A S .
R E E E N C A R P E T A D O A S F Á L T I C O D E 5 C M D E E S P E S O R E N C A L L E B E N I T O J U Á R E Z
E N T R E C A R R E T E R A T A M P I C O - M A N T E Y C A L L E F U N D A D O R E S , E N E L E J I D O B E N I T O
J U Á R E Z , Z O N A R U R A L , E N E L M U N I C I P I O D E A L T A M I R A , T A M A U L I P A S .
P A V I M E N T A C I Ó N D E C O N C R E T O A S F Á L T I C O E N C A M I N O A E J I D O J O S É M A R Í A L U I S
M O R A , Z O N A R U R A L , E N E L M U N I C I P I O D E A L T A M I R A , T A M A U L I P A S .
P A V I M E N T A C I Ó N D E C O N C R E T O H I D R Á U L I C O Y A L U M B R A D O P Ú B L I C O E N V I A L I D A D P D ,
E N T R E C A L L E R E A L D E L P R A D O O R I E N T E Y L I S B O A Y C A L L E L I S B O A E N T R E V I A L I D A D
P D , Y N A V A R R A , F R A C C I O N A M I E N T O L A S H A C I E N D A S , Z O N A L A G U N A D E L A P U E R T A ,
E N E L M U N I C I P I O D E A L T A M I R A , T A M A U L I P A S .
C O N S T R U C C I Ó N D E 5 R E C Á M A R A S C O N B A Ñ O D E 5 . 0 0 X 4 . 0 0 M , E N L A S C O L O N I A S
N U E V O M A D E R O Y S E C - 2 , Z O N A M I R A M A R , E N E L M U N I C I P I O D E A L T A M I R A
T A M A U L I P A S .
C O N S T R U C C I Ó N D E 5 R E C Á M A R A S C O N B A Ñ O D E 5 . 0 0 X 4 . 0 0 M , E N L A S C O L O N I A S
B R I S A S , L O M A S D E A L T A M I R A Y L O M A S D E M I R A L T A , Z O N A M O N T E A L T O , E N E L
M U N I C I P I O D E A L T A M I R A T A M A U L I P A S .
C O N S T R U C C I Ó N D E 5 R E C Á M A R A S C O N B A Ñ O D E 5 . 0 0 X 4 . 0 0 M , E N L A S C O L O N I A S L A S
A D E L I T A S Y M U N I C I P I O S L I B R E S , Z O N A L A G U N A D E L A P U E R T A , E N E L M U N I C I P I O D E
A L T A M I R A T A M A U L I P A S .
C O N S T R U C C I Ó N D E D R E N P L U V I A L R E C T A N G U L A R D E L C A D . 0 + 0 0 0 . 0 0 A L C A D .
0 + 0 9 0 . 0 0 E N C A L L E M I G U E L H I D A L G O , E N E L E J I D O R I C A R D O F L O R E S M A G Ó N , E N E L
M U N I C I P I O D E A L T A M I R A T A M A U L I P A S .
C O N S T R U C C I Ó N D E D R E N P L U V I A L E N C A L L E C - 7 S U R , E N T R E C A L L E C - 7 P O N I E N T E Y
Á R E A V E R D E , F R A C C . C O R R E D O R I N D U S T R I A L , Z O N A L A G U N A D E L A P U E R T A , E N E L
M U N I C I P I O D E A L T A M I R A T A M A U L I P A S .
C O N S T R U C C I Ó N D E T E R R A C E R Í A S P A R A E S T R U C T U R A D E V E L A T O R I O Y
E S T A C I O N A M I E N T O E N C A L L E A G U S T Í N D E I T U R B I D E E N T R E D I A G O N A L C A V A Z O S
L E R M A Y B O U L E V A R D I G N A C I O A L L E N D E , E N Z O N A C E N T R O , E N E L M U N I C I P I O D E
A L T A M I R A T A M A U L I P A S .
C O N S T R U C C I Ó N D E N U E V O T R A M O D E L Í N E A M E D I A T E N S I Ó N A É R E A 3 F A S E S , 4 H I L O S
E N E L C I R C U I T O M T Y - 5 1 7 0 , U B I C A D O E N E L E J I D O E S T E R O S , Z O N A R U R A L , E N E L
M U N I C I P I O D E A L T A M I R A T A M A U L I P A S .
NOVIEMBRE 2018
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
3. y
REPORTE FOTOGRÁFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
FECHA DESCRIPCIÓN
OCTUBRE
2018
CONSTRUCCIÓN DE RED ELÉCTRICA (PRIMER ETAPA), COLONIA
PEDREGAL, ZONA CENTRO NORTE, EN EL MUNICIPIO DE ALTAMIRA,
TAMAULIPAS.
PROYECTO: ( C O N S T R U C C I Ó N D E R E D E L É C T R I C A )
4. y
REPORTE FOTOGRÁFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
PROYECTO: ( R E E N C A R P E TA D O A S F Á LT I C O )
FECHA DESCRIPCIÓN
OCTUBRE
2018
REENCARPETADO ASFÁLTICO DE 5 CM EN CALLE FUNDO LEGAL
ENTRE CALLE LAGUNA DE CHAMPAYÁN Y CALLE PEDRO J. MÉNDEZ,
COLONIA REVOLUCIÓN VERDE, ZONA CENTRO, EN EL MUNICIPIO
DE ALTAMIRA, TAMAULIPAS.
5. y
REPORTE FOTOGRÁFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
PROYECTO: ( PAV I M E N TAC I Ó N D E C O N C R E TO
A S F Á LT I C O )
FECHA DESCRIPCIÓN
OCTUBRE
2018
PAVIMENTACIÓN DE CONCRETO ASFÁLTICO EN CALLE RÍO
PÁNUCO, ENTRE CALLE 2 Y RÍO PAPALOAPAN, CALLE RÍO PÁNUCO,
ENTRE CALLE 4 Y CALLE 2, EN LA COLONIA RÍO TAMIAHUA, EN EL
MUNICIPIO DE ALTAMIRA, TAMAULIPAS.
6. y
REPORTE FOTOGRÁFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
PROYECTO: ( R E E N C A R P E TA D O A S F Á LT I C O )
FECHA DESCRIPCIÓN
OCTUBRE
2018
REEENCARPETADO ASFÁLTICO DE 5 CM DE ESPESOR EN CALLE
BENITO JUÁREZ ENTRE CARRETERA TAMPICO-MANTE Y CALLE
FUNDADORES, EN EL EJIDO BENITO JUÁREZ, ZONA RURAL, EN EL
MUNICIPIO DE ALTAMIRA, TAMAULIPAS.
7. y
REPORTE FOTOGRÁFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
PROYECTO: ( PAV I M E N TAC I Ó N D E C O N C R E TO
A S F Á LT I C O )
FECHA DESCRIPCIÓN
OCTUBRE
2018
PAVIMENTACIÓN DE CONCRETO ASFÁLTICO EN CAMINO A EJIDO
JOSÉ MARÍA LUIS MORA, ZONA RURAL, EN EL MUNICIPIO DE
ALTAMIRA, TAMAULIPAS.
8. y
REPORTE FOTOGRÁFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
PROYECTO: ( PAV I M E N TAC I Ó N D E C O N C R E TO
H I D R Á U L I C O )
FECHA DESCRIPCIÓN
OCTUBRE
2018
PAVIMENTACIÓN DE CONCRETO HIDRÁULICO Y ALUMBRADO
PÚBLICO EN VIALIDAD PD, ENTRE CALLE REAL DEL PRADO ORIENTE Y
LISBOA Y CALLE LISBOA ENTRE VIALIDAD PD, Y NAVARRA,
FRACCIONAMIENTO LAS HACIENDAS, ZONA LAGUNA DE LA
PUERTA, EN EL MUNICIPIO DE ALTAMIRA, TAMAULIPAS.
9. y
REPORTE FOTOGRÁFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
PROYECTO: ( C O N S T R U C C I Ó N D E C I N C O R E C Á M A R A S )
FECHA DESCRIPCIÓN
OCTUBRE
2018
CONSTRUCCIÓN DE 5 RECÁMARAS CON BAÑO DE 5.00 x 4.00 M,
EN LAS COLONIAS NUEVO MADERO Y SEC-2, ZONA MIRAMAR, EN
EL MUNICIPIO DE ALTAMIRA TAMAULIPAS.
10. y
REPORTE FOTOGRÁFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
PROYECTO: ( C O N S T R U C C I Ó N D E C I N C O R E C Á M A R A S )
FECHA DESCRIPCIÓN
OCTUBRE
2018
CONSTRUCCIÓN DE 5 RECÁMARAS CON BAÑO DE 5.00 x 4.00 M,
EN LAS COLONIAS BRISAS, LOMAS DE ALTAMIRA Y LOMAS DE
MIRALTA, ZONA MONTE ALTO, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
11. y
REPORTE FOTOGRÁFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
PROYECTO: ( C O N S T R U C C I Ó N D E C I N C O R E C Á M A R A S )
FECHA DESCRIPCIÓN
OCTUBRE
2018
CONSTRUCCIÓN DE 5 RECÁMARAS CON BAÑO DE 5.00 x 4.00 M,
EN LAS COLONIAS LAS ADELITAS Y MUNICIPIOS LIBRES, ZONA
LAGUNA DE LA PUERTA, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
12. y
REPORTE FOTOGRÁFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
PROYECTO: ( C O N S T R U C C I Ó N D E D R E N P LU V I A L )
FECHA DESCRIPCIÓN
OCTUBRE
2018
CONSTRUCCIÓN DE DREN PLUVIAL RECTANGULAR DEL CAD.
0+000.00 AL CAD. 0+090.00 EN CALLE MIGUEL HIDALGO, EN EL
EJIDO RICARDO FLORES MAGÓN, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
13. y
REPORTE FOTOGRÁFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
PROYECTO: ( C O N S T R U C C I Ó N D E D R E N P LU V I A L )
FECHA DESCRIPCIÓN
OCTUBRE
2018
CONSTRUCCIÓN DE DREN PLUVIAL EN CALLE C-7 SUR, ENTRE CALLE
C-7 PONIENTE Y ÁREA VERDE, FRACC. CORREDOR INDUSTRIAL,
ZONA LAGUNA DE LA PUERTA, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
14. y
REPORTE FOTOGRÁFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
PROYECTO: ( C O N S T R U C C I Ó N D E T E R R A C E R Í A S )
FECHA DESCRIPCIÓN
OCTUBRE
2018
CONSTRUCCIÓN DE TERRACERÍAS PARA ESTRUCTURA DE
VELATORIO Y ESTACIONAMIENTO EN CALLE AGUSTÍN DE ITURBIDE
ENTRE DIAGONAL CAVAZOS LERMA Y BOULEVARD IGNACIO
ALLENDE, EN ZONA CENTRO, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
15. y
REPORTE FOTOGRÁFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
PROYECTO: ( C O N S T R U C C I Ó N D E L Í N E A D E M E D I A
T E N S I Ó N )
FECHA DESCRIPCIÓN
OCTUBRE
2018
CONSTRUCCIÓN DE NUEVO TRAMO DE LÍNEA MEDIA TENSIÓN
AÉREA 3 FASES, 4 HILOS EN EL CIRCUITO MTY-5170, UBICADO EN
EL EJIDO ESTEROS, ZONA RURAL, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
16. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
INFORME DE
ACTIVIDADES
MES DE
SEPTIEMBRE
OCTUBRE
NOVIEMBRE
2018
DPTO DE
PROYECTOS
ESTRATÉGICOS
17. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
INDICE
P L A N O P R O P U E S T A D E R U T A S D E E V A C U A C I Ó N Y S E Ñ A L E T I C A P A R A E L
O B R A S P Ú B L I C A S D E A L T A M I R A .
P L A N O P R O P U E S T A D E R U T A S D E E V A C U A C I Ó N , O B R A S P U B L I C A S
A L T A M I R A . P L A N O G E N E R A L , P L A N T A B A J A , P L A N T A A L T A
B A R D A P A R A E S C U E L A P R I M A R I A J O S É M A R I A M O R E L O S E N E L E J I D O E L
R E P E C H O
P R O P U E S T A D E C O M E D O R P A R A O B R A S P U B L I C A S , A L T A M I R A .
P R O Y E C T O F I N A L D E C O M E D O R D E O B R A S P Ú B L I C A S .
A L I N E A M I E N T O D E P A S O D E S E R V I D U M B R E ( A C C E S O A O B R A S P Ú B L I C A S )
P R O P U E S T A P A R A P U E N T E S P E A T O N A L E S Y P A R A D E R O S E N Z O N A
A L T A M I R A .
D O C U M E N T O S Q U E S E O B T U V I E R O N P A R A P R O Y E C T O S D I V E R S O S .
( D O C U M E N T A C I Ó N F I S I C A Y E L E C T R Ó N I C A ) .
A N T E P R O Y E C T O : P A V I M E N T A C I Ó N D E L A A V E N I D A M O N T E R R E Y , E N T R E
B O U L E V A R D P U E R T O I N D U S T R I A L Y C A L L E Z A R A G O Z A , E N Z O N A C E N T R O
A L T A M I R A .
A N T E P R O Y E C T O : C O N S T R U C C I Ó N D E P U E N T E P E A T O N A L A D Y A C E N T E A
P U E N T E V E H I C U L A R D E B O U L E V A R D A L L E N D E .
P R O P U E S T A D E P U E N T E S P E A T O N A L E S Y P A R A D E R O S .
D O C U M E N T A C I O N P A R A C O M I T É Y C O M I S I Ó N P A R A L O S P R O C E D I M I E N T O S
D E C O N C U R S O Y C O N T R A T A C I Ó N D E O P .
P R O Y E C T O D E L D R E N D E L A R E T A M A D E N T R O D E L C O M P L E J O
A D M I N I S T R A T I V O
P R O Y E C T O P R O P U E S T A D E P A R Q U E - A N D A D O R E N D R E N C A V A Z O S , Z O N A
C E N T R O A L T A M I R A .
C U A N T I F I C A C I Ó N D E P I N T U R A P A R A E L E D I F I C I O D E S I S T E M A D I F . C A S A
D E L A D U L T O M A Y O R .
D I S T R I B U C I Ó N V E H I C U L A R P A R A L A S O F I C I N A S D E O B R A S P U B L I C A S .
P R O P U E S T A D E F A C H A D A P A R A L A C A S A D E L A D U L T O M A Y O R .
T E R R A C E R Í A S P A R A D R E N E L E D É N E N Z O N A C E N T R O D E A L T A M I R A .
SEP.- OCT- NOV
18. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
SEP
2018
PLANO PROPUESTA DE RUTAS DE EVACUACIÓN
Y SEÑALETICA PARA EL OBRAS PÚBLICAS DE
ALTAMIRA.
REPORTE FOTOGRÁFICO
PROYECTO: P L A N O P R O P U E S T A D E R U T A S
D E E V A C U A C I Ó N , O B R A S P U B L I C A S
A L T A M I R A .
CONSTRUCCIÓN ACTUAL
PROYECTO PROPUESTA EN PROCESO
19. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
SEP
2018
PLANO PROPUESTA DE RUTAS DE
EVACUACIÓN Y SEÑALETICA PARA EL
DEPARTAMENTO DE OBRAS PÚBLICAS DE
ALTAMIRA. PLANTA BAJA.
REPORTE FOTOGRÁFICO
PROYECTO: P L A N O P R O P U E S T A D E R U A S
D E E V A C U A C I Ó N , O B R A S P U B L I C A S
A L T A M I R A .
CONSTRUCCIÓN ACTUAL
PROYECTO PROPUESTA EN PROCESO
PLANTA BAJA
20. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
SEP
2018
PLANO PROPUESTA DE RUTAS DE EVACUACIÓN
Y SEÑALETICA PARA EL DEPARTAMENTO DE
OBRAS PÚBLICAS DE ALTAMIRA. PLANTA ALTA.
REPORTE FOTOGRÁFICO
PROYECTO: P L A N O P P O P U E S T A D E R U T A S
D E E V A C U A C I Ó N , O B R A S P U B L I C A S
A L T A M I R A .
CONSTRUCCIÓN ACTUAL
PROYECTO PROPUESTA EN PROCESO
PLANTA ALTA
21. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
SEP
2018
PROYECTO DE BARDA PARA ESCUELA
PRIMARIA JOSÉ MARIA MORELOS EN EL EJIDO
EL REPECHO.
REPORTE FOTOGRÁFICO
PROYECTO: B A R D A P A R A E S C U E L A
P R I M A R I A J O S É M A R I A M O R E L O S E N E L
E J I D O E L R E P E C H O
ESTADO ACTUAL
BARDA
UBICACIÓN
22. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
SEP
2018
PROPUESTA DE COMEDOR PARA EL
DEPARTAMENTO DE OBRAS PUBLICAS.
ALTAMIRA.
REPORTE FOTOGRÁFICO
PROYECTO: P R O P U E S T A D E C O M E D O R
P A R A O B R A S P U B L I C A S , A L T A M I R A .
CONSTRUCCIÓN ACTUAL
PROYECTO
PROPUESTA
DE SITIO
23. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
OCT
2018
PROYECTO DE COMEDOR DE OBRAS PÚBLICAS
DOCUMENTACIÓN
PROYECTO: P R O Y E C T O D E C O M E D O R
D E O B R A S P Ú B L I C A S .
PROYECTO DE COMEDOR PARA OBRAS PÚBLICAS DE
ALTAMIRA.
CUENTA CON :
-ÁREA DE COCINA.
-ÁREA DE COMEDOR
CUPO PARA 32 PERSONAS
ZONA DE COMEDOR
24. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
SEP
2018
ALINEAMIENTO DE PASO DE SERVIDUMBRE
(ACCESO A OBRAS PÚBLICAS).
REPORTE FOTOGRÁFICO
–ELABORACIÓN DE PLANO DE ALINEAMIENTO.
–PLANO PARA MOVIMIENTO DE POSTE DE C.F.E.
PROYECTO: A L I N E A M I E N T O D E P A S O D E
S E R V I D U M B R E ( A C C E S O A O B R A S P Ú B L I C A S )
ELABORACIÓN
PROYECTO
POSTE
C.F.E.
25. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
SEP
2018
PROPUESTA PARA REALIZAR PROYECTOS
DE PUENTES PEATONALES Y PARADEROS.
REPORTE
PROYECTO: P R O P U E S T A P A R A P U E N T E S
P E A T O N A L E S Y P A R A D E R O S E N Z O N A
A L T A M I R A .
PROPUESTA DE ZONAS
Puentes Peatonales zona Urbana.
a) Col. Alameda
b) Arteli vía.
c) Cementerio municipal. Zona centro
Altamira.
d) Col. Francisco Villa.
e) La morita
f) Monte alto.
g) Náutico
h) Arteli norte
Puentes peatonales zona Rural.
a) Río Tamiahua 40.
b) Esteros
c) Villa Cuauhtémoc.
d) Maclovio Herrera.
Techumbre “Paraderos de Autobuses”.
a) Cementerio Municipal. Zona centro
Altamira. Norte-Sur.
b) La Morita Sur-Norte.
c) Col. Francisco Villa Norte-Sur.
d) Náutico Sur-Norte.
26. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
SEP-OCT
2018
ELABORACIÓN DE ACTAS Y FORMATOS DE
LAS SESIONES MENSUALES DEL COMITÉ.
DOCUMENTACIÓN
PROYECTO: D O C U M E N T O S Q U E S E
O B T U V I E R O N P A R A P R O Y E C T O S D I V E R S O S .
( D O C U M E N T A C I Ó N F I S I C A Y E L E C T R Ó N I C A ) .
1.- Comité y comisión. (Para los Procedimientos de
Concurso y Contratación de Obras Públicas y Servicios
Relacionados con las Mismas de la Dirección de Obras y
Servicios Públicos del Municipio de Altamira).
Elaboración de convocatorias para sesiones del
comité.
Elaboración de actas las sesiones mensuales del
comité.
Elaboración de las actas de las sesiones
extraordinarias del Comité.
27. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
SEP-OCT
2018
DOCUMENTOS QUE SE OBTUVIERON PARA
PROYECTOS DIVERSOS. (DOCUMENTACIÓN
FISICA Y ELECTRÓNICA).
DOCUMENTACIÓN
PROYECTO:D O C U M E N T O S Q U E S E
O B T U V I E R O N P A R A P R O Y E C T O S D I V E R S O S .
( D O C U M E N T A C I Ó N F I S I C A Y E L E C T R Ó N I C A ) .
1. REVISIÓN DE CERTEZA JURÍDICA DE LOS
TERRENOS QUE RESULTAN AFECTADOS POR EL
PROYECTO DE CANAL DE CD LOMAS DE ROSALES
(EN PROCESO)
2. REVISIÓN DE INSTALACIONES PETROLERAS,
CADENAMIENTOS EN EL DERECHO DE VÍA
MADERO, CADEREYTA. TRAMO COL. LAURELES
SANTO DOMINGO PARA PROYECTAR VIALIDAD
ALTERNATIVA (EN PROCESO).
3. CONTINUIDAD EN ACTUALIZACIÓN DE PLANO
MUNICIPAL. PARA INSERCIÓN DE
LEVANTAMIENTOS FISICOS (COORDENADOAS
U.T.M. EN PROCESO).
28. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
OCT
2018
Ante Proyecto: Pavimentación de la Avenida
Monterrey, entre Boulevard Puerto Industrial y
Calle Zaragoza, en Zona Centro Altamira.
DOCUMENTACIÓN
PROYECTO: A N T E P R O Y E C T O :
P A V I M E N T A C I Ó N D E L A A V E N I D A M O N T E R R E Y ,
E N T R E B O U L E V A R D P U E R T O I N D U S T R I A L Y C A L L E
Z A R A G O Z A , E N Z O N A C E N T R O A L T A M I R A .
2.- Ante Proyecto: Pavimentación de la Avenida Monterrey,
entre Boulevard Puerto Industrial y Calle Zaragoza, en Zona
Centro Altamira.
Levantamiento Físico.
Elaboración de Presentación.
Propuesta de ante proyecto.
29. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
OCT
2018
Ante Proyecto: Construcción de puente peatonal
adyacente a puente vehicular de Boulevard
Allende, sobre vía ferroviaria Tampico-Monterrey,
en zona Centro, Altamira.
DOCUMENTACIÓN
PROYECTO : A N T E P R O Y E C T O :
C O N S T R U C C I Ó N D E P U E N T E P E A T O N A L
A D Y A C E N T E A P U E N T E V E H I C U L A R D E
B O U L E V A R D A L L E N D E .
3.- Ante Proyecto: Construcción de puente peatonal
adyacente a puente vehicular de Boulevard Allende,
sobre vía ferroviaria Tampico-Monterrey, en zona
Centro, Altamira.
Levantamiento Físico.
Elaboración de Presentación.
Propuesta de Ubicación y solución.
30. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
OCT
2018
PROPUESTA DE PUENTES PEATONALES Y
PARADEROS.
PROYECTO: P R O P U E S TA D E P U E N T E S
P E AT O N A L E S Y PA R A D E R O S .
.
4.- Proyecto: Puentes Peatonales y Paraderos.
Propuesta y Ubicación de Puentes peatonales y
paraderos en zona urbana y rural -
31. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
OCT
2018
DOCUMENTACION PARA COMITÉ Y COMISIÓN
DOCUMENTACIÓN
PROYECTO: D O C U M E N T A C I O N P A R A C O M I T É Y
C O M I S I Ó N P A R A L O S P R O C E D I M I E N T O S D E
C O N C U R S O Y C O N T R A T A C I Ó N D E O P .
1.- Comité y comisión. (Para los Procedimientos de Concurso
y Contratación de Obras Públicas y Servicios Relacionados
con las Mismas de la Dirección de Obras y Públicas del
Municipio de Altamira).
Elaboración de convocatorias para sesiones del comité.
Elaboración de actas las sesiones mensuales del
comité.
Elaboración de las actas de las sesiones extraordinarias
del Comité.
32. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
OCT
2018
PROYECTO DREN EN LA RETAMA, PARTE
DEL COMPLEJO ADMINISTRATIVO
DOCUMENTACIÓN
PROYECTO: P R O Y E C T O D E L D R E N D E L A
R E T A M A D E N T R O D E L C O M P L E J O
A D M I N I S T R A T I V O
3.- Proyecto: Dren Ubicado en “La Retama”, Parte de
Complejo Administrativo.
Levantamiento Físico.
Proyecto Arquitectónico.
Catalogó de Proyecto.
TRAMO EXISTENTE
PROYECTO
Mu
ret
e
Ex
iste
nte
AC
CE
SO
A
CO
MP
LE
JO
AD
MI
NIS
TR
AT
IVO
Mure
te
H=0.60 Mts
Luminaria
Luminaria
2.4
0
1.
60
2.
40
1.
60
Murete H=0.60Mts
Murete H=0.60 Mts
2.40
0
.5
4
8.41
6.56
/
/
/
/
/
/
/
2.15
3.5
0
3.5
0
1.60
/
/ /
33. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
OCT-
NOV
2018
PROPUESTA DE PARQUE-ANDADOR EN
DREN CAVAZOS
IMÁGENES
PROYECTO: P R O Y E C T O P R O P U E S T A D E
P A R Q U E - A N D A D O R E N D R E N C A V A Z O S ,
Z O N A C E N T R O A L T A M I R A .
UBICACIÓN DEL PROYECTO
PARQUE - ANDADOR
34. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
OCT-
NOV
2018
PROPUESTA PARA PROYECTO DE PARQUE-
ANDADOR EN DREN CAVAZOS
IMÁGENES
PROYECTO: P R O Y E C T O P R O P U E S T A D E
P A R Q U E - A N D A D O R E N D R E N C A V A Z O S ,
Z O N A C E N T R O A L T A M I R A .
corte
35. R.AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
OCT-
NOV
2018
PROPUESTA DE PARQUE-ANDADOR EN
DREN CAVAZOS
CORTES
PROYECTO: P R O Y E C T O P R O P U E S T A D E
P A R Q U E - A N D A D O R E N D R E N C A V A Z O S , Z O N A
C E N T R O A L T A M I R A .
2.- Proyecto: Dren Cavazos Lerma.
Apoyo en la Elaboración de Planos Arquitectónico.
36. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
NOV
2018
CUANTIFICACIÓN DE PINTURA PARA EL
EDIFICIO DE SISTEMA DIF. CASA DEL
ADULTO MAYOR.
PROYECTO: C U A N T I F I C A C I Ó N D E P I N T U R A
P A R A E L E D I F I C I O D E S I S T E M A D I F . C A S A
D E L A D U L T O M A Y O R .
4.- Proyecto: Cuantificación de Pintura, para edificio del
Sistema DIF.
3.20
4.76
1.20
2.04
8.00
3.58
4.02
37. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
NOV
2018
PROPUESTA DE COLORES PARA LA
FACHADA DE LA CASA DEL ADULTO MAYOR.
UBICADA EN ZONA CENTRO DE ALTAMIRA.
REPORTE
PROYECTO: P R O P U E S T A D E F A C H A D A
P A R A L A C A S A D E L A D U L T O M A Y O R .
ACTUAL
PROPUESTA
38. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
OCT-
NOV
2018
TERRACERÍAS PARA DREN EL EDÉN EN
ZONA CENTRO DE ALTAMIRA.
PROYECTO: T E R R A C E R Í A S P A R A D R E N
E L E D É N E N Z O N A C E N T R O D E A L T A M I R A .
LOCALIZACIÓN
DREN DREN
ZONA DE TERRACERÍAS
39. R.AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
y
FECHA DESCRIPCION
NOV
2018
DISTRIBUCIÓN VEHICULAR PARA LAS
OFICINAS DE OBRAS PÚBLICAS.
DOCUMENTACIÓN
PROYECTO: D I S T R I B U C I Ó N V E H I C U L A R
P A R A L A S O F I C I N A S D E O B R A S P U B L I C A S .
5.- Proyecto: Distribución Vehicular de las Oficinas de Obras
Públicas, del Municipio de Altamira.
CAJONES TOTALES DE ESTACIONAMIENTO
AREA N° CAJONES DIMENSIONES
1 VISITANTES 26 3.00 X 5.00
2 VISITANTES 18 3.00 X 5.00
3 EMPLEADOS 28 3.00 X 5.00
4 VEHICULOS OFICIALES
Y STAFF DE DIRECCIÓN
26 3.00 X 5.00
5 DIRECCIÓN 2 4.00 X 5.00
6 SERVICIOS PÚBLICOS 9 2.50 X 5.00
7 CONSTRUCCIÓN 2 2.50 X 5.00
TOTAL: 111
1
2
3
4
5
6
7
8
9
10
A B C D
40. INFORME DE ACTIVIDADES
MES DE NOVIEMBRE 2018
R.AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
41. R.AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
•PROYECTOS
INDICE
•
•
•
SUPERVISIÓN DE OBRAS
CONSTRUCCIÓN
MAQUINARIA, EQUIPO Y SUMINISTROS
TOPOGRAFIA
•
NOV I E M BRE 2018
42. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
LEVANTAMIENTO TOPOGRAFICO CALLE ALAMO
O CT U B R E 2 0 1 8
DESCRIPCIÓN
TRAZO Y NIVELES DE LA UNIDAD DEPORTIVA DE ALTAMIRA
TAMAULIPAS CAMPO DE BEISBOL PARA JUEGOS
PANAMERICANOS CATEGORIA 13 -14 AÑOS.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMBRE
2018
TRAZO Y NIVELES NESTOR
PUENTE
CAMPO UNIDAD
DEPORTIVA
43. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
TOPOGRAFIA PARA SUPERVISION DE OBRA
NOV I E M BRE 2018
44. SUPERVISION DE NIVELES Y TRAZO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
N OV I E M B R E 2 0 1 8
DESCRIPCIÓN
SUPERVICION DE OBRA DE LA CALLE TAMPICO PARA
VERIFICAR NIVELES DE BASE Y SUB-BASE.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMBRE
2018
TRAZO Y NIVELES DARIO SUPERVICION DE OBRA
45. SUPERVISION DE NIVELES Y TRAZO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
RE PO RTE FOTOGRÁFICO
NOVIEMBRE 2018
DESCRIPCIÓN
MODIFICACION DE PROYECTO EN LA CALLE LISBOA, EN
EL FRACCIONAMIENTO HACIENDAS.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMBRE
2018
TRAZO Y NIVELES VICENTE SUPERVICION DE OBRA
46. SUPERVISION DE NIVELES Y TRAZO
R.AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
N OV I E M B R E 2 0 1 8
DESCRIPCIÓN
SUPERVICION DE OBRA EN LA VIALIDAD PARA CAMBIO Y
AJUSTE DE PROYECTO.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMB
RE 2018
TRAZO Y NIVELES VICENTE SUPERVICION DE OBRA
47. SUPERVICION DE NIVELES Y TRAZO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
NOV I E M B RE 2 018
DESCRIPCIÓN
TRAZO DE UN AULA EN LA ESCUELA PRIMARIA LAZARO
CARDENAS EN LA COLONIA ROGER GOMEZ.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMB
RE 2018
TRAZO Y NIVELES ISMAEL SUPERVICION DE OBRA
48. SUPERVISION DE NIVELES Y TRAZO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
OCTUBRE 201
8
DESCRIPCIÓN
SUPERVICION DE OBRA PARA NIVELES DE DRENAJE
EN LA CALLE ARMANDO MARTINEZ EN LA COLONIA
JARDIN.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMB
RE 2018
TRAZO Y NIVELES JOSE LUIS
CORONARO
SUPERVICION DE OBRA
49. SUPERVISION DE NIVELES Y TRAZO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
O CT U B R E 2 0 1 8
DESCRIPCIÓN
TRAZO Y NIVELES PARA PROYECTO DE LINEA DE
AGUA EN LA COLONIA PERSEVERANCIA EN EL EJIDO
EL 40
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMB
RE 2018
TRAZO Y NIVELES ENRIQUE
ALEJANDRE
SUPERVICION DE OBRA
50. SUPERVICION DE NIVELES Y TRAZO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
NOVIEMBRE 2018
DESCRIPCIÓN
TRAZO Y NIVELES PARA PROYECTO DE DRENAJE DE LA
CALLE ALLENDE EN VILLA CUAUHTEMOC.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMB
RE 2018
TRAZO Y NIVELES JOSE LUIS
CORONARO
SUPERVICION DE OBRA
51. SUPERVISION DE NIVELES Y TRAZO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
NOVIEMBRE 2018
DESCRIPCIÓN
TRAZO Y NIVELES PARA MODIFICACION Y AJUSTE DE
PROYECTO DE DRENAJE DE LA CALLE TRUJILLO.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMB
RE 2018
TRAZO Y NIVELES JUVENAL
GUILLEN
GOMEZ
SUPERVICION DE OBRA
52. SUPERVISION DE NIVELES Y TRAZO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
NOVIEMBRE 2018
DESCRIPCIÓN
TRAZO Y NIVELES PARA MODIFICACION Y AJUSTE DE
PROYECTO DE CAMINO ACCESO A MARGARITAS, PARA
ENCARPETADO.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMB
RE 2018
TRAZO Y NIVELES JOSE LUIS
CORONARO
SUPERVICION DE OBRA
53. SUPERVISION DE NIVELES Y TRAZO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
NOVIEMBRE 2018
DESCRIPCIÓN
LEVANTAMIENTO TOPOGRAFICO PARA PLANOS ASBUILT EN
LA CALLE JOSE ESCANDON,ANGEL ROSALES Y PEDRO J
MENDEZ.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMBRE
2018
TRAZO Y NIVELES ENRIQUE
ALEJANDRE
SUPERVICION DE OBRA
54. SUPERVISION DE NIVELES Y TRAZO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
NOVIEMBRE 2018
DESCRIPCIÓN
TRAZO Y NIVELES DEL DREN LA RETAMA PARA CALCULO
DE VOLUMETRIAS Y QUE SUPERVICION AJUSTE
PROYECTO Y VER QUE ARBOLES HAY QUE DERRUMBAR.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMB
RE 2018
TRAZO Y NIVELES ENRIQUE
ALEJANDRE
SUPERVICION DE OBRA
55. SUPERVISION DE NIVELES Y TRAZO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
NOVIEMBRE 2018
DESCRIPCIÓN
TRAZO Y NIVELES DE REFERENCIA EN LA OBRA DEL
VELATORIO MUNICIPAL EN ZONA CENTRO.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMBRE
2018
TRAZO Y NIVELES TEC MARTIN SUPERVICION DE OBRA
57. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
TRAZO VIALIDAD Y ESTACIONAMIENTO
NOVIEMBRE 2018
DESCRIPCIÓN
TRAZO Y NIVELES DEL ESTACIONAMIENTO DE OBRAS
PUBLICAS Y ACCESO PRINCIPAL.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMB
RE 2018
TRAZO Y NIVELES DORIAN PEREZ TRAZO
59. LEVANTAMIENTO TOPOGRAFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
NOVIEMBRE 201
8
DESCRIPCIÓN
LEVANTAMIENTO TOPOGRAFICO PLANIMETRICO Y DE LA
CALLE CAPITAN PEREZ PARA REENCARPETADO.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMB
RE 2018
TRAZO Y NIVELES ARQ ZENON
CUEVAS
TRAZO
60. LEVANTAMIENTO TOPOGRAFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
NOVIEMBRE 2018
DESCRIPCIÓN
LEVANTAMIENTO TOPOGRAFICO PLANIMETRICO Y
ALTIMETRICO DE LA CALLE BARRA DE BOCA Y BARRA DE
SANDOVAL PARA REENCARPETADO.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMB
RE 2018
TRAZO Y NIVELES ARQ ZENON
CUEVAS
TRAZO
61. LEVANTAMIENTO TOPOGRAFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
NOVIEMBRE 2018
DESCRIPCIÓN
LEVANTAMIENTO TOPOGRAFICO PLANIMETRICO Y
ALTIMETRICO DE VIALIDAD CONOCIDA COMO DERECHO
DE VIA DE PEMEX, EN LA COLONIA LOS LAURELES PARA
FIN DE PROYECTO DE ENCARPETADO ASFALTICO.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMBRE
2018
TRAZO Y NIVELES ARQ ZENON
CUEVAS
TRAZO
62. LEVANTAMIENTO TOPOGRÁFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
R E PO RTE FOTOGRÁFICO
NOVIEMBRE 2018
DESCRIPCIÓN
LEVANTAMIENTO TOPOGRAFICO PLANIMETRICO Y
ALTIMETRICO DE AREA CERCANA AL DREN CAVAZOS,PARA
PROYECTAR UN PARQUE O AREA VERDE.
FECHA PROYECTO SOLICITADO
POR
DESCRIPCIÓN
NOVIEMB
RE 2018
TRAZO Y NIVELES ARQ ZENON
CUEVAS
TRAZO
63. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
INFORME DE ACTIVIDADES
MES DE NOVIEMBRE 2018
64. INDICE
NOVIEMBRE 2018
• DIRECCIÓN DE OBRAS
PÚBLICAS
• PROYECTOS
• SUPERVISIÓN DE
OBRAS
• CONSTRUCCIÓN
• MAQUINARIA, EQUIPO Y
SUMINISTROS
• TOPOGRAFIA
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
65. RELACIÓN DE OBRA CONTRATADA
CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIER
O
FISIC
O
C-DOP-001/2018
REHABILITACIÓN DE DREN PLUVIAL EN
CALLE CHICHORERA, EN LA COLONIA
LAGUNA FLORIDA, EN ZONA CENTRO,
MAQUINARIA
MUEVE TIERRA,
S.A. DE C.V.
ING. JUVENAL
GUILLEN GOMEZ
131.92% 100%
OBRA TERMINADA
C-DOP-002/2018
CONSTRUCCIÓN DE AULA DIDÁCTICA EN
ESCUELA PRIMARIA "LÁZARO CÁRDENAS",
CALLE PERIMETRAL MADERO, COLONIA
ROGER GÓMEZ,
RINAC, S.A. DE
C.V.
ING. JUVENAL
GUILLEN GOMEZ
117.55% 100% OBRA TERMINADA
C-DOP-003/2018
CONSTRUCCIÓN DE AULA DIDÁCTICA
ADOSADA TIPO 6.00X8.00 M EN
TELESECUNDARIA "LÁZARO CÁRDENAS DEL
RIO", EN CALLE ADOLFO LÓPEZ MATEOS
ESQUINA CON FIDEL VELÁZQUEZ EN EJIDO
ESTACIÓN COLONIAS
IENM
CONSTRUCCIONE
S, S.A. DE C.V.
ING. JOSE LUIS
CORONADO
GUZMAN
95.23% 100%
OBRA TERMINADA
C-DOP-004/2018
CONSTRUCCIÓN DE DESAYUNADOR
4.85X9.00 M INDIVIDUAL EN CENTRO DE
ASISTENCIA INFANTIL COMUNITARIO (JARDÍN
DE NIÑOS) CRI CRI, UBICADO EN CALLE
DUNAS, EN FRACCIONAMIENTO LAS
MARISMAS
JURERI
CONSTRUCCIONE
S DIVERSAS DE
TAMAULIPAS, S.A.
DE C.V.
ARQ. RICARDO
SOSA SERVIN
97.66% 100%
OBRA TERMINADA
C-DOP-005/2018
REHABILITACIÓN DE BIBLIOTECA Y AULAS DE
JARDÍN DE NIÑOS "EVA SAMANO DE LÓPEZ
MATEOS" EN CALLE VICENTE GUERRERO
ENTRE CALLE ITURBIDE Y CALLE ABASOLO,
ZONA CENTRO, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS.
RG MOVILES, S.A.
DE C.V.
ING. JUVENAL
GUILLEN GOMEZ
99.58% 100% OBRA TERMINADA
66. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISICO
C-DOP-006/2018
CONSTRUCCIÓN DE CUBIERTA METÁLICA
DE 13.00 X20.00 MTS, EN ESCUELA
TELESECUNDARIA "CARMEN SERDÁN
ALATRISTE", EN EL EJIDO EL FUERTE,
ZONA RURAL, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS.
SERVICIOS Y
MANTENIMIENTO
JR. DEL ANGEL,
S.A. DE C.V.
ING. ENRIQUE
AEROPAJITO
ALEJANDRE
MARTINEZ
99.79% 100% OBRA TERMINADA
C-DOP-007/2018
REENCARPETADO ASFALTICO EN CALLE
MANANTIAL ENTRE AVENIDA DE LA
INDUSTRIA Y CALLE CEDRO, COLONIA
LOMAS DE MONTE ALTO, ZONA MONTE
ALTO, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
CONSTRUCCIONE
S JEYZA, S.A. DE
C.V.
ING. ORLANDO
CRUZ
RODRIGUEZ
103.89% 100% OBRA TERMINADA
C-DOP-008/2018
REHABILITACIÓN DE MODULO DE BAÑOS,
EN ESCUELA PRIMARIA EMILIANO ZAPATA,
CALLE RAMIRO PEÑA ESQUINA CON CALLE
DOS BOCAS, FRACCIONAMIENTO
ELECTRICISTAS, ZONA CENTRO NORTE,
EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
IENM
CONSTRUCCIONE
S, S.A. DE C.V.
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
112.52% 100%
OBRA TERMINADA
C-DOP-009/2018
CONSTRUCCIÓN DE DREN PLUVIAL “EL
EDÉN” SEGUNDA ETAPA ENTRE VÍA FFCC
MONTERREY Y BOULEVARD ALLENDE, EN
LA ZONA CENTRO, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS.
IENM
CONSTRUCCIONE
S, S.A. DE C.V.
ING. JUVENAL
GUILLEN GOMEZ
118.65% 100% OBRA TERMINADA
C-DOP-010/2018
CONSTRUCCION DE 3 AULAS ADOSADAS
DE 6.0 X 8.00 EN PRIMARIA PRISCILIANO
PERAZA CHAGOYA, EN FRACCIONAMIENTO
LOS MANGOS, ZONA CENTRO NORTE, EN
EL MUNICIPIO DE ALTAMIRA TAMAULIPAS.
INGENIERIA Y
PROYECTOS DE
ALTAMIRA S.A. DE
C.V.
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
100% 100% OBRA TERMINADA
RELACIÓN DE OBRA CONTRATADA
67. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISIC
O
C-DOP-011/2018
CONSTRUCCIÓN DE CUBIERTA
METÁLICA DE 19.00X20.00 MTS, EN
ESCUELA PRIMARIA “NIÑOS HÉROES
DE CHAPULTEPEC”, EJIDO
CERVANTES, ZONA RURAL, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
RINAC, S.A. DE
C.V.
ING. JOSE LUIS
CORONADO
GUZMAN
99.47% 100% OBRA TERMINADA
C-DOP-012/2018
CONSTRUCCION DE 2 AULAS
DIDACTICAS , MODULO DE BAÑOS,Y
FOSA SEPTICA EN
TELEBACHILLERATO COMUNITARIO
NO. 14 EJIDO RICARDO FLORES
MAGON, ZONA RURAL DEL MUNICIPIO
DE ALTAMIRA TAMAULIPAS.
JUAN MIGUEL
VILEGAS
BARBOSA
ING. ENRIQUE
AEROPAJITO
ALEJANDRE
MARTINEZ
120.80% 100%
OBRA TERMINADA
C-DOP-013/2018
REPOSICION DE RED HIDROSANITARIA
EN CALLE JUAN GENARO DE LA
PORTILLA, ENTRE CALLE TAMPICO Y
CALLE GUADALUPE VICTORIA,
COLONIA ALEJANDRO BRIONES, ZONA
CENTR, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS.
CEMPRINSA
CONSTRUCCIONE
S S.A. DE .V.
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
126.71% 100%
OBRA TERMINADA
C-DOP-014/2018
REPOSICION DE RED HIDROSANITARIA
EN CALLE BENITO JUARE ENTRE
CALLE EMILIANO ZAPATA Y F.F.C.C.
VILLS CUAUHTEMOC, ZONA RURAL, EN
EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS
KSA
CONSTRUCTORA
S.A. DE C.V.
ING. ENRIQUE
AEROPAJITO
ALEJANDRE
MARTINEZ
99.20% 100% OBRA TERMINADA
C-DOP-015/2018
BACHEO DE CONCRETO HIDRAULICO
EN LA CALLE REAL ENTRE AVENIDA
MONTERREY Y BOULEVARD ALLENDE,
COLONIA ALTAMIRA SECTOR 3, EN
ZONA CENTRO, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS
KSA
CONSTRUCTORA
S.A. DE C.V.
ING. JUVENAL
GUILLEN GOMEZ
110.96% 100% OBRA TERMINADA
RELACIÓN DE OBRA CONTRATADA
68. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISIC
O
C-DOP-016/2018
CONSTRUCCIÓN DE DREN PLUVIAL
EN CALLE AZUCENA, ENTRE CALLE
LAS FLORES Y CALLE JAZMIN EN LA
COLONIA MONTE ALTO, ZONA
MONTE ALTO, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS. RINAC S.A. DE C.V.
ING. ORLANDO
CRUZ
RODRIGUEZ
86.15% 100% OBRA TERMINADA
C-DOP-017/2018
CONSTRUCCION DE GUARNICIONES
Y BANQUETAS EN CALLE EL
ESFUERZO, ACCESO A ESCUELA
PRIMARIA, COLONIA UNIDOS
AVANZAMOS, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS.
BALDOMERO
VALDEZ PONCE
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
99.98% 100% OBRA TERMINADA
C-DOP-018/2018
CONSTRUCCION DE SUBESTACION
ELECTRICA BIFASICA DE 50 KVA. EN
CENTRO DE ATENCION MULTIPLE
(CAM), UBICADO EN CALLE SAN
JACINTO, ENTRE CALLE SAN
RODRIGO Y SAN AGUSTIN,
FRACCIONAMIENTO SAN JACINTO,
ZONA LAGUNA DE LA PUERTA.
JUAN HERON LARA
MENDIOLA
ING. VICENTE
URIEL BELTRAN
CASTILLO
94.28% 99%
OBRA EN PROCESO
DE EJECUCION
C-DOP-019/2018
CONSTRUCCION DE SUBESTACION
ELECTRICA BIFASICA DE 75 KVA. EN
ESCUELA PRIMARIA PRISCILIANO
PERAZA CHAGOYA, UBICADO EN
CALLE MANZANO, ENTRE CALLE
CHABACANO Y DURAZNO,
FRACCIONAMIENTO LOS MANGOS
JURERI
CONSTRUCCIONES
DIVERSAS DE
TAMAULIPAS, S.A.
DE C.V.
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
54.19% 90%
OBRA EN PROCESO
DE EJECUCION
C-DOP-020/2018
REPOSICION DE RED
HIDROSANITARIA EN CALLE JOSE
QUIROZ SILVA ENTRE CALLE
ROMANA FLORES RIVERA Y CALLE
SABINO SAUCEDO TAVERA ,
COLONIA LOS PRESIDENTES, ZONA
CENTRO NORTE, EN EL MUNICIPIO
DE ALTAMIRA TAMAULIPAS
PROYECTOS
EJECUTIVOS DEL
GOLFO S.A. DE C.V.
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
101.91% 100%
OBRA TERMINADA
RELACIÓN DE OBRA CONTRATADA
69. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISICO
C-DOP-021/2018
REPOSICION DE RED HIDROSANITARIA
EN CALLE GUSTAVO DIAZ ORDAZ
ENTRE AVENIDA CUAUHTEMOC Y
CALLE CONSTITUCION, COLONIA LA
GANADERA, ZONA TAMPICO-ALTAMIRA,
EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
TERRYCOT, S.A. DE
C.V.
P.T.C. JOSE
DARIO SANCHEZ
AGUILAR
124.24% 100%
OBRA TERMINADA
C-DOP-022/2018
REPOSICION DE RED HIDROSANITARIA
EN CALLES ANGEL ROSALES, PEDRO
J. MENDEZ Y JOSE DE ESCANDON
ENTRE AVENIDA CUAUHTEMOC Y
AVENIDA CUAUHTEMOC, ESTACION
CUAUHTEMOC, ZONA RURAL, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
CONSTRUCCIONES
Y SUMINISTROS H,
S.A. DE C.V.
ING. ENRIQUE
AEROPAJITO
ALEJANDRE
MARTINEZ
129.72% 100%
OBRA TERMINADA
C-DOP-023/2018
REPOSICION DE RED HIDROSANITARIA
EN CALLE PUERTO RICO ENTRE CALLE
SEXTA Y CALLE CUARTA, COLONIA
HABITACIONAL, ZONA MIRAMAR, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
JUAN GARCIA
CANSECO
P.T.C. JOSE
DARIO SANCHEZ
AGUILAR
114.16% 100% OBRA TERMINADA
C-DOP-024/2018
REPOSICION DE RED HIDROSANITARIA
EN CALLE IGNACIO ALLENDE Y
MORELOS ENTRE EMILIANO ZAPATA Y
EMILIANO ZAPATA , EN VILLA
CUAUHTEMOC, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS.
ASECMA S. DE R.L.
DE C.V.
ING. JOSE LUIS
CORONADO
GUZMAN
111.71% 100% OBRA TERMINADA
C-DOP-025/2018
REPOSICION DE RED HIDROSANITARIA
EN CALLE PALO DE ROSA ENTRE
CALLE MILTA Y CALLE TEXCOCO,
FRACCIONAMIENTO ALEJANDRO
BRIONES, ZONA MONTE ALTO, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
PROYECTOS Y
MATERIALES DE
CONSTRUCCION EL
CERRO,C S.A. DE
C.V.
ING. ORLANDO
CRUZ
RODRIGUEZ
102.70% 100% OBRA TERMINADA
RELACIÓN DE OBRA CONTRATADA
70. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISICO
C-DOP-026/2018
BACHEO DE CONCRETO ASFALTICO
EN PROLONGACION CARRANZA ENTRE
CALLE FUNDO LEGAL Y ACCESO AL
FRACCIONAMIENTO LAGUNA FLORIDA,
EN EL FRACCIONAMIENTO LAS
MARISMAS
CONSTRUCCIONE
S JEYZA S.A. DE
C.V.
ING. JUVENAL
GUILLEN GOMEZ
117.64% 100% OBRA TERMINADA
C-DOP-027/2018
CONSTRUCCION DE SUBESTACION
ELECTRICA BIFASICA DE 45 KVA. EN
JARDIN DE NIÑOS JUAN GENARO DE
LA PORTILLA, UBICADO EN CALLE
PEDRO J. MENDEZ, ENTRE CALLE
LAGUNA DEL CHAREL Y PEDRO J.
MENDEZ, FRACCIONAMIENTO LAGUNA
DE CHAMPAYAN, ZONA CENTRO.
INGENIERIA
MECANICA Y CIVIL
DE ALTAMIRA S.A.
DE C.V.
ARQ. RICARDO
SOSA SERVIN
72.89% 92%
OBRA EN PROCESO
DE EJECUCION
C-DOP-028/2018
CONSTRUCCION DE SUBESTACION
ELECTRICA BIFASICA DE 75 KVA. EN
JARDIN DE NIÑOS JOSE
VASCONCELOS, UBICADO EN AVENIDA
DEL SOL, ENTRE CALLE VENUS Y
CALLE ESTRELLA, COLONIA UNIDAD
SATELITE, ZONA LAGUNA DE LA
PUERTA
INGENIERIA
MECANICA Y CIVIL
DE ALTAMIRA S.A.
DE C.V.
ING. VICENTE
URIEL BELTRAN
CASTILLO
83.11% 100%
OBRA TERMINADA
C-DOP-029/2018
CONSTRUCCION DE SUBESTACION
ELECTRICA BIFASICA DE 75 KVA. EN
ESCUELA PRIMARIA JAIME TORRES
BODET, UBICADA EN PRIVADA VALLE
DEL PARQUE, ENTRE CALLE C-3 Y
CALLE VALLE ESCONDIDO,
FRACCIONAMIENTO PASEO REAL,
ZONA LAGUNA DE LA PUERTA
PREALALTAMIRA
S.A. DE C.V.
ING. VICENTE
URIEL BELTRAN
CASTILLO
100% 100%
OBRA TERMINADA
C-DOP-030/2018
REPOSICION DE RED HIDROSANITARIA
EN CALLE LAZARO CARDENAS ENTRE
CALLE BENUSTIANO CARRANZXA Y
CALLE SOLIDARIDAD, COLONIA
ADOLFO LOPEZ MATEOS, ZONA
CENTRO NORTE, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS.
GENERAL DE
OBRAS Y
SERVICIOS DE
TAMAULIPAS S.A.
DE C.V.
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
99.98% 100%
OBRA TERMINADA.
RELACIÓN DE OBRA CONTRATADA
71. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIER
O
FISICO
C-DOP-031/2018
CONSTRUCCION DE SUBESTACION
ELECTRICA BIFASICA DE 50 KVA. EN
ESCUELA PRIMARIA ANDRES OSUNA
HINOJOSA, UBICADO EN CALLE RIO
VERDE, ENTRE CALLE BERMUDAS Y
CALLE MEXICO, COLONIA LOMAS DE
ALTAMIRA, ZONA MONTE ALTO, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
SERVICIOS DE
INGENIERIA Y
CONSTRUCCIONE
S SICON, S.A. DE
C.V.
ING. ORLANDO
CRUZ
RODRIGUEZ
58.12% 100%
OBRA TERMINADA
C-DOP-032/2018
CONSTRUCCION DE GUARNICIONES Y
BANQUETAS EN ACCESO A SECATI EN LA
CALLE MATA DEL ABRA ENTRE CALLE
CUAUHTMOC Y CALLE CHAMPAYAN EN
LA COLONIA UNIDOS AVANZAMOS, ZONA
CENTRO, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
SAUL JUAREZ
MURGA
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
100% 100%
OBRA TERMINADA
C-DOP-033/2018
CONSTRUCCION DE GUARNICIONES Y
BANQUETAS EN ACCESO A SECUNDARIA
EN CALLE SANTA PATRICIA ENTRE CALLE
CUAUHTMOC Y CALLE CHAMPAYAN EN
LA COLONIA UNIDOS AVANZAMOS, ONA
CENTRO, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
SAUL JUAREZ
MURGA
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
100% 100%
OBRA TERMINADA
C-DOP-034/2018
REPOSICION DE RED HIDROSANITARIA
EN CALLE PUERTO RICO, ENTRE CALLE
OCTAVA Y CALLE SEXTA, COLONIA
AMPLIACION MIRAMAR, ZONA MIRAMAR,
SECTOR II,, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS.
GRUPO JEI
CONSTRUCCIONE
S S.A. DE C.V.
P.T.C. JOSE
DARIO SANCHEZ
AGUILAR
117.64% 100% OBRA TERMINADA
C-DOP-035/2018
CONSTRUCCIÓN DE DREN PLUVIAL
“PRIMERA ETAPA, EN CALLE FUNDO
LEGAL Y CALLE ABASOLO,
FRACCIONAMIENTO LAGUNA FLORIDA,
EN LA ZONA CENTRO, EN EL MUNICIPIO
DE ALTAMIRA TAMAULIPAS.
JURERI
CONSTRUCCIONE
S DIVERSAS DE
TAMAULIPAS, S.A.
DE C.V.
ING. JUVENAL
GUILLEN GOMEZ
99.99% 100%
OBRA TERMINADA
RELACIÓN DE OBRA CONTRATADA
72. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISICO
C-DOP-036/2018
TERMINACION DE SUBESTACION
ELECTRICA EN JARDIN DE NIÑOS LAZRO
CARDENAS DEL RIO, UBICADO EN CALLE
PERIMETRAL MADERO, COLONIA ROGER
GOMEZ, ZONA CENTRO NORTE, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
AIRE TOTAL
CONTROLADO S.A.
DE C.V.
ING. JUVENAL
GUILLEN GOMEZ
95.48% 100% OBRA TERMINADA
C-DOP-037/2018
CONSTRUCCIÓN DE DREN PLUVIAL EN
CALLE RUTILIO MONTAÑO, ENTRE CALLE
RIO BLANCO Y CALLE LAGUNA DEL
CHAMPAYAN, COLONIA LOMA ALTA, ZONA
MONTE ALTO, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS.
CUAUHTEMOC,
COMERCIO Y
CONSTRUCCION,
S.A. DE C.V.
ING. ORLANDO
CRUZ
RODRIGUEZ
99.99% 100% OBRA TERMINADA
C-DOP-038/2018
PAVIMENTACION DE CONCRETO
HIDRAULICO Y ALUMBRADO PUBLICO EN
CALLE BENITO JUAREZ, ENTRE CALLE
IGNACIO ALLENDE Y F.F.C.C., EN VILLA
CUAUHTEMOC, ZONA RURAL, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
KSA
CONSTRUCTORA
S.A. DE C.V.
ING. ENRIQUE
AEROPAJITO
ALEJANDRE
MARTINEZ
84.78% 100% OBRA TERMINADA
C-DOP-040/2018
PAVIMENTACION DE CONCRETO
HIDRAULICO Y ALUMBRADO PUBLICO EN
CALLE NAYARIT ENTRE CALLE
TAMAULIPAS Y CALLE HEROES DE
NACOZARI, COLONIA LA ESPERANZA,
ZONA RURAL, EN EL MUNICIPIO DE
ALTAMIRA, TAMAULIPAS.
GONZALO RAMOS
RODRIGUEZ
ING. ENRIQUE
AEROPAJITO
ALEJANDRE
MARTINEZ
97.33% 100%
OBRA TERMINADA
C-DOP-041/2018
PAVIMENTACION DE CONCRETO
HIDRAULICO EN CALLE GUSTAVO DIAZ
ORDAZ ENTRE AVENIDA CUAHTEMOC Y
CALLE CONSTITUCION, COLONIA LA
GANADERA, ZONA TAMPICO _ ALTAMIRA,
EN EL MUNICIPIO DE ALTAMIRA,
TAMAULIPAS.
TERRYCOT, S.A.
DE C.V.
P.T.C. JOSE
DARIO SANCHEZ
AGUILAR
98.20% 100%
OBRA TERMINADA
RELACIÓN DE OBRA CONTRATADA
73. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISICO
C-DOP-042/2018
PAVIMENTACION DE CONCRETO
HIDRAULICO DE LA CALLE JUAN GENARO
DE LA PORTILLA, ENTRE CALLE TAMPICO Y
CALLE GUADALUPE VICTORIA, COLONIA
ALEJANDRO BRIONES, ZONA CENTRO, EN
EL MUNICIPIO DE ALTAMIRA TAMAULIPAS.
CEMPRINSA
CONSTRUCCIONE
S, S.A. DE C.V.
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
91.99% 100% OBRA TERMINADA
C-DOP-043/2018
CONSTRUCCION DE PUENTE PEATONAL
DE 25.00 MTS. EN CRUCE DE D.D.V. DE
R.R.C.C., EN BOULEVARD ALLENDE, ZONA
CENTRO, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
RINAC, S.A. DE
C.V.
ING. JUVENAL
GUILLEN GOMEZ
30% 0%
CONTRATO EN
SUSPENSION
TEMPORAL.
C-DOP-044/2018
PAVIMENTACION DE CONCRETO
HIDRAULICO Y ALUMBRADO PUBLICO EN
CALLES ANGEL ROSALES, PEDRO J.
MENDEZ Y JOSE DE ESCANDON ENTRE
AVENIDA CUAUHTEMOC Y AVENIDA
CUAUHTEMOC, ESTACION CUAUHTEMOC,
ZONA RURAL, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS.
CONSTRUCCIONE
S, SERVICIOS Y
SUMINISTROS H,
S.A. DE C.V.
ING. ENRIQUE
AEROPAJITO
ALEJANDRE
MARTINEZ
109.42% 100%
OBRA TERMINADA
C-DOP-045/2018
PAVIMENTACION DE CONCRETO
HIDRAULICO Y ALUMBRADO PUBLICO EN
CALLE IGNACIO ALLENDE Y MORELOS
ENTRE EMILIANO ZAPATA Y EMILIANO
ZAPATA , EN VILLA CUAUHTEMOC, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
PROYECTOS Y
CONSTRUCCIONE
S PROGAR, S.A.
DE C.V.
ING. JOSE LUIS
CORONADO
GUZMAN
82.63% 90%
OBRA EN PROCESO
DE EJECUCION
C-DOP-046/2018
PAVIMENTACION DE CONCRETO
HIDRAULICO Y ALUMBRADO PUBLICO EN
CALLE JOSE QUIROZ SILVA ENTRE CALLE
ROMANA FLORES RIVERA Y CALLE SABINO
SAUCEDO TAVERA, COLONIA LOS
PRESIDENTES, ZONA CENTRO NORTE, EN
EL MUNICIPIO DE ALTAMIRA TAMAULIPAS.
PROYECTOS
EJECUTIVOS DEL
GOLFO, S.A. DE
C.V.
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
94.27% 99%
OBRA EN PROCESO
DE EJECUCION
C-DOP-047/2018
PAVIMENTACION DE CONCRETO
HIDRAULICO Y ALUMBRADO PUBLICO EN
CALLE HEROES DE NACOZARI ENTRE
CALLE ZARAGOZA Y BOULEBARD PUERTO
INDUSTRIAL, ZONA CENTRO, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
CATETE
COMPANY, S.A. DE
C.V.
ARQ. RICARDO
SOSA SERVIN 0% 0%
CONTRATO EN
SUSPENSION
TEMPORAL.
RELACIÓN DE OBRA CONTRATADA
74. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISICO
C-DOP-048/2018
CONSTRUCCION DE DREN PLUVIAL
TRAPEZOIDAL DEL CAD. 0+339 AL CAD.
0+780, FRACCIONAMIENTO HACIENDAS,
ZONA LAGUNA DE LA PUERTA, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
CONSULTORIA EN
OBRA, S.A. DE C.V.
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
94.58% 87%
OBRA EN PROCESO
DE EJECUCION
C-DOP-050/2018
PAVIMENTACION DE CONCRETO
HIDRAULICO Y ALUMBRADO PUBLICO EN
CALLE LAZARO CARDENAS ENTRE CALLE
VENUSTIANO CARRANZA Y CALLE
SOLIDARIDAD, COLONIA LOPEZ MATEOS,
ZONA CENTRO NORTE, EN EL MUNICIPIO
DE ALTAMIRA TAMAULIPAS.
TRES GARCIAS
CONSTRUCCIONE
S, S.A. DE C.V.
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
62.33% 98%
OBRA EN PROCESO
DE EJECUCION
C-DOP-051/2018
PAVIMENTACION DE CONCRETO
HIDRAULICO Y ALUMBRADO PUBLICO EN
CALLE PUERTO RICO, ENTRE CALLE
OCTAVA Y CALLE SEXTA, COLONIA
AMPLIACION MIRAMAR, ZONA MIRAMAR,
SECTOR II, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
TRES GARCIAS
CONSTRUCCIONE
S, S.A. DE C.V.
P.T.C. JOSE
DARIO SANCHEZ
AGUILAR
83.89% 99%
OBRA EN PROCESO
DE EJECUCION
C-DOP-052/2018
CONSTRUCCION DE R.D. EN MEDIA Y BAJA
TENSION, PARA SUMINISTRO DE ENERGIA
ELECTRICA EN LA COLONIA
PERSEVERANCIA, SEGUNDA ETAPA, EN EL
KM. 40, ZONA RURAL, EN EL MUNICIPIO DE
ALTAMIRA, TAMAULIPAS.
JUAN HERON LARA
MENDIOLA
ING. ENRIQUE
AEROPAJITO
ALEJANDRE
MARTINEZ
43.15% 70%
OBRA EN PROCESO
DE EJECUCION
C-DOP-053/2018
TRABAJOS COMPLEMENTARIOS EN RED
DE ALUMBRADO PUBLICO DE 1.5 KM DE
CRIT (TELETON) A DISTRIBUIDOR VIAL
(ACCESO A EL FRACCIONAMIENTO EL
EDEN), EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
JURERI
CONSTRUCCIONE
S DIVERSAS DE
TAMAULIPAS, S.A.
DE C.V.
ING. VICENTE
URIEL BELTRAN
CASTILLO
98.11% 92%
OBRA EN PROCESO
DE EJECUCION
RELACIÓN DE OBRA CONTRATADA
75. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISICO
C-DOP-054/2018
CONSTRUCCION DE SUBESTACION
ELECTRICA TRIFASICA DE 45 KVA. EN
TELEBACHILLERATO No. 14, UBICADO EN
CALLE MELCHOR OCAMPO, ENTRE CALLE
ALDAMA Y MADERO, EJIDO RICARDO
FLORES MAGON, ZONA RURAL, EN EL
MUNICIPIO DE ALTAMIRA, TAMAULIPAS.
JUAN HERON LARA
MENDIOLA
ING. ENRIQUE
AEROPAJITO
ALEJANDRE
MARTINEZ
112.21% 100%
OBRA TERMINADA
C-DOP-055/2018
CONSTRUCCION DE DREN PLUVIAL EN
CALLE ALCATRAZ Y CALLE CEDRO, EN LA
COLONIA LOMAS DE MONTE ALTO, EN
ZONA MONTE ALTO, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS.
OPERADORA
TECNOFERROVIAR
IA DEL PUERTO,
S.A. DE C.V.
ING. ORLANDO
CRUZ
RODRIGUEZ
93.90% 100% OBRA TERMINADA
C-DOP-056/2018
CONSTRUCCION DE CUBIERTA METALICA
DE 8.35X20.00 MTS. EN JARDIN DE NIÑOS
"ESTEFANIA CASTAÑEDA" COLONIA
ADOLFO LOPEZ MATEOS, ZONA CENTRO,
EN EL MUNUCIPIO DE ALTAMIRA
TAMAULIPAS.
JUANA MARIA RUIZ
LEYVA
ING. VICENTE
URIEL BELTRAN
CASTILLO
100% 100% OBRA TERMINADA
C-DOP-057/2018
CONSTRUCCION DE SUBESTACION
ELECTRICA TRIFASICA DE 75 KVA. EN
ESCUELA PRIMARIA JOSE MARIA PINO
SUAREZ, UBICADO EN CALLE RIO PANUCO,
ENTRE CALLE RIO PAPALOAPAN Y RIO
PURON, COLONIA RIO TAMIAHUA, ZONA
RURAL, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
JURERI
CONSTRUCCIONE
S DIVERSAS DE
TAMAULIPAS, S.A.
DE C.V.
ING. JOSE LUIS
CORONADO
GUZMAN
71.86% 76%
OBRA EN PROCESO
DE EJECUCION
C-DOP-058/2018
PAVIMENTACION DE CONCRETO
HIDRAULICO Y ALUMBRADO PUBLICO, EN
CALLE ALEJANDRO PRIETO ENTRE CALLE
SONORA Y CALLE ESTUARDO PORTES Y
CALLE ESTUARDO PORTES ENTRE CALLE
ALEJANDRO PRIETO Y CALLE CANDIDO
SAUCEDO, COLONIA LOS PRESIDENTES,
EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
INTEGRERT, S.A.
DE C.V.
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
106.57% 100%
OBRA TERMINADA
RELACIÓN DE OBRA CONTRATADA
76. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISICO
C-DOP-059/2018
CONSTRUCCION DE SUBESTACION
ELECTRICA TRIFASICA DE 45 KVA. EN
ESCUELA TELESECUNDARIA JESUS
RAMIREZ PALACIOS, EN CALLE FRANCISCO
GUZMAN, ENTRE CALLE GONZALO PEÑA Y
BENITO JUAREZ, EN EL EJIDO FRANCISCO
MEDRANO, ZONA RURAL, EN EL MUNICIPIO
DE ALTAMIRA, TAMAULIPAS.
MMI
MANTENIMIENTO Y
CONSTRUCCIONE
S, S.A. DE C.V.
ING. ENRIQUE
AEROPAJITO
ALEJANDRE
MARTINEZ
78.17% 90%
OBRA EN PROCESO
DE EJECUCION
C-DOP-060/2018
PAVIMENTACION DE CONCRETO
HIDRAULICO Y ALUMBRADO PUBLICO EN
CALLE PUERTO RICO, ENTRE CALLE SEXTA
Y CALLE CUARTA, COLONIA
HABITACIONAL, ZONA MIRAMAR, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
CONSEER, S.A. DE
C.V.
P.T.C. JOSE
DARIO SANCHEZ
AGUILAR
100.91% 100%
OBRA TERMINADA
C-DOP-061/2018
PAVIMENTACION DE CONCRETO
HIDRÁULICO Y ALUMBRADO PÚBLICO EN
LA CALLE GOLFO DE MÉXICO ENTRE
CALLE RIO GRIJALVA Y CALLE RIO
ALVARADO, EN LA COLONIA NUEVO
MADERO, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
CONSULTORIA EN
OBRA, S.A. DE C.V.
P.T.C. JOSE
DARIO SANCHEZ
AGUILAR
80.08% 98%
OBRA EN PROCESO
DE EJECUCION
C-DOP-062/2018
PAVIMENTACION DE CONCRETO
HIDRÁULICO Y ALUMBRADO PÚBLICO EN
CALLE PALO DE ROSA ENTRE CALLE MITLA
Y CALLE TEXCOCO, FRACCIONAMIENTO
ALEJANDRO BRIONES, ZONA MONTE ALTO,
EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
CONSTRUCCIONE
S ARYVE S.A. DE
C.V.
ING. ORLANDO
CRUZ
RODRIGUEZ
30% 88%
OBRA EN PROCESO
DE EJECUCION
C-DOP-063/2018
PAVIMENTACION DE CONCRETO
HIDRÁULICO, REPOSICIÓN DE RED
HIDROSANITARIA Y ALUMBRADO PÚBLICO
EN CALLE MUNICIPIO DE TAMPICO ENTRE
CALLE JAUMAVE Y CALLE REYNOSA,
COLONIA COLINAS DE ALTAMIRA, ZONA
LAGUNA DE LA PUERTA, EN EL MUNICIPIO
DE ALTAMIRA TAMAULIPAS.
OPERADORA
TECNOFERROVIAR
IA DEL PUERTO,
S.A. DE C.V.
P.T.C. JOSE
DARIO SANCHEZ
AGUILAR
53.26% 80%
OBRA EN PROCESO
DE EJECUCION
RELACIÓN DE OBRA CONTRATADA
77. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISICO
C-DOP-064/2018
PAVIMENTACION DE CONCRETO
HIDRÁULICO Y ALUMBRADO PÚBLICO EN
LA CALLE GOLFO DE MÉXICO ENTRE
CALLE RIO ALVARADO Y CALLE RIO YAQUI,
EN LA COLONIA NUEVO MADERO, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
RINAC, S.A. DE
C.V.
P.T.C. JOSE
DARIO SANCHEZ
AGUILAR
78.55% 100% OBRA TERMINADA
C-DOP-065/2018
CONSTRUCCIÓN DE BARDA LATERAL EN
ESCUELA SECUNDARIA TÉCNICA No. 84
"LÁZARO GALLEGOS HERNÁNDEZ", CALLE
LAGUNA DEL CHAIREL, COLONIA JARDINES
DE CHAMPAYAN, ZONA CENTRO, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
MAQUINARIA
MUEVE TIERRA,
S.A. DE C.V.
ARQ. RICARDO
SOSA SERVIN
67.01% 100% OBRA TERMINADA
C-DOP-066/2018
CONSTRUCCIÓN DE AULA DIDÁCTICA EN
ESCUELA PRIMARIA NUEVA CREACIÓN,
COLONIA AMPLIACIÓN LÓPEZ MATEOS,
ZONA CENTRO NORTE, EN EL MUNICIPIO
DE ALTAMIRA TAMAULIPAS.
BRENYA
CONSTRUCCIONE
S, S.A. DE C.V.
ING. YOLANDA
ELIZABET DE LA
TORRE CRUZ
66.89% 85%
OBRA EN PROCESO
DE EJECUCION
C-DOP-067/2018
CONSTRUCCIÓN DE AULA DIDÁCTICA EN
ESCUELA PRIMARIA CELIA RODRIGUEZ
POLANCO, COLONIA MONTE ALTO
SIPOBLADUR, ZONA MONTE ALTO, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
RG MOVILES, S.A.
DE C.V.
ING. ISMAEL
HERNÁNDEZ
MÉNDEZ
69.25% 70%
OBRA EN PROCESO
DE EJECUCION
C-DOP-068/2018
CONSTRUCCIÓN DE AULA DIDÁCTICA EN
ESCUELA TELESECUNDARIA MANUEL
CASTELLANOS LARA, COLONIA NUEVO
MADERO, SECTOR 1, ZONA MIRAMAR, EN
EL MUNICIPIO DE ALTAMIRA TAMAULIPAS.
CORDOVA
CONSTRUCCIONE
S Y
MANTENIMIENTO,
S.A. DE C.V.
P.T.C. JOSE
DARIO SANCHEZ
AGUILAR
30% 65% OBRA EN PROCESO
DE EJECUCION
RELACIÓN DE OBRA CONTRATADA
78. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISICO
C-DOP-074/2018
PAVIMENTACIÓN DE CONCRETO
HIDRÁULICO Y ALUMBRADO PÚBLICO EN
CALLE COR. TRUJILLO ENTRE BOULEVARD
PRIMEX Y CALLE EMILIO MARTINEZ
MANAUTOU, COLONIA FRANCISCO VILLA,
ZONA CENTRO, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS.
TERRYCOT, S.A.
DE C.V.
ING. JUVENAL
GUILLEN GOMEZ
30% 20%
OBRA EN PROCESO
DE EJECUCION
C-DOP-075/2018
PAVIMENTACIÓN DE CONCRETO
HIDRÁULICO Y ALUMBRADO PÚBLICO EN
CALLE PUERTO ALVARADO Y CALLE
PUERTO ESCONDIDO ENTRE CALLE
CATORCE Y CALLE PUERTO VALLARTA,
COLONIA LOS ARADOS, ZONA MONTE
ALTO, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
CONSEER, S.A. DE
C.V.
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
30% 93%
OBRA EN PROCESO
DE EJECUCION
C-DOP-076/2018
PAVIMENTACIÓN DE CONCRETO
HIDRÁULICO, ALUMBRADO PÚBLICO Y
REPOSICIÓN DE RED HIDROSANITARIA EN
CALLE FRANCISCO I. MADERO ENTRE
CALLE LÁZARO CÁRDENAS Y CALLE
BENITO JUÁREZ, COLONIA LOS
PLOMEROS, ZONA MIRAMAR, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
PETRO SERVICIOS
DEL GOLFO, S.A.
DE C.V.
P.T.C. JOSE
DARIO SANCHEZ
AGUILAR
52.04% 55%
OBRA EN PROCESO
DE EJECUCION
C-DOP-077/2018
REHABILITACIÓN DE EDIFICIO PÚBLICO
DEL SISTEMA DIF (CECUDI), EN CALLE
EMILIANO ZAPATA ENTRE CALLE
MOCTEZUMA Y CALLE 16 DE SEPTIEMBRE,
COLONIA LOMAS DE REAL, ZONA MONTE
ALTO, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
SEALS AND
MANUFACTURED
TECHNOLOGY,
S.A. DE C.V.
ING. VICENTE
URIEL BELTRAN
CASTILLO
30% 82%
OBRA EN PROCESO
DE EJECUCION
C-DOP-078/2018
REHABILITACIÓN DE MODULO DE BAÑOS
EN ESCUELA PRIMARIA MARTIRES DE LA
REVOLUCIÓN, EN ZONA CENTRO, EN EL
MUNCIPIO DE ALTAMIRA TAMAULIPAS.
INGENIERIA
MECANICA Y CIVIL
DE ALTAMIRA, S.A.
DE C.V.
ARQ. RICARDO
SOSA SERVIN
88.05% 100% OBRA TERMINADA
RELACIÓN DE OBRA CONTRATADA
79. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISICO
C-DOP-079/2018
REHABILITACIÓN DE AULA DIDÁCTICA Y
ANDADORES EN JARDÍN DE NIÑOS
ESTEFANÍA CASTAÑEDA, EN LA COLONIA
ADOLFO LÓPEZ MATEOS, EN ZONA
CENTRO NORTE, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS.
INGENIERIA
MECANICA Y CIVIL
DE ALTAMIRA, S.A.
DE C.V.
ING. VICENTE
URIEL BELTRAN
CASTILLO
30% 95%
OBRA EN PROCESO
DE EJECUCION
C-DOP-080/2018
CONSTRUCCIÓN DE 5 RECAMARAS CON
BAÑO DE 5.00X4.00 M, EN LAS COLONIAS
AMPLIACIÓN ADOLFO LÓPEZ MATEOS
LÁZARO CÁRDENAS, ZONA CENTRO
NORTE, EN EL MUNICIPO DE ALTAMIRA
TAMAULIPAS.
CONSTRUCTORA
JESAS, S.A. DE
C.V.
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
30% 50%
OBRA EN PROCESO
DE EJECUCION
C-DOP-081/2018
CONSTRUCCIÓN DE 5 RECAMARAS CON
BAÑO DE 5.00X4.00 M, EN LOS SECTORES
AMPLIACIÓN PRESIDENTES, LOS
PRESIDENTES SEC. 2, SEC.3, SEC.4, SEC.5,
ZONA CENTRO NORTE, EN EL MUNICIPO
DE ALTAMIRA TAMAULIPAS.
BRENYA
CONSTRUCCIONE
S, S.A. DE C.V.
ING. VICENTE
URIEL BELTRAN
CASTILLO
30% 68%
OBRA EN PROCESO
DE EJECUCION
C-DOP-082/2018
CONSTRUCCIÓN DE 5 RECAMARAS CON
BAÑO DE 5.00X4.00 M, EN LAS COLONIAS
NUEVO MADERO Y LAS ADELITAS, ZONA
LAGUNA DE LA PUERTA Y ZONA MIRAMAR,
EN EL MUNICIPO DE ALTAMIRA
TAMAULIPAS.
JUAN MIGUEL
VILEGAS BARBOSA
P.T.C. JOSE
DARIO SANCHEZ
AGUILAR
30% 45%
OBRA EN PROCESO
DE EJECUCION
C-DOP-083/2018
CONSTRUCCIÓN DE 5 RECAMARAS CON
BAÑO DE 5.00X4.00 M, EN LAS COLONIAS
AMPLIACIÓN PORTES GIL, EMILIO PORTES
GIL Y AMPLIACIÓN ADOLFO LÓPEZ
MATEOS, ZONA CENTRO NORTE, EN EL
MUNICIPO DE ALTAMIRA TAMAULIPAS.
BALDOMERO
VALDEZ PONCE
ING. JUVENAL
GUILLEN GOMEZ
30% 30%
OBRA EN PROCESO
DE EJECUCION
RELACIÓN DE OBRA CONTRATADA
80. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISICO
C-DOP-084/2018
CONSTRUCCIÓN DE 5 RECAMARAS CON
BAÑO DE 5.00X4.00 M, EN VILLA
CUAUHTÉMOC Y MARTIN A. MARTÍNEZ,
ZONA CUAUHTÉMOC Y ZONA CENTRO
NORTE, EN EL MUNICIPO DE ALTAMIRA
TAMAULIPAS.
CONSTRUCCIONE
S, SERVICIOS Y
SUMINISTROS H,
S.A. DE C.V.
ING. ENRIQUE
AEROPAJITO
ALEJANDRE
MARTINEZ
30% 55%
OBRA EN PROCESO
DE EJECUCION
C-DOP-085/2018
CONSTRUCCIÓN DE 5 RECAMARAS CON
BAÑO DE 5.00X4.00 M, EN
PERSEVERANCIA, RIO TAMIAHUA, COLONIA
JARDÍN, EMILIO PORTES GIL Y PRIMAVERA
NORTE, EN ZONA RURAL Y ZONA CENTRO
NORTE, EN EL MUNICIPO DE ALTAMIRA
TAMAULIPAS.
KSA
CONSTRUCTORA
S.A. DE C.V.
ING. JOSE LUIS
CORONADO
GUZMAN
30% 18%
OBRA EN PROCESO
DE EJECUCION
C-DOP-086/2018
CONSTRUCCIÓN DE RED DE AGUA
POTABLE EN LA COLONIA
PERSEVERANCIA, ZONA RURAL, EN EL
MUNICIPO DE ALTAMIRA TAMAULIPAS.
CEMPRINSA
CONSTRUCCIONE
S S.A. DE C.V.
ING. ENRIQUE
AEROPAJITO
ALEJANDRE
MARTINEZ
30% 90%
OBRA EN PROCESO
DE EJECUCION
C-DOP-087/2018
REPOSICIÓN DE RED HIDROSANITARIA EN
CALLE ARMANDO MARTÍNEZ, ENTRE CALLE
AURELIA FAJARDO Y CALLE CLAVEL,
COLONIA JARDÍN, VILLA CUAUHTÉMOC, EN
EL MUNICIPO DE ALTAMIRA TAMAULIPAS.
GENERAL DE
OBRAS Y
SERVICIOS DE
TAMAULIPAS, S.A.
DE C.V.
ING. JOSE LUIS
CORONADO
GUZMAN
30% 35%
OBRA EN PROCESO
DE EJECUCION
C-DOP-088/2018
REPOSICIÓN DE RED HIDROSANITARIA EN
CALLE IGNACIO ALLENDE, ENTRE CALLE
MORELOS E HIDALGO, Y CALLE HIDALGO
ENTRE CALLE IGNACIO ALLENDE Y CALLE
ZAPATA, VILLA CUAUHTÉMOC, EN EL
MUNICIPO DE ALTAMIRA TAMAULIPAS.
CORDOVA
CONSTRUCCIONE
S Y
MANTENIMIENTO,
S.A. DE C.V.
ING. JOSE LUIS
CORONADO
GUZMAN
30% 30%
OBRA EN PROCESO
DE EJECUCION
RELACIÓN DE OBRA CONTRATADA
81. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISICO
C-DOP-089/2018
REPOSICIÓN DE RED HIDROSANITARIA EN
CALLE SAN LUIS, ENTRE CALLE DURANGO
Y CALLE MORELOS, EN LA COLONIA
NUEVO MÉXICO, EN EL MUNICIPO DE
ALTAMIRA TAMAULIPAS.
MMI
MANTENIMIENTO Y
CONSTRUCCIONE
S, S.A. DE C.V.
ING. ORLANDO
CRUZ
RODRIGUEZ
30% 40%
OBRA EN PROCESO
DE EJECUCION
C-DOP-090/2018
REENCARPETADO ASFÁLTICO EN CALLE
BARRA DE SAN ANTONIO, ENTRE
BOULEVARD BENITO JUÁREZ Y CALLE
FUNDO LEGAL, COLONIA REVOLUCIÓN
VERDE, ZONA CENTRO, EN EL MUNICIPO
DE ALTAMIRA TAMAULIPAS.
TERRYCOT, S.A.
DE C.V.
ING. JUVENAL
GUILLEN GOMEZ
30% 20%
OBRA EN PROCESO
DE EJECUCION
C-DOP-091/2018
CONSTRUCCIÓN DE DESAYUNADOR EN
ESCUELA PRIMARIA "LÁZARO CÁRDENAS
DEL RIO", COLONIA ROGER GÓMEZ, ZONA
CENTRO, EN EL MUNICIPO DE ALTAMIRA
TAMAULIPAS.
IENM
CONSTRUCCIONE
S, S.A. DE C.V.
ING. ISMAEL
HERNÁNDEZ
MÉNDEZ
30% 40%
OBRA EN PROCESO
DE EJECUCION
C-DOP-092/2018
CONSTRUCCIÓN DE RED ELÉCTRICA
(PRIMERA ETAPA), COLONIA EL PEDREGAL,
ZONA CENTRO NORTE, EN EL MUNICIPO
DE ALTAMIRA TAMAULIPAS.
JUAN HERON LARA
MENDIOLA
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
30% 38%
OBRA EN PROCESO
DE EJECUCION
C-DOP-093/2018
REENCARPETADO ASFÁLTICO DE 5 CM EN
CALLE FUNDO LEGAL ENTRE CALLE
LAGUNA DE CHAMPAYAN Y CALLE PEDRO
J. MÉNDEZ, COLONIA REVOLUCIÓN VERDE,
ZONA CENTRO, EN EL MUNICIPO DE
ALTAMIRA TAMAULIPAS.
TERRYCOT, S.A.
DE C.V.
ING. JUVENAL
GUILLEN GOMEZ
30% 25%
OBRA EN PROCESO
DE EJECUCION
C-DOP-094/2018
PAVIMENTACIÓN DE CONCRETO
ASFÁLTICO EN CALLE RIO PANUCO, ENTRE
CALLE 2 Y RIO PAPALOAPAN, CALLE RIO
PANUCO, ENTRE CALLE 4 Y CALLE 2, EN LA
COLONIA RIO TAMIAHUA, EN EL MUNICIPIO
DE ALTAMIRA TAMAULIPAS.
CONSTRUCCIONE
S JEYZA, S.A. DE
C.V.
ING. ENRIQUE
AEROPAJITO
ALEJANDRE
MARTINEZ
30% 30%
OBRA EN PROCESO
DE EJECUCION
RELACIÓN DE OBRA CONTRATADA
82. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISICO
C-DOP-095/2018
REENCARPETADO ASFÁLTICO DE 5 CM DE
ESPESOR EN CALLE BENITO JUÁREZ
ENTRE CARRETERA TAMPICO-MANTE Y
CALLE FUNDADORES, ZONA RURAL, EN EL
MUNICIPO DE ALTAMIRA TAMAULIPAS.
TERRYCOT, S.A.
DE C.V.
ING. ENRIQUE
AEROPAJITO
ALEJANDRE
MARTINEZ
30% 30%
OBRA EN PROCESO
DE EJECUCION
C-DOP-096/2018
PAVIMENTACIÓN DE CONCRETO
ASFÁLTICO EN CAMINO A EJIDO JOSÉ
MARÍA LUIS MORA, ZONA RURAL, EN EL
MUNICIPIO DE ALTAMIRA TAMAULIPAS.
CATETE
COMPANY, S.A. DE
C.V.
ING. JOSE LUIS
CORONADO
GUZMAN
30% 8%
OBRA EN PROCESO
DE EJECUCION
C-DOP-097/2018
PAVIMENTACIÓN DE CONCRETO
HIDRÁULICO Y ALUMBRADO PÚBLICO EN
VIALIDAD PD. ENTRE CALLE REAL DEL
PRADO ORIENTE Y LISBOA Y CALLE LISBOA
ENTRE VIALIDAD PD. Y NAVARRA,
FRACCIONAMIENTO LAS HACIENDAS, ZONA
LAGUNA DE LA PUERTA, EN EL MUNICIPIO
DE ALTAMIRA TAMAULIPAS.
PROYECTOS Y
MATERIALES DE
CONSTRUCCION
EL CERRO, S.A. DE
C.V.
ING. VICENTE
URIEL BELTRAN
CASTILLO
30% 5%
OBRA EN PROCESO
DE EJECUCION
C-DOP-098/2018
CONSTRUCCIÓN DE 5 RECAMARAS CON
BAÑO DE 5.00X4.00 M, EN LAS COLONIAS
NUEVO MADERO Y NUEVO MADERO SEC-2,
ZONA MIRAMAR, EN EL MUNICIPO DE
ALTAMIRA TAMAULIPAS.
JURERI
CONSTRUCCIONE
S DIVERSAS DE
TAMAULIPAS, S.A.
DE C.V.
ARQ. RICARDO
SOSA SERVIN
30% 20%
OBRA EN PROCESO
DE EJECUCION
C-DOP-099/2018
CONSTRUCCIÓN DE 5 RECAMARAS CON
BAÑO DE 5.00X4.00 M, EN LAS COLONIAS
BRISAS, LOMAS DE ALTAMIRA Y LOMA
ALTA, ZONA MONTE ALTO, EN EL MUNICIPO
DE ALTAMIRA TAMAULIPAS.
CUAUHTEMOC,
COMERCIO Y
CONSTRUCCION,
S.A. DE C.V.
ING. ORLANDO
CRUZ
RODRIGUEZ
30% 50%
OBRA EN PROCESO
DE EJECUCION
C-DOP-100/2018
CONSTRUCCIÓN DE 4 RECAMARAS CON
BAÑO DE 5.00X4.00 M, EN LAS COLONIAS
LAS ADELITAS Y MUNICIPIOS LIBRES, ZONA
LAGUNA DE LA PUERTA, EN EL MUNICIPO
DE ALTAMIRA TAMAULIPAS.
IENM
CONSTRUCCIONE
S, S.A. DE C.V.
ARQ. RICARDO
SOSA SERVIN
30% 20%
OBRA EN PROCESO
DE EJECUCION
RELACIÓN DE OBRA CONTRATADA
83. CONTRATO OBRA CONTRATISTA SUPERVISOR AVANCE OBSERVACIONES
FINANCIERO FISICO
C-DOP-101/2018
CONSTRUCCIÓN DE DREN PLUVIAL
RECTANGULAR DEL CAD. 0+000.00 AL CAD.
0+090.00 EN CALLE MIGUEL HIDALGO, EN
EL EJIDO RICARDO FLORES MAGÓN, EN EL
MUNICIPO DE ALTAMIRA TAMAULIPAS.
CATETE
COMPANY, S.A. DE
C.V.
ING. ENRIQUE
AEROPAJITO
ALEJANDRE
MARTINEZ
30% 0%
OBRA EN PROCESO
DE EJECUCION
C-DOP-102/2018
CONSTRUCCIÓN DE DREN PLUVIAL EN
CALLE C-7 SUR, ENTRE CALLE C-7
PONIENTE Y ÁREA VERDE,
FRACCIONAMIENTO CORREDOR
INDUSTRIAL, ZONA LAGUNA DE LA
PUERTA, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
CONSTRUCCIONE
S, SERVICIOS Y
SUMINISTROS H,
S.A. DE C.V.
P.T.C. JOSE
DARIO SANCHEZ
AGUILAR
30% 5%
OBRA EN PROCESO
DE EJECUCION
C-DOP-103/2018
CONSTRUCCIÓN DE TERRACERIAS PARA
ESTRUCTURA DE VELATORIO Y
ESTACIONAMIENTO EN CALLE AGUSTIN DE
ITURBIDE ENTRE DIAGONAL CAVAZOS
LERMA Y BOULEVARD IGNACIO ALLENDE,
EN ZONA CENTRO, EN EL MUNICIPIO DE
ALTAMIRA TAMAULIPAS.
CONSTRUCCIONE
S ARYVE, S.A. DE
C.V.
TEC.C. JUAN
MARTIN
HERNANDEZ
RUBIO
30% 0%
OBRA EN PROCESO
DE EJECUCION
C-DOP-104/2018
CONSTRUCCIÓN DE NUEVO TRAMO DE
LÍNEA DE MEDIA TENSIÓN AÉREA 3 FASES,
4 HILOS EN EL CIRCUITO MTY-5170,
UBICADO EN EJIDO ESTEROS, EN ZONA
RURAL, EN EL MUNICIPIO DE ALTAMIRA
TAMAULIPAS.
JUAN HERON LARA
MENDIOLA
ING. JOSE LUIS
CORONADO
GUZMAN
30% 20%
OBRA EN PROCESO
DE EJECUCION
RELACIÓN DE OBRA CONTRATADA
84. APOYO TÉCNICO COMPLEMENTO
DE PROYECTOS
2018
T I T U L O . - ( C O N S T R U C C I Ó N D E D R E N
P L U V I A L “ P R I M E R A E T A P A , E N C A L L E
F U N D O L E G A L Y C A L L E A B A S O L O ,
F R A C C I O N A M I E N T O L A G U N A F L O R I D A , E N
L A Z O N A C E N T R O , E N E L M U N I C I P I O D E
A L T A M I R A T A M A U L I P A S . ) ( C - D O P - 0 3 5 / 2 0 1 8 )
FECHA INICIO
02 Junio 18
OBSERVACIONES:
Apoyo en levantamiento físico.
y/o
Verificación del Alcance.
FECHA TERMINACION
16 Julio 18
REPORTE FOTOGRÁFICO
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
85. 2018
T I T U L O . - ( P A V I M E N T A C I Ó N D E C O N C R E T O
H I D R Á U L I C O Y A L U M B R A D O P Ú B L I C O E N
C A L L E B E N I T O J U A R E Z , E N T R E C A L L E
I G N A C I O A L L E N D E Y F . F . C . C . , E N V I L L A
C U A U H T É M O C , Z O N A R U R A L , E N E L
M U N I C I P I O D E A L T A M I R A T A M A U L I P A S .
( C - D O P - 0 3 8 / 2 0 1 8 )
FECHA INICIO
07 Junio 18
OBSERVACIONES:
Apoyo en levantamiento físico.
y/o
Verificación del Alcance.
FECHA TERMINACION
21 Julio 18
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
APOYO TÉCNICO COMPLEMENTO
DE PROYECTOS
REPORTE FOTOGRÁFICO
86. 2018
T I T U L O . - ( P A V I M E N T A C I Ó N D E C O N C R E T O
H I D R Á U L I C O Y A L U M B R A D O P Ú B L I C O E N
C A L L E L A Z A R O C Á R D E N A S E N T R E C A L L E
V E N U S T I A N O C A R R A N Z A Y C A L L E
S O L I D A R I D A D , C O L O N I A L O P E Z M A T E O S ,
Z O N A C E N T R O N O R T E , E N E L M U N I C I P I O D E
A L T A M I R A T A M A U L I P A S . ) ( C - D O P - 0 5 0 / 2 0 1 8 )
FECHA INICIO
12 Julio 18
OBSERVACIONES:
Apoyo en levantamiento físico.
y/o
Verificación del Alcance.
FECHA TERMINACION
09 Septiembre 18
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
APOYO TÉCNICO COMPLEMENTO
DE PROYECTOS
REPORTE FOTOGRÁFICO
87. 2018
T I T U L O . - ( P A V I M E N T A C I O N D E C O N C R E T O
H I D R A U L I C O Y A L U M B R A D O P U B L I C O E N
C A L L E P U E R T O R I C O , E N T R E C A L L E
O C T A V A Y C A L L E S E X T A , C O L O N I A
A M P L I A C I O N M I R A M A R , Z O N A M I R A M A R ,
S E C T O R I I , E N E L M U N I C I P I O D E A L T A M I R A
T A M A U L I P A S . ) ( C - D O P - 0 5 1 / 2 0 1 8 )
FECHA INICIO
12 Julio 18
OBSERVACIONES:
Apoyo en levantamiento físico.
y/o
Verificación del Alcance.
FECHA TERMINACION
09 Septiembre 18
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
APOYO TÉCNICO COMPLEMENTO
DE PROYECTOS
REPORTE FOTOGRÁFICO
88. 2018
T I T U L O . - ( C O N S T R U C C I Ó N D E
S U B E S T A C I Ó N E L É C T R I C A T R I F A S I C A D E 7 5
K V A . E N E S C U E L A P R I M A R I A J O S E M A R I A
P I N O S U A R E Z , U B I C A D O E N C A L L E R I O
P A N U C O , E N T R E C A L L E R I O P A P A L O A P A N Y
R I O P U R O N , C O L O N I A R I O T A M I A H U A , Z O N A
R U R A L , E N E L M U N I C I P I O D E A L T A M I R A
T A M A U L I P A S . ) ( C - D O P - 0 5 7 / 2 0 1 8 )
FECHA INICIO
24 Julio 18
OBSERVACIONES:
Apoyo en levantamiento físico.
y/o
Verificación del Alcance.
FECHA TERMINACION
21 Septiembre 18
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
APOYO TÉCNICO COMPLEMENTO
DE PROYECTOS
REPORTE FOTOGRÁFICO
89. 2018
T I T U L O . - ( P A V I M E N T A C I Ó N D E C O N C R E T O
H I D R Á U L I C O Y A L U M B R A D O P Ú B L I C O , E N
C A L L E A L E J A N D R O P R I E T O E N T R E C A L L E
S O N O R A Y C A L L E E S T U A R D O P O R T E S Y
C A L L E E S T U A R D O P O R T E S E N T R E C A L L E
A L E J A N D R O P R I E T O Y C A L L E C A N D I D O
S A U C E D O , C O L O N I A L O S P R E S I D E N T E S , E N
E L M U N I C I P I O D E A L T A M I R A
T A M A U L I P A S . ) ( C - D O P - 0 5 8 / 2 0 1 8 )
FECHA INICIO
25 Julio 18
OBSERVACIONES:
Apoyo en levantamiento físico.
y/o
Verificación del Alcance.
FECHA TERMINACION
22 Septiembre 18
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
APOYO TÉCNICO COMPLEMENTO
DE PROYECTOS
REPORTE FOTOGRÁFICO
90. 2018
T I T U L O . - ( P A V I M E N T A C I O N D E C O N C R E T O
H I D R Á U L I C O Y A L U M B R A D O P Ú B L I C O E N L A
C A L L E G O L F O D E M É X I C O E N T R E C A L L E R I O
A L V A R A D O Y C A L L E R I O Y A Q U I , E N L A
C O L O N I A N U E V O M A D E R O , E N E L M U N I C I P I O
D E A L T A M I R A T A M A U L I P A S . )
( C - D O P - 0 6 4 / 2 0 1 8 )
FECHA INICIO
15 Septiembre 18
OBSERVACIONES:
Apoyo en levantamiento físico.
y/o
Verificación del Alcance.
FECHA TERMINACION
13 Noviembre 18
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
APOYO TÉCNICO COMPLEMENTO
DE PROYECTOS
REPORTE FOTOGRÁFICO
91. 2018
TITULO.- C O N S T R U C C I Ó N D E B A R D A
L A T E R A L E N E S C U E L A S E C U N D A R I A
T É C N I C A N O . 8 4 " L Á Z A R O G A L L E G O S
H E R N Á N D E Z " , C A L L E L A G U N A D E L C H A I R E L ,
C O L O N I A J A R D I N E S D E C H A M P A Y A N , Z O N A
C E N T R O , E N E L M U N I C I P I O D E A L T A M I R A
T A M A U L I P A S . C - D O P - 0 6 5 / 2 0 1 8
FECHA INICIO
23 Octubre 18
OBSERVACIONES:
Apoyo en levantamiento físico.
y/o
Verificación del Alcance.
FECHA TERMINACION
11 Diciembre 18
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
APOYO TÉCNICO COMPLEMENTO
DE PROYECTOS
REPORTE FOTOGRÁFICO
92. 2018
T I T U L O . - ( C O N S T R U C C I Ó N D E A U L A
D I D Á C T I C A E N E S C U E L A P R I M A R I A N U E V A
C R E A C I Ó N , C O L O N I A A M P L I A C I Ó N L Ó P E Z
M A T E O S , Z O N A C E N T R O N O R T E , E N E L
M U N I C I P I O D E A L T A M I R A T A M A U L I P A S . )
( C - D O P - 0 6 6 / 2 0 1 8 )
FECHA INICIO
26 Septiembre 18
OBSERVACIONES:
Apoyo en levantamiento físico.
y/o
Verificación del Alcance.
FECHA TERMINACION
14 Noviembre 18
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
APOYO TÉCNICO COMPLEMENTO
DE PROYECTOS
REPORTE FOTOGRÁFICO
93. ATENCIÓN GENERAL
NUMERO
CONTRATO OBRA CANTIDAD
SUPERVISOR
OBSERVACIO
NES
1 Evaluación
accidente vial
6 varios Ninguna
2 Peticiones
generales
1 varios Ninguna
94. R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACION 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
INFORME DE ACTIVIDADES
MES DE NOVIEMBRE
2018
95. INDICE
NOVIEMBRE
2018
• PROYECTOS
• SUPERVISIÓN DE OBRAS
• CONSTRUCCIÓN
• MAQUINARIA, EQUIPO Y
SUMINISTROS
• TOPOGRAFIA
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
96. NOVIEMBRE 2018
TITULO.- L I M P I E Z A Y D E S A Z O L V E M AN U A L
D E D R E N P L U V I A L D E C O L . L O M A S D E M O N T E
AL T O .
FECHA
INICIO
FECHA
TERMINACIÓN
MANO DE OBRA:
2 MAESTRO DE OBRA
16 AYUDANTES
1 RETRO
2 CAMIONES DE
VOLTEO
COSTO:
$ 19,5111.94
F E C H A
1 3 / 1 1 / 2 0 1 8
F E C H A
1 3 / 1 1 / 2 0 1 8
REPORTE FOTOGRÁFICO
DESCRIPCIÓN.- L I M P I E Z A Y D E S A Z O LV E
C O N H E R R A M I E N TA M A N U A L D E D R E N
P L U V I A L D E L A C O L . L O M A S D E M O N T E
A LT O E N T R E C A L L E S L I M O N Y P I Ñ A .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
97. NOVIEMBRE 2018
TITULO.- L I M P I E Z A Y D E S AZ O LV E D E
D R E N P L U V I AL D E L A P E P S I .
FECHA INICIO FECHA
TERMINACIÓN
MANO DE OBRA:
2 MAESTRO DE
OBRA
16 AYUDANTES
COSTO:
$ 24,912.00
F E C H A
0 8 / 1 1 / 2 0 1 8
F E E C H A
2 7 / 1 1 / 2 0 1 8
DESCRIPCIÓN.- L I M P I E Z A Y D E S A Z O LV E
D E D R E N P L U V I A L D E L A P E P S I C O N
H E R R A M I E N TA M A N U A L .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
REPORTE FOTOGRÁFICO
98. NOVIEMBRE 2018
TITULO.- R E P A R A C I Ó N D E B A R D A D A Ñ A D A
E N F R AC C I O N AM I E N T O L AG U N A F L O R I D A .
FECHA INICIO FECHA
TERMINACIÓN
MANO DE OBRA:
1 MAESTRO DE OBRA
6 AYUDANTES
COSTO:
$ 4,152.00
F E C H A
2 8 / 1 1 / 2 0 1 8
F E C H A
2 9 / 1 1 / 2 0 1 8
DESCRIPCIÓN.- R E PA R A C I Ó N D E B A R D A
D E C O L I N D A N C I A D A Ñ A D A E N
F R A C C I O N A M I E N T O L A G U N A F L O R I D A .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
REPORTE FOTOGRÁFICO
99. NOVIEMBRE 2018
TITULO.- C O N S T R U C C I Ó N D E TO P E S E N
E L L I B R AM I E N TO ALTAM I R A.
FECHA INICIO FECHA
TERMINACIÓN
MANO DE OBRA:
1 MAESTRO DE OBRA
5 AYUDANTES
1 CAMION VOLTEO
COSTO:
$ 39,243.90
F E C H A
0 1 / 1 1 / 2 0 1 8
F E C H A
0 1 / 1 1 / 2 0 1 8
DESCRIPCIÓN.- C O N S T R U C C I Ó N D E T O P E S
A B A S E D E C A R P E T A A S F A L T I C A C A L I E N T E E N
E L L I B R A M I E N T O A L T A M I R A ( C A R R E T E R A
T A M P I C O – M A N T E ) .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
REPORTE FOTOGRÁFICO
100. NOVIEMBRE 2018
TITULO.- R E H U B I C A C I Ó N D E C O N T E N E D O R
D E C AL D E O B R AS P Ú B L I C AS .
FECHA INICIO FECHA
TERMINACIÓN
MANO DE OBRA:
1 MAESTRO DE OBRA
6 AYUDANTES
1
RETROEXCAVADORA
COSTO:
$ 4,794.67
F E C H A
1 4 / 1 1 / 2 0 1 8
F E C H A
1 4 / 1 1 / 2 0 1 8
DESCRIPCIÓN.- R E H U B I C A C I Ó N D E
C O N T E N E D O R Y T R A S L A D O D E S A C O S D E
C A L D E B O D E G A D E S E RV I C I O S P Ú B L I C O S
A C O N T E N E D O R D E O B R A S P Ú B L I C A S .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
REPORTE FOTOGRÁFICO
101. NOVIEMBRE 2018
TITULO.- T R AS L AD O D E M AD E R A PAR A
P I S TA D E H I E L O A P L AZ A C E N T R AL D E
ALTAM I R A.
FECHA INICIO FECHA
TERMINACIÓN
MANO DE OBRA:
1 MAESTRO DE
OBRA
6 AYUDANTES
COSTO:
$ 1,131.00
F E C H A
1 4 / 1 1 / 2 0 1 8
F E C H A
1 4 / 1 1 / 2 0 1 8
DESCRIPCIÓN.- T R A S L A D O D E M A D E R A
PA R A P I S TA D E H I E L O A P L A Z A C E N T R A L
D E A LTA M I R A .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
REPORTE FOTOGRÁFICO
102. NOVIEMBRE 2018
TITULO.- L I M P I E Z A M AN U AL D E
E S TAC I O N AM I E N TO D E O B R AS P Ú B L I C AS .
FECHA INICIO FECHA
TERMINACIÓN
MANO DE OBRA:
1 MAESTRO DE OBRA
6 AYUDANTES
COSTO:
$ 2,768.00
F E C H A
1 5 / 1 1 / 2 0 1 8
F E C H A
1 6 / 1 1 / 2 0 1 8
DESCRIPCIÓN.- L I M P I E Z A M A N U A L D E
E S TA C I O N A M I E N T O D E O B R A S P Ú B L I C A S .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
REPORTE FOTOGRÁFICO
103. NOVIEMBRE 2018
TITULO.- P R E PAR AC I Ó N PAR A L A P I S TA
D E H I E L O E N L A P L AZ A C E N T R AL Z O N A
C E N T R O .
FECHA INICIO FECHA
TERMINACIÓN
MANO DE OBRA:
1 MAESTRO DE OBRA
6 AYUDANTES
1
RETROEXCAVADORA
2 CAMION VOLTEO
COSTO:
$ 11,949.27
F E C H A
1 5 / 1 1 / 2 0 1 8
F E C H A
1 5 / 1 1 / 2 0 1 8
DESCRIPCIÓN.- A C A R R E O Y T E N D I D O D E
T I E R R A N E G R A PA R A S E N TA R L A P I S TA D E
H I E L O E N L A P L A Z A C E N T R A L Z O N A
C E N T R O .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
REPORTE FOTOGRÁFICO
104. NOVIEMBRE 2018
TITULO.- B AC H E O C O N C AR P E TA
C AL I E N T E E N AV E N I D A D E L A I N D U S T R I A.
FECHA INICIO FECHA
TERMINACIÓN
MANO DE OBRA:
1 MAESTRO DE OBRA
6 AYUDANTES
1 CAMION VOLTEO
COSTO:
$ 17,547.30
F E C H A
2 3 / 1 1 / 2 0 1 8
F E C H A
2 3 / 1 1 / 2 0 1 8
DESCRIPCIÓN.- B A C H E O C O N C A R P E T A
C A L I E N T E E N A V E N I D A D E L A I N D U S T R I A .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACION 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
REPORTE FOTOGRÁFICO
105. NOVIEMBRE 2018
TITULO.- R AS T R E O Y C O N F O R M AC I Ó N D E
V I AL I D AD A U N C O S TAD O D E AR T E L I V I A.
FECHA INICIO FECHA
TERMINACIÓN
MANO DE OBRA:
1 MAESTRO DE OBRA
1 AYUDANTES
1
MOTOCONFORMADO
RA
COSTO:
$ 5,013.73
F E C H A
2 9 / 1 1 / 2 0 1 8
F E C H A
2 9 / 1 1 / 2 0 1 8
DESCRIPCIÓN.- R A S T R E O Y C O N F O R M A C I Ó N
D E V I A L I D A D A U N C O S T A D O D E A R T E L I V I A P A R A
R A M P A D E A C C E S O A R U T A L A G U N A F L O R I D A .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
REPORTE FOTOGRÁFICO
106. NOVIEMBRE 2018
TITULO.- R AS T R E O Y C O N F O R M AC I Ó N D E
C O L . N U E V O M É X I C O .
FECHA INICIO FECHA
TERMINACIÓN
MANO DE OBRA:
1 MAESTRO DE OBRA
6 AYUDANTES
1
RETROEXCAVADORA
1
MOTOCONFORMADOR
A
1 CAMION VOLTEO
COSTO:
$ 12,919.70
F E C H A
2 0 / 1 1 / 2 0 1 8
F E C H A
2 0 / 1 1 / 2 0 1 8
DESCRIPCIÓN.- L I M P I E Z A G E N E R A L , R A S T R E O
Y C O N F O R M A C I Ó N D E C A L L E T A M A U L I P A S Y C A L L E
V I L L A H E R M O S A E N C O L . N U E V O M É X I C O .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
REPORTE FOTOGRÁFICO
107. NOVIEMBRE 2018
TITULO.- R AS T R E O Y C O N F O R M AC I Ó N E N
C O L . E M I L I AN O Z APATA .
FECHA INICIO FECHA
TERMINACIÓN
MANO DE OBRA:
1 MAESTRO DE OBRA
6 AYUDANTES
1
RETROEXCAVADORA
1
MOTOCONFORMADO
RA
1 CAMION VOLTEO
COSTO:
$ 12,919.70
F E C H A
2 4 / 1 1 / 2 0 1 8
F E C H A
2 4 / 1 1 / 2 0 1 8
DESCRIPCIÓN.- L I M P I E Z A G E N E R A L , R A S T R E O
Y C O N F O R M A C I Ó N D E C A L L E R E V O L U C I Ó N Y C A L L E
L A R E D O E N C O L . E M I L I A N O Z A P A T A .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
REPORTE FOTOGRÁFICO
108. NOVIEMBRE 2018
TITULO.- C H AP O L E O D E D R E N D E AV.
M O N T E R R E Y.
FECHA INICIO FECHA
TERMINACIÓN
MANO DE OBRA:
1 MAESTRO DE OBRA
6 AYUDANTES
COSTO:
$ 2,768.00
F E C H A
2 9 / 1 1 / 2 0 1 8
F E C H A
3 0 / 1 1 / 2 0 1 8
DESCRIPCIÓN.- C H A P O L E O C O N
H E R R A M I E N T A M A N U A L D E D R E N D E A V E N I D A
M O N T E R R E Y E N T R E B L V D . A L L E N D E Y C A L L E
F U N D O L E G A L .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
REPORTE FOTOGRÁFICO
109. NOVIEMBRE 2018
TITULO.- E X C AVAC I Ó N D E S AN G R I AS E N
D R E N P L U V I AL E N L AS H AC I E N D AS I I .
FECHA INICIO FECHA
TERMINACIÓN
MANO DE OBRA:
1 MAESTRO DE OBRA
5 AYUDANTES
COSTO:
$ 1,251.00
F E C H A
0 7 / 1 1 / 2 0 1 8
F E C H A
0 7 / 1 1 / 2 0 1 8
DESCRIPCIÓN.- E X C A V A C I Ó N D E S A N G R I A S
P A R A D R E N A D O D E D R E N P L U V I A L E N L A S
H A C I E N D A S I I .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACION 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
REPORTE FOTOGRÁFICO
110. NOVIEMBRE 2018
TITULO.- R A S T R E O D E V I AL I D A D E S D E L
T E L E B A C H I L L E R A T O E N E L E J I D O R I C AR D O
F L O R E S M AG Ó N .
FECHA INICIO FECHA
TERMINACIÓN
MANO DE OBRA:
1 MAESTRO DE OBRA
6 AYUDANTES
1
RETROEXCAVADORA
1
MOTOCONFORMADO
RA
2 CAMION VOLTEO
COSTO:
$ 16,497.00
F E C H A
0 7 / 1 1 / 2 0 1 8
F E C H A
0 7 / 1 1 / 2 0 1 8
DESCRIPCIÓN.- R A S T R E O Y C O N F O R M A C I Ó N
D E C A L L E S L A T E R A L E S A L T E L E B A C H I L L E R A T O
R I C A R D O F L O R E S M A G Ó N , R E P O S I C I Ó N D E
T U B E R I A D E P V C 4 " D E D R E N A J E D E S A L Ó N D E
A C T O S , C O R T E Y C O N F O R M A C I Ó N D E P A T I O ,
C A R G A Y A C A R R E O D E M A T E R I A L P R O D U C T O
D E C O R T E .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
REPORTE FOTOGRÁFICO
111. NOVIEMBRE 2018
TITULO.- B A C H E O E N C I R C U I T O
A R B O L E D A S D E L F R A C C I O N AM I E N T O V I L L A S
D E AL T A M I R A .
FECHA INICIO FECHA
TERMINACIÓN
MANO DE OBRA:
1 MAESTRO DE OBRA
6 AYUDANTES
1
RETROEXCAVADORA
1
MOTOCONFORMADO
RA
1 CAMIÓN VOLTEO
COSTO:
$ 12,919.70
F E C H A
2 3 / 1 1 / 2 0 1 8
F E C H A
2 3 / 1 1 / 2 0 1 8
DESCRIPCIÓN.- B A C H E O C O N C H A M P A Y A N
C A L I D A D B A S E M E J O R A D O C O N C A L E N
C I R C U I T O A R B O L E D A S D E L
F R A C C I O N A M I E N T O V I L L A S D E A L T A M I R A .
R. AYUNTAMIENTO DE ALTAMIRA
ADMINISTRACIÓN 2018-2021
DIRECCIÓN DE OBRAS PÚBLICAS
REPORTE FOTOGRÁFICO